1Baltimore County Public Schools
Schematic Design Presentation
Catonsville Elementary School
at Bloomsbury1104 Kenilworth Dr.Suite 500Towson, MD 21204(410) 337-2886fax (410) 337-2974
www.rubeling.com
© 2014
2Aerial Location View
© 2014
3
Current C.E.S. Proposed C.E.S.Site 6.16 acres 11.8 acres
SRC 405 700
Current Enrollment 445
Bus Loop 2 8
Parking 68 150
Building Size 59,600 sf 103,000 sf
Historic Structure Yes Yes
Original Construction 1909 1925
Additions 1929, 1934, 1970 1930-1962 (additions removed 1990)
Converted to County Building N/A 1980’s
Current Use Elementary School Bureau of Elections Recreation & Park
Overview and Comparison Existing Catonsville E.S. & Proposed Catonsville E.S. at Bloomsbury
© 2014
4Existing Bloomsbury Site
1990’s Gymnasium
1930’s Building
© 2014
5EXISTING SITE PHOTOS
1990’s Gymnasium
1930’s Building
© 2014
6Site & Grading Plan
ENTRY
ENTRY
© 2014
7
• Restore Historic Features of the Original 1925 Building
• Interior Renovation and Addition to Convert Building to a New 21st Century Learning Facility
• Incorporate Facility Upgrades to Support the Instructional Environment for Students
• Provide All New Building Systems
• Provide Building Security and Address Student Safety
• Address all Code, ADA and Life Safety Issues
Project Objectives
© 2014
8GROUND FLOOR
1ST GRADECLASSROOMS (TYP)
KINDERGARTEN
PARENT DROP OFF
PRE-K
GROUND FLOOR
© 2014
9GROUND FLOOR
GROUND FLOOR
STAIRS (TYP)
ELEVATOR
© 2014
10FIRST FLOOR
CLASSROOMS (TYP)
MEDIA CENTER
ENTRY
MAIN FLOOR
© 2014
11FIRST FLOOR
MAIN FLOOR
STAIRS (TYP)
ELEVATOR
© 2014
12SECOND FLOOR
CLASSROOMS (TYP.)
SECOND FLOOR
© 2014
13
Curriculum:
•The building interior will be new and designed to current curriculum and building standards and will meet BCPS and State of Maryland’s Standard for Technology.
Building Envelope Improvements:
•Replace existing roof.
Code Improvements:
•Install elevator to access all levels.•All new doors and hardware to be in compliance with current code.•New restrooms to comply with ADA guidelines.
MEP System Improvements:
•New mechanical system to all year round climate control thru central heating and cooling.•New lights to meet BCPS standards and building code.•New light controls.•New intercom and clock system.
Summary of Improvements
© 2014
14BUILDING ELEVATIONS
© 2014
15BUILDING ELEVATIONS
© 2014
16BUILDING ELEVATIONS
© 2014
17BUILDING ELEVATIONS
© 2014
18BUILDING ELEVATIONS
© 2014
19BUILDING ELEVATIONS
© 2014
20BUILDING ELEVATIONS
© 2014
21BUILDING ELEVATIONS
© 2014
22Project Schedule
Design March 2014 - February 2015
Bid & BCPS Board Meeting February 2015 - April 2015
Construction May 2015 - July 2016
Opening August 2016
© 2014