2104251I N T R O D U C T I O N T O
M A N U F A C T U R I N G S Y S T E M S
C H A P T E R 1 0 :
P R O J E C T M A N A G E M E N T
1
P R O J E C T M A N A G E M E N T D E F I N E D
2
Project is a series of related jobs usually directed toward some major output and requiring a significant period to perform
Project Management are the management activities of planning, directing, and controlling resources (people, equipment, material) to meet the technical, cost, and time constraints of a project
S O M E N E C E S S A R Y T E R M S
3
Statement of the work: A written description of the objectives to be achieved.
Task and subtask: A task is a further subdivision of the project.
Work package: A group of activities combined to be assignable to a single organizational unit.
Milestones: Specific events to be reached at points in time.
4
W O R K B R E A K D O W N S T R U C T U R E
• A work breakdown structure defines the hierarchy of project tasks, subtasks, and work packages
Program
Project 1 Project 2
Task 1.1
Subtask 1.1.1
Work Package 1.1.1.1
Level
1
2
3
4
Task 1.2
Subtask 1.1.2
Work Package 1.1.1.2
5
G A N T T C H A R T
Activity 1Activity 2Activity 3Activity 4Activity 5Activity 6
Time
Vertical Axis: Always Activities or Jobs
Horizontal Axis: Always Time
Horizontal bars used to denote length of time for each activity or job.
6
G A N T T C H A R T: E X A M P L E20 4 106 8
31 5 7 9Month
Month
½ ½ ½ ½ ½
½ ½ ½ ½ ½
Activity
Design house andobtain financing
Lay foundation
Order and receivematerials
Build house
Select paint
Select carpet
Finish work
O R G A N I Z A T I O N A L S T R U C T U R E S• It determines the relation between the project and the parent firm.
• Pure project
• Functional project
• Matrix project
7
P U R E P R O J E C T
8
A PURE PROJECT IS WHERE A SELF-CONTAINED TEAM WORKS FULL-
TIME ON THE PROJECT
EQUIPMENT AND PEOPLE ARE NOT SHARED ACROSS PROJECTS.
A D V A N TA G E S
9
The project manager has full authority over the project
Team members report to one boss
Shortened communication lines
Team pride, motivation, and commitment are high
D I S A D V A N T A G E S
10
Duplication of resources.
Organizational goals and policies are ignored.
Lack of technology transfer.
Team members have no functional area "home."
11
F U N C T I O N A L P R O J E C T
President
Research and development
Engineering Manufacturing
Project Project Project
A B C
Project Project Project
A B C
Project Project Project
A B C
A D V A N TA G E S
12
A team member can work on several projects
Technical expertise is maintained within the functional area
The functional area is a “home” after the project is completed
Critical mass of specialized knowledge
D I S A D V A N T A G E S
13
Aspects of the project that are not directly related to the functional area get short-changed.
Motivation of team members is often weak.
Needs of the client are secondary and are responded to slowly.
A D V A N TA G E S
15
Enhanced communications between functional areas
Pinpointed responsibility
Duplication of resources is minimized
Functional “home” for team members
Policies of the parent organization are followed
D I S A D V A N T A G E S
16
Too many bosses
Depends on project manager’s negotiating skills
Potential for sub-optimization
N E T W O R K P L A N N I N G
M O D E L S
17
A project is made up of a sequence of activities that form a network representing a project
The path taking longest time through this network of activities is called the “critical path”
The critical path provides a wide range of scheduling information useful in managing a project
Critical Path Method (CPM) helps to identify the critical path(s) in the project networks
E L E M E N T S O F
P R O J E C T P L A N N I N G
18
Define project objective(s)
Identify activities
Make time estimates
Determine project completion time
Determine resource requirements to meet objective
N E T W O R K C O N S T R U C T I O N
20
Nodes can be used to represent activities & events for points in time
Arrows represent activities & show precedence relationships
An event is the completion or beginning of an activity
21
P R E R E Q U I S I T E S F O R C P MA project must have:
• well-defined jobs or tasks whose completion marks the end of the project;
• independent jobs or tasks;
• and tasks that follow a given sequence.
T Y P E S O F C P M
22
CPM with a Single Time Estimate• Used when activity times are known with certainty• Used to determine timing estimates for the project,
each activity in the project, and slack time foractivities
CPM with Three Activity Time Estimates• Used when activity times are uncertain• Used to obtain the same information as the Single
Time Estimate model and probability information
Time-Cost Models• Used when cost trade-off information is a major
consideration in planning• Used to determine the least cost in reducing total
project time
23
S T E P S I N T H E C P M W I T H S I N G L E T I M E E S T I M A T E D1. Activity Identification
2. Activity Sequencing and Network Construction
3. Determine the critical path
• From the critical path all of the project and activity timing information can be obtained
24
C P M W I T H S I N G L E T I M E E S T I M A T EConsider the following consulting project:Activity Designation Immed. Pred. Time (Weeks)Assess customer's needs A None 2Write and submit proposal B A 1Obtain approval C B 1Develop service vision and goals D C 2Train employees E C 5Quality improvement pilot groups F D, E 5Write assessment report G F 1
Develop a critical path diagram and determine theduration of the critical path and slack times for allactivities.
25
E X A M P L E 1 : F I R S T D R A W T H E N E T W O R K
Designation Immes. Pred. Time (weeks)
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
G F 1
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
E A R L Y T I M E S
26
ES - earliest time activity can start
Forward pass starts at beginning of CPM network to determine ES times
EF = ES + activity time
L A T E T I M E S
27
LF - latest time activity can finish & not delay project
Backward pass starts at end of CPM network to determine LS times
LS = LF - activity time
29
E X A M P L E 1 : D E T E R M I N E E A R L Y S T A R T A N D E A R L Y F I N I S H T I M E S
ES=9EF=14
ES=14EF=15
ES=0EF=2
ES=2EF=3
ES=3EF=4
ES=4EF=9
ES=4EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
Hint: Start with ES=0 and go forward in the network from A to G.
30
E X A M P L E 1 : D E T E R M I N E L A T E S T A R T A N D L A T E F I N I S H T I M E S
LS=4LF=9
ES=9EF=14
ES=14EF=15
ES=0EF=2
ES=2EF=3
ES=3EF=4
ES=4EF=9
ES=4EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
LS=14LF=15
LS=9LF=14
LS=7LF=9
LS=3LF=4
LS=2LF=3
LS=0LF=2
Hint: Start with LF=15 or the total time of the project and go backward in the network from G to A.
31
E X A M P L E 1 : C R T I C A L P A T H A N D S L A C K
ES=9EF=14
ES=14EF=15
ES=0EF=2
ES=2EF=3
ES=3EF=4
ES=4EF=9
ES=4EF=6
A(2) B(1) C(1)
D(2)
E(5)
F(5) G(1)
LS=14LF=15
LS=9LF=14
LS=4LF=9
LS=7LF=9
LS=3LF=4
LS=2LF=3
LS=0LF=2
Duration=15 weeks
Slack=(7-4)=(9-6)= 3 Wks
32
C P M W I T H T H R E E A C T I V I T Y T I M E E S T I M A T E S• Reflects uncertainty of activity times
a = optimistic estimatem = most likely time estimateb = pessimistic time estimate
where,
Mean (expected time): ETa + 4m + b
6=
22 )6
a -b( = sVariance:
33
P R O B A B I L I S T I C N E T W O R K A N A LY S I SDetermine probability that project is completed within specifiedtime
where
TE = Expected completion time from CPM network
σ = project standard deviation along critical path
D = Desired completion date
Z = number of standard deviations D is from mean
Z = D - TE
cp2så
34
E X A M P L E 2 : C P M W I T H T H R E E A C T I V I T Y T I M E E S T I M A T E S
TaskImmediate
Predecesors Optimistic Most Likely PessimisticA None 3 6 15B None 2 4 14C A 6 12 30D A 2 5 8E C 5 11 17F D 3 6 15G B 3 9 27H E,F 1 4 7I G,H 4 19 28
35
E X A M P L E 2 : E X P E C T E D T I M E C A L C U L A T I O N
ET(A)= 3+4(6)+15
6
ET(A)=42/6=7Task
Immediate Predecesors
Expected Time
A None 7B None 5.333C A 14D A 5E C 11F D 7G B 11H E,F 4I G,H 18
TaskImmediate
Predecesors Optimistic Most Likely PessimisticA None 3 6 15B None 2 4 14C A 6 12 30D A 2 5 8E C 5 11 17F D 3 6 15G B 3 9 27H E,F 1 4 7I G,H 4 19 28
Expected Time = Opt. Time + 4(Most Likely Time) + Pess. Time
6
36
E X A M P L E 2 : T H E N E T W O R K
A(7)
B(5.333)
C(14)
D(5)
E(11)
F(7)
H(4)
G(11)
I(18)
Duration = 54 Days
37
E X A M P L E 2 : P R O B A B I L I T Y E X E R C I S EWhat is the probability of finishing this project in less than 53 days?
Z = D - TE
cp2så
p(t < D)
TE = 54t
D=53
38
E X A M P L E 2 : V A R I A N C E
Activity variance, = (Pessim. - Optim.
6)2 2s
Task Optimistic Most Likely Pessimistic VarianceA 3 6 15 4B 2 4 14C 6 12 30 16D 2 5 8E 5 11 17 4F 3 6 15G 3 9 27H 1 4 7 1I 4 19 28 16
(Sum the variance along the critical path.) s 2å = 41
39
E X A M P L E 2 : C O N C L U S I O N
There is a 43.8% probability that this project will be completed in less than 53 weeks.
p(Z < -.156) = .438, or 43.8 % (NORMSDIST(-.156))
Z = D - T
=53- 54
41= -.156E
cp2så
TE = 54
p(t < D)
tD=53
40
E X A M P L E 2 . 5 : W H A T I S T H E P R O B A B I L I T Y O F F I N I S H I N G T H I S P R O J E C T I N L E S S T H A N 5 6 D A Y S ?
tTE = 54
p(t < D)
D=56
Z = D - T
=56 - 54
41= .312E
cp2så
p(Z > .312) = .378, or 37.8 % (1-NORMSDIST(.312))
41
T I M E A N D C O S T M O D E L S• Basic Assumption: Relationship between activity completion time and project cost.
• Time Cost Models: Determine the optimum point in time-cost tradeoffs.
• Activity direct costs
• Project indirect costs
• Activity completion times
42
C O S T R E L A T E D T O P R O J E C T S• Project direct costs: cost associated with expediting the project
• Project indirect costs: cost associated with sustaining the project.
43
P R O J E C T C R A S H I N G• Crashing is reducing project time by expending additional resources
• Crash time is an amount of time an activity is reduced
• Crash cost is the cost of reducing the activity time
• Goal is to reduce project duration at minimum cost
44
E X A M P L E 3 : H O U S E B U I L D I N G N E T W O R K
1 2 4 6 7
3
5
12
80
4
12
44
4
Design house and obtain financing
Lay foundation
Order and receive materials
Select paint
Select carpet
Finish workBuild
house
Dummy
45
N O R M A L A C T I V I T Y A N D C R A S H D A T A
1-2 12 7 $3,000 $5,000 5 $400
2-3 8 5 2,000 3,500 3 500
2-4 4 3 4,000 7,000 1 3,000
3-4 0 0 0 0 0 0
4-5 4 1 500 1,100 3 200
4-6 12 9 50,000 71,000 3 7,000
5-6 4 1 500 1,100 3 200
6-7 4 3 15,000 22,000 1 7,000
$75,000 $110,700
TotalNormal Crash Allowable CrashTime Time Normal Crash Crash Time Cost per
Activity (wks) (wks) Cost Cost (wks) Week
46
E X A M P L E 3 : N E T W O R K W I T H C R A S H I N G C O S T• Activity 1-2 can be crashed a total of 5 weeks for $2000
• Crash cost per week = Total crash cost/Total crash time= $2,000/5 = $400 perweek
1 2 4 6 7
3
5
128 0
412
4 4
4
$7,000$7,000
$500
$3,000$400
$200 $200
47
N O R M A L A N D C R A S H R E L A T I O N S H I P S
1242 6 8 10 140
1,000
3,000
4,000
5,000
7,000
2,000
6,000
$
Weeks
Crashed activity
Normal activity
Crash cost
Normal cost
Crash time Normal time
Slope = crash cost per week
48
C R A S H I N G S O L U T I O N
1-2 12 7 5 $400 $2,000
2-3 8 5 3 500 1,500
2-4 4 3 0 3,000 0
3-4 0 0 0 0 0
4-5 4 1 0 200 0
4-6 12 9 3 7,000 21,000
5-6 4 1 0 200 0
6-7 4 3 1 7,000 7,000
12 $31,500
Normal Crash Crash Crash CrashingTime Time Time Cost per Cost
Activity (wks) (wks) Used Week Incurred
49
C R A S H E D P R O J E C T
1 2 4 6 7
3
5
12 7
8 5
0
4 3
12 9
4 4
4 3
Original time Crashed times
A S S I G N M E N T # 1• Find Critical Path
• Find the project expected completion days
• Company will be paid 5.4 Millions for this project
• $150,000 bonus for finishing within 40 weeks
• $300,000 penalty for not finishing within 47 weeks
• What is the least expensive way of crashing some activities to reduce the project duration to 40 weeks
50
I N F O # 1
51
ActivityImmediat
e Predecess
ors
Time (Weeks)
a m b
A - 1 2 3B A 2 3.5 8C B 6 9 18D C 4 5.5 10E C 1 4.5 5F E 4 4 10G D 5 6.5 11H E,G 5 8 17I C 3 7.5 9J F,I 3 9 9K J 4 4 4L J 1 5.5 7M H 1 2 3N K,L 5 5.5 9
I N F O # 2
52
Activity
Time (Weeks) Cost
Normal Crash Normal Crash
A 2 1 ฿180,000.00 ฿ 280,000.00
B 4 2 ฿320,000.00 ฿ 420,000.00
C 10 7 ฿620,000.00 ฿ 860,000.00
D 6 4 ฿260,000.00 ฿ 340,000.00
E 4 3 ฿410,000.00 ฿ 570,000.00
F 5 3 ฿180,000.00 ฿ 260,000.00
G 7 4 ฿900,000.00 ฿1,020,000.00
H 9 6 ฿200,000.00 ฿ 380,000.00
I 7 5 ฿210,000.00 ฿ 270,000.00
J 8 6 ฿430,000.00 ฿ 490,000.00
K 4 3 ฿160,000.00 ฿ 200,000.00
L 5 3 ฿250,000.00 ฿ 350,000.00
M 2 1 ฿100,000.00 ฿ 200,000.00
N 6 3 ฿330,000.00 ฿ 510,000.00
A S S I G N M E N T # 2• Ken Johnston, The data processing manager for Stanley Morgan Bank, is planning aproject to install a new management information system. He now is ready to start theproject, and wishes to finish in 20 weeks. After identifying the 14 separate activitiesneeded to carry out this project, as well as their precedence relationships andestimated durations (in weeks).
53
54
Activity Immediate Predecessors Estimated Duration Estimated CostA - 6 ฿ 180,000.00
B - 3 ฿ 75,000.00
C - 4 ฿ 120,000.00
D A 4 ฿ 140,000.00
E B 7 ฿ 175,000.00
F C 4 ฿ 80,000.00
G C 6 ฿ 210,000.00
H D 3 ฿ 45,000.00
I A 5 ฿ 125,000.00
J E 4 ฿ 100,000.00
K F 3 ฿ 60,000.00
L G 5 ฿ 50,000.00
M H,I,J 6 ฿ 90,000.00
N K,L 5 ฿ 150,000.00
Q U E S T I O N S• Find Critical Path
• Find the earliest time, latest time, slack. Will he meet the deadline?
• Which activities he should focus more on?
• What if one of these activities delay by 2 weeks, I H, and J?
• Calculate the budget and schedule based on earliest/latest starttime
• What are the focused activities?
55
A LT E R N A T I V E S Q U E S T I O N S• After 8 weeks, activities A, B, and C have been completed
with actual costs of $190,000, $70,000, and $150,000,respectively. Activities D, E, F, G, and I are under way, with thepercent completed being 40,50, 60, 25, and 20 percent,respectively. Their actual costs to date are $70000, $100000,$45000, $50000, and $35000, respectively. Construct aPERT/Cost report after week 8. Which activities should Keninvestigate to try to improve their performances
56