bridge over bnsf railroad 7 km east of windham - east bridge replacement project using accelerated...

Post on 14-Dec-2015

219 Views

Category:

Documents

3 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Bridge over BNSF Railroad

7 km East of Windham - East

Bridge Replacement Project Using Accelerated Bridge Construction

Project Location

Existing Bridgeo 3-Span Concrete Tee Beamo 123 Feet Longo 28 Feet Wide

Approach Looking Southeast

Profile Looking Southwest

Design Parameterso National Highway Routeo 2500 vehicles per day (23% Trucks)o Major truck route between Great Falls and Billings o US Air Force Missile Routeo Grain Elevator in Moccasin o BNSF Railroad Crossingo Accident cluster at bridge

New Bridge Requirements

o New width = 40 feeto Increased railroad lateral clearanceo Increased railroad vertical clearanceo Avoid existing foundations (timber piles)o Minimize grade raise to catch slopes on

existing approaches – avoid sliver fills and new R\W

o Minimize traffic disruptions

What are our options?o New Bridge on Offset Alignment

o New Bridge on same alignment using On-site Detour

o New Bridge on same alignment using Phase Construction

o New Bridge on same alignment using Off-site detour and ABC

Could Accelerated Construction work

here??o How long can we shut down bridge site?o How quickly can we build a new bridge?o How much building can be completed before with

existing bridge in place?o Is there a reasonable detour route?

Possible detour route

o Secondary Highways – wide shoulders / flat slopeso Similar detour length for thru-traffico Detour through town of Hobson – school crossingo At-grade RR crossing in Hobsono Many local detours possible (County Roads)

o Contacts with o Town of Hobson - Mayoro Hobson Schoolo County Commissionerso Trucking Industry – grain elevatoro Air Force Baseo BNSF Railroad

o Road User Cost Calculationso Preliminary ABC Ideaso Contract Time Estimateso Local Events

ABC Planning Efforts

– Hay Days – Utica

Montana

What can we accelerate?What portion of construction takes the most time?

o Foundation construction – 4 days/shaft or 4 piles/day

o Drilled Shaft testing – 14 days before testing / longer if problems are encountered

o Forming bent caps – 3 days eacho Curing bent caps – 15 days per projecto Deck forming – 20 days up to 300 feeto Deck curing and sealing – 28 days

Allowing for some overlap……80 days for major items

Potential Solutionso Foundations

o What can we do while traffic is on existing bridge?o What foundation types will work?

o Forming and curing bent capso What cast-in-place can be done while traffic is on existing bridge?o Precast end and intermediate caps?

o Deck forming and curingo Full-depth precast deck panelso Partial-depth o Stay-in-place Forms

o What could be completed before detouring traffic

o What would be accelerated while traffic is on detour route

o What work could be done after traffic is moved back on new bridge

Divided Work Into Stages

Work Prior to Detouring Traffic

Drilled 4 shafts outside the bridge limits and behind the existing intermediate bents.

Cast struts/crash wall on top of and between shafts

Cast walls on top of struts

Traffic on DetourDay 1o Removed span 2 deck and beamso Removed span 3 deck

Day 2o Removed span 3 beamso Removed bent 3 and 4o Removed span 1 deck

Day 3o Bent 4 – drove piles, formed and placed capo Bent 3 – Set cap and placed closureo Removed span 1 beamso Removed bents 1 and 2

Precast Pier Cap

Day 4o Bent 2 – Set cap o Bent 1 – drove piles

Day 5o Bent 2 – placed closureo Bent 4 –formed and placed cap

Day 6o Span 3 – Set girders and deck panels

Day 7o Sunday – no work

Day 8o Span 2 – Set girders and deck panels

Day 9o Span 1 – Set girders and half the deck panels

Day 10o Span 1 – Set remaining deck panelso Began forming closure pours

Day 11o Bents 1 & 4 – Formed and placed backwallso Formed deck panel closure pours

Day 12o Continued forming deck panel closure pours

Day 13 and 14o Saturday and Sunday – No work

Day 15o Adjusted deck gradeso Prepare for deck closure pours

Day 16 and 17 o UHPC Closure Pours

Day 18 and 19o Removing form work and grinding jointso Fill low spots

Day 20 and 21o Weekend no bridge work – building approach fills

Day 22o More grinding and approach fills

Day 23o Tying barrier steel o Test run with slip form

Day 24 o Approach work

Day 25o Slip formed barrierso Final grading along RR tracks

Day 26 and 27o More grading worko Approach rails

Day 28o Finished approach rails

Day 29 o Opened to Traffic

One day ahead of schedule (incentive/disincentive deadline)

Now lets see that in fast motion

Lessons Learned

o Project scheduling was intensiveo Design details are critical – things need to fito Allow adequate tolerance on precast elementso UHPC is difficult to grind – reduce exposed area to

minimize grindingo Have an Engineer on site during construction of

critical elements – be prepared to make decisions

Questions??

Project Contact: Jeff Olsen

jolsen@mt.gov406-444-7610

top related