amendment no. 7 to the agreement between owner and
TRANSCRIPT
Amendment No. 7 to the Agreement between Owner and Construction Manager
Pursuant to Paragraph 2.2 of the Agreement, dated December 15, 2018 between The School Board ofSeminole County, Florida {Owner) and Charles Perry Partners Inc. {Construction Manager), for theLyman High School, Elevator Refurbishment Project, the Owner and Construction Manager establish aGuaranteed Maximum Price and Contract Time for the Work as set forth below.
ARTICLE I
GUARANTEED MAXIMUIVl PRICE
The Construction Manager's Guaranteed Maximum Price for the Work, including the estimated Cost ofthe Work as defined in Article 6 and the Construction Manager's Fee as defined in Article 5, is: OneHundred Forty Nine Thousand, Eight Hundred Thirty One Dollars and Zero Cents. ($149,831.00).
This Price is for the performance of the Work in accordance with the contract Documents listed andattached to this Amendment and marked Exhibit A. as follows:
Exhibit "A" Charles Perry Partners Inc. GMP Proposal Dated September 20, 2019
ARTICLE II
CONTRACT TIME
Work is to commence on October 10, 2019, and be substantially completed on February 21, 2020, withfinal completion on March 20. 2020. Liquidated Damages are set at: Two hundred dollars ($200) percalendar day for failure to complete the project as stated herein.
THE SCHOOL BOARD OF SEMINOLE
COUNTY, FLORIDA
Tina Calderone, Ed.D., Board Chair
Wall Griffin. Ed.D., Superintendent
Date:
Charles Perry^Partners I
Jasor^org^. Vi^e President
essea
GMP Estimate
SCPS Lyman HS Elevator
Charles Perry Partners Inc Page 1
9/20/2019
Sub Cost/Unit Sub Amount Sub Name Total AmountD'escri^Ton f Takeoff Quantity Ji:ELEVATORS, LIFTS
Elevator Subcontract 1.00 1s
ELECTRICAL
Electrical Work 1.00 1s
STAFFING
Staff Cost 3.00 wk
GENERAL REQUIREMENTS
General Conditions 3.00 wk
94.21414-00-90.00 94,214.00 /Is 94,214 Skyline Elevator
22,53926-00-90.00 22,539 TECC Electric22,539.00 /Is
11.370 CPP 11,37001-11-00.00 3,790.00 /wk
01-11-00.00 560.67 /wk 1,682 CPPI
Charles Perry Partners Inc
Estimate Totals
Description AmountProfit/Overhead 13,630
subtotal fee 13,630
construction contingency 5,000
subtotal contingencies 5,000builder's risk inland 569
general liability 03.09.2016 827subtotal ins, bonding 1,396
Total
GMP Estimate
SCPS Lyman HS Elevator
Totals Hours
143,435
148,435
149,831
149,831
Rate
10.500 %
0.380 $/ 100
5.520 $/ 1,000
Page 2
9/20/2019
Cost Basis cost per unit Percent of Total
TECCElectrical Contractors333 S. SR 415 • Ostccn, PL 32764
Phone: (407) 330-2900 • Fax: (407) 330-2939
PROPOSAL
CUSTOMER
CHARLES PERRY PARTNERS, INC.200 E. PALM VALLEY DRIVE
OVIEDO.FL 32765
DATE PROPOSAL#
9/12/2019 8192
PROJECT
LYMAN HIGH SCHOOL
865 S. CR 427
LONGWOOD, PL 32750
DESCRIPTION TOTAL
LYMAN HIGH SCHOOL BUILDING 7 ELEVATOR RENOVATIONS
PROPOSAL BASED ON SITE WALK-THROUGH
PROPOSAL INCLUDES:
- FURNISH AND INSTALL (3) SMOKE DETECTORS AS FOLLOWS: (1) AT 1 ST FLOOR ELEVATORLANDING; (I) AT 2ND FLOOR ELEVATOR LANDING; AND (1) IN ELEVATOR MACHINE ROOM
- FURNISH AND INSTALL (1) 60 AMP DISCONNECT IN ELEVATOR EQUIPMENT ROOM WITH WO AND N/CCONTACTS
- RELOCATE EXISTING ELEVATOR PIT LIGHT TO OPPOSITE CORNER OF CURRENT LOCATION ANDREPLACE LAMP WITH HIGH WATTAGE LED LAMP
- REPLACE DUPLEX RECEPTACLE WITH NEW OFCI RECEPTACLE AND REPLACE
SWITCH WITH NEW SWITCH UNDER RAISED SURFACE COVER
- REMOVE EXISTING SIMPLEX RECEPTACLE AND REPLACE WITH DUPLEX RECEPTACLE AND RAISEDSURFACE COVER
- FURNISH AND INSTALL (3) RELAYS INSIDE ELEVATOR MACHINE ROOM- FURNISH AND INSTALL (3) NEW I' X 4' LED WRAP AROUND FIXTURES IN ELEVATOR FXJUIPMENT ROOM- FIRE ALARM PERMIT APPUCATION AND FIRE ALARM ENQINEER STAMP
PROPOSAL NOTES:
- IN THE EVENT THIS WORK IS TO BE SUPERVISED UNDER THE ENGINEER OP RECORD. ALL ADDITIONALCOSTS TO BE PAID BY OTHERS
- A COPY OF THE EXISTING B8T 3 FIRE ALARM CONTROL SYSTEMS DATABASE AND PASSWORDINFORMATION TO BE PROVIDED BY OTHERS FOR PROGRAMMING CHANGES
THIS PROPOSAL MAY BE WITHDRAWN IF NOT ACCEPTED WmilN 30 DAYS.
PROPOSAL ACCEPTED BY: TOTAL
Page 1 Page 17
TECCElectrical Contractors333 S. SR 415 • Osteen, FL 32764
Phone: (407) 330-2900 • Fax: (407) 330-2939
PROPOSAL
CUSTOMER
CHARLES PERRY PARTNERS. INC.200 E. PALM VALLEY DRIVEOVIEDO, PL 32765
DATE PROPOSAL#
9/12/2019 8192
PROJECT
LYMAN HIGH SCHOOL
865 S.CR427
LONGWOOD.FL 32750
DESCRIPTION
■ AS THE CURRENT SYSTEM WAS IN TROUBLE ATTIMB OF SITE VISIT AND PROGRAMMING CHANGESARE INCLUDED. A (10) PERCENT TEST OF EXISTING SYSTEM WILL BE PROVIDED PIUOR TO RENOVATIONAND AFTER DEVICE INSTALLATION COMPLETION
- A FULL TEST OF THE SYSTEM CAN BE PROVIDED AT AN ADDITIONAL COST. COMPLETE RACEWAYS FOR FIRE ALARM CABLING CAN BE PROVIDED AT AN ADDITIONAL COST. IN EVENT FULL SHOP DRAWINGS ARE REQUIRED, THIS SERVICE CAN BE PROVIDED AT ADDITIONALCOST
EXCLUSIONS:
- AFTER HOURS / OVERTIME
■ DAVIS BACON WAGES
PROPOSED COST
TOTAL
22,539.00
TIUS PROPOSAL MAY BE WITHDRAWN IF NOT ACCEPTED WITHIN 30 DAYS.PROPOSAL ACCEPTED BY: TOTAL $22,539.00
SIGNATURE
Page 2 Page 18
Material Breakdown
ControBer MCE $5,196.19 $5,196.19
Pump Unit MEi $4,788.81 $4,78881
Piping $5.34 $26.72
Hydraulic on $415.70 $83139
Vies $29.69 $118.77
Pit Stop Switches $22.57 $2237
Holstway Wiring SO $1.66 $83.14
Traveling Cable Draka 50 $10.81 ^4040
iamb Tags $10.87 $4347
Kellum Grips $35,63 $7136
Door Operator GAL $1,575.82 $137532
Car Door Track/Header GAl $118.65 $11835
Infrared Detector TrfTronics $497.05 $49735
HW Door Tracks GAL $61.57 $123.14
Interlocks GAL $92.36 $184.71
Closers GAL $40.41 $8031
6U» GAL ' • $4.45 $26.72
Spacer 3/4' MO Roller Release GAL $37.84 $75.61
Clutch GAL $394.44 $39444
COP Innov $3,983.14 $3,983.14
Car lantern Innov $155.15 $155.15
Hall Fixtures Bottom T^lnal Innov $1,088.85 $138835
Halt Fixtures Top Terminal Innov $455.40 $45540
Rath Junction Board innov $2L30 $2130
Car Top Inspection Station Quality $156.85 $15835
Car Top Fan Quality $106.89 $10638
Paint $118.77 $118.77
Code Data Plate $53.45 $5345
Sundries 1 $2,007.95 $230735
Inspections 1 $400.00 $40030
Total Material $2334949
lOX Markup per contract terms $2,33435
Subcontractor $16490.00
Cab Work $830030
Subtotal $50,67444
Labor Lead Disc Rate for 2ndTech Ttvo Person Tocii TlrnelHoun) labor Cost
Per contract Terms Sieojx) $9000 S27aoo 16Ue $43,539.00
Grand Total $94,213.44
Page 16