Hugh Kennedy 16 th July 2013 Alstom CFB boilers achieve high combustion efficiency with challenging discarded coal

Upload: others

Post on 30-Mar-2020

11 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

Hugh Kennedy

16th July 2013

Alstom CFB boilers achieve high combustion efficiency with challenging discarded coal

Page 2: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Agenda

Baima 300 MWe CFB demonstration plant Page 3

Emile Huchet 125 MWe captive power plant Page 9

Seward 2 x 260 MWe Page 13

Conclusion Page 16

Page 3: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Baima 300 MWel CFB Demonstration Plant

• Technology CFB

• Fuel Anthracite

• Province Sichuan, P.R.C.

• Capacity 1025 t/h

• MS Pressure 174 bar

• MS/HR Temperature 540/540°c

• FW Temperature 281°C

• Sulphur removal rate 94%

• Emissions level, mg/Nm3 (@6%O2 DG) :

• SO2 600

• NOx 250

• Dust 100

First 300 MW CFB Boiler in China

Page 4: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Baima 300 MWel CFB Demonstration Plant

Milestones

• Contract signed July 2002

• Contract into effect April 2003

• Commercial operation April 2006

• Performance tests May 2007

Technical challenges

• Carbon burnout with anthracite

• Limestone consumption

• Potential uncontrolled SO2: 10 000 mg/Nm3

• Sulphur removal rate 94%

• Added Ca/S < 2

Owner: Sichuan Baima CFB Demonstration Power Plant Co Ltd. ( State Power Grid / Sichuan Bashu Development Company)

The Baima Project also includes a ToT for CFBs 200-350 MWel

Page 5: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Baima performance tests BECR Perf test 1 BECR Perf test 2 Design

Date 26th June 2007 27th June 2007 BECR

Coal quality stability Good Good Good

Coal LHV MJ/kg 15.38 16.49 18.5

Ash % 43.5 40.5 35.3

LHV boiler efficiency % (corr) > 93 > 93 < 92

Added Ca/S (corr) < 1.5 < 1.7 < 2.0

Sulfur capture % > 95 > 94 > 94

SO2 emission mg/Nm3 @6% O2 dry < 600 < 600 600

CO emission mg/Nm3 @6% O2 dry < 150 < 130 NA

NOx emission mg/Nm3 @6% O2 dry < 100 < 100 250

Baima 300 MWel CFB Demonstration Plant

Trial run April 17th 2006, performance tests May and June 2007

Successful performance tests with the worst coal

Carbon heat loss < 3% LHV carbon content in fly ash: 1.5 – 2.5%.

Page 6: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

250

300

350

400

450

500

550

07:12 08:24 09:36 10:48 12:00 13:12 14:24 15:36 16:48 18:00

Hours

Re

he

at

ste

am

Te

mp

. °C

LTR inlet temp

HTR Bed 4 inlet temp

HTR Bed 1 inlet temp

HTR Bed 4 Outlet temp

HTR Bed 1 Outlet temp

HTS outlet temp

760

780

800

820

840

860

880

900

920

940

960

07:12 08:24 09:36 10:48 12:00 13:12 14:24 15:36 16:48 18:00

Hours

°C

Cyclone 301 outlet temp

Cyclone 201 outlet temp

~70% MCR 40% MCR

Baima 300 MWel CFB Demonstration Plant

0

50

100

150

200

250

09:36 10:48 12:00 13:12 14:24 15:36

Hours

mg

/Nm

3

Flue gas to stack CO

Flue gas to stack NOX

Gross Output Power

~70% MCR

40% MCR

80 mg/Nm3

50 mg/Nm3

Sup

er /

Reh

eat

stea

m °

C 550

500

450

400

360

300

Cyc

lone

ful

e ga

s °C

960

940

920

900

880

860

840

820

800

780

760

time

time

CO emission

NOx < 100 mg/Nm3

time

250

200

150

100

50

0

Load variation from ~70% to 40% MCR:

• MS and HR temperatures close to full-load value

• Combustion temperature remains above 860°C

• CO emission drops from 80 to 50 mg/Nm3

• NOx emission remains below 100 mg/Nm3

Page 7: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Baima 300 MWel CFB Demonstration Plant

Automatic boiler control despite coal quality variations

ash content 40 % to +60%

35% fuel flow reduction within 1 hour at constant output

Page 8: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

• Ash content > 45% (out of the contractual range) • Large amount of stones in the raw coal • Very abrasive ash

• Rapid wear of secondary crusher hammers • Required coal PSD never achieved • Oversized particles including stones

Coal quality the real challenge

• Stone build-up in the FBACs impacts heat transfer • Erosion of water walls above the refractory tip • Erosion of nozzles in the furnace

Baima 300 MWel CFB Demonstration Plant

Page 9: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Agenda

Baima 300 MWe CFB demonstration plant Page 3

Emile Huchet 125 MWe captive power plant Page 9

Seward 2 x 260 MWe Page 13

Conclusion Page 16

Page 10: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

• Customer: SODELIF, France • Fuel:

• Coal washing plants byproduct • Ultra fine product: d50% =150 microns, d99% < 2 mm • Slurry :

• 30% ash • 33% moisture • 2500 Kcal/Kg (LHV)

• Schlamms: • 8% moisture, • 5000 Kcal/kg (LHV)

• Steam Conditions: 367 t/h, 155 bar, 545/540°C • Emission levels (mg/Nm3 @6%O2 DG):

• SO2: 330 • NOx: 300

CFB-based power plant to burn low grade coal residues

Emile Huchet 125 MWel CFB boiler

Page 11: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Cyclones were designed to achieve the highest collection efficiency

Emile Huchet 125 MWel CFB boiler

Test facility ( France)

Page 12: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

0

10

20

30

40

50

60

70

80

90

100

10 100 1000 10000

Particle size en µm

PS

D P

assin

g %

Bottom ash

Seal pot

Fly ash

Field data Fly ash

Field data Bottom ash

Field Data Seal pot 18/11/92

Field Data Seal pot 08/04/92

Simulation

Field data

Emile Huchet 125 MWel CFB boiler

Actual performances match computerized PSD forecast

Particle size, µm

Fuel

Unburnt carbon loss % LHV 1,4 1,2 2,55 1,71

Unburnt carbon in bottom ash % 1,2 1,0 0,4 0,4

Unburnt carbon in fly ash % 6,0 5,6 5,0 3,8

Fly Ash - Bottom Ash split % - % 70/30 60/40 62/38 58/42

Performance test

Schlamm Slurry

Page 13: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Agenda

Baima 300 MWe CFB demonstration plant Page 3

Emile Huchet 125 MWe captive power plant Page 9

Seward 2 x 260 MWe Page 13

Conclusion Page 16

Page 14: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

• Customer: Reliant Resources, USA • Commissioning: 2004 • Steam Conditions:

• Capacity: 2 x 872 t/h • Pressure: 174 bar • SH/RH Temperature: 541/541°C

Seward 2 x 260 MWe CFB boilers

• Fuel: Pennsylvania • 2 millions tonnes of mining waste coal on site • 100 millions within 80 km

Carbon % wt 29.32 (25-35)

Volatile matter % 11 ( 9-30)

Sulphur % 2.75 (2 – 4.25)

Ash % 51 (25-58)

Moisture % 8.7 ( 7 – 12)

Heating ValueMJ/kg

Kcal/kg

12.8 (11.6-14)

3050

Page 15: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Emission levels

SO2 mg/Nm³ @ 6 % O2 780

or sulphur removal 95%

NOX mg/Nm³ @ 6 % O2 130

Particulates mg/Nm³ @ 6 % O2 40

Three-bay arrangement: • Coal feeding on the front wall. • Three aligned cyclones • 2 x FBAC • 2 x FBHE

• Proprietary NIDTM dry scrubber • SNCR

Seward 2 x 260 MWe CFB boilers

Clean Power from Waste Coal

Page 16: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Agenda

Baima 300 MWe CFB demonstration plant Page 3

Emile Huchet 125 MWe captive power plant Page 9

Seward 2 x 295 MWe Page 13

Conclusion Page 16

Page 17: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Conclusions

• Correctly applied CFB efficiently combusts discard coal

• Full fuel knowledge is mandatory: • Coal rank • Ash chemical composition • Uncontrolled moisture • Fuel PSD • Coal fragmentation and ash attrition

• Required low load performance drives

the CFB technology choice

• SO2 and NOx emissions may drive back-end treatment options • NIDTM dry scrubber • SNCR

Alstom leverages off its relevant experience to offer discarded fuel-fired CFB

8890

HHV with inherent moisture without mineral matter (kcal/kg)

Anthracite

VM/MAF in %

7780 7220 6110 5280 4610

31

22

14

2

0

High vol. C Bit. or

Subbit. ASubbit. B Subbit. C Lignite

60

Low Vol. Bit

High vol. A bit.High vol.

B bit.

Medium Vol. Bit.

High Volume of Flue GasHigh Reactivity

Low Volume of Flue GasLow Reactivity

Tamuin (petcoke)

Mai Liao (petcoke)

BaimaCoa Ngam

Emile HuchetGilbert #3Spurlock #4

KaiyuanXiaolongtanCanAkrimotaRed Hills

Tarahan

Seward

GardanneQuinhangdaoZeran

Page 18: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Alstom - CFB Product portfolio

CFB installed base over 13,000 MWe with 140 references

Three Bay Arrangement

• From 100 MW to 350MW class

• Up to 4 cyclones in line

175 bars – 565°C/565°C

Dual Grate Arrangement

• 350MW class

• External bed technology

175 bars – 565°C/565°C

USC CFB Platform

• 660 MW and up

• +6 % increased efficiency

275 bars - 600°C/620°C

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3

Page 19: Alstom CFB boilers achieve high combustion efficiency with challenging discarded … · 2014-01-07 · Hugh Kennedy 16th July 2013 Alstom CFB boilers achieve high combustion efficiency

© ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on that it is complete or correct or will apply to any particular project. This will depend on the technical and commercial circumstances. It is provided without liability and is subject to change without notice. Reproduction, use or disclosure to third parties, without express written authority, is strictly prohibited.

Alstom CFB Product portfolio

Leveraging boiler technology experience

World class supplier of SC/USC PC-fired boiler up to 1100MW

290 bar – 600/620°C

USC CFB Platform 660 MW and up

• 275 bar - 600°C/620°C

• +6 % increased efficiency

Fuel combustion expertise Leading CFB technology Supplier

• Over 13GW installed based

• up to 350MW

• 175 bar – 565/565°C

Dual Grate Arrangement

3-Bay Arrangement

8890

HHV with inherent moisture without mineral matter (kcal/kg)

60

7780 7220 6110 5280 4610

High vol. A

bit.

High

vol. B

bit.

High vol. C

Bit. or

Subbit. A

Subbit.

B

Subbit.

CLignite

Low Vol. Bit22

Medium Vol.

Bit.31

VM/MAF in %

0

2

Anthracite

14 High Volume of Flue Gas

High Reactivity

Low Volume of Flue Gas

Low Reactivity

ALSTOM EXPERIENCE WITH CFB

Fluidised Bed Combustion and Gasification, Johannesburg - 16/07/2013 - P 3