Audi, Sytner Group LtdBradford, UK

the complete construc tion company

“A new car dealership, with service and repair workshop”

“A new car dealership, with service and repair workshop”

The design and construction of a New

Car Dealership with service and repair

workshop and valet cleaning.

The site was previously part of Bradford

Gas Works, its part remediation was

carried out in 2004. The three plotted

site required the full remediation for

the construction of the dealership and

the connecting Estate Road.

The plot is divided by the Bradford

Beck, the culvert cover formed the

basis of the building design, with

showroom and workshop constructed

on opposting sides of the Beck bridging

with the covered drive through.

Audi, Sytner Group Ltd.

“Two storey office, and welfare accommodation”

Start Date | September 2007

Duration | 36 Weeks

Completion Date | July 2008

Project Value | £7m

Client Details | Sytner Group HQ

2.4 Hectares of development

363m2 showroom display area

732m2 workship, 16 working bays & one MOT station

258m2 drive through drop off area

242m2 valet facilities

Two Storey office and welfare accommodation

Key Features

Statistics