Eglinton West/Allen Road Station Potential South Side Entrance Options
Online ConsultationApril 2nd to April 16th
Eglinton West/Allen Road Station Consultation #1
• Most common comment: south side entrance very important
• Most common location requested – Ben Nobleman Park
• Conversely, comments also expressed to avoid park (community orchard)
• Other locations requested: Police Station Lot and Everden Road
• Many expressed concerns crossing Eglinton and Allen
Crosstown Station Design: Principles for ALL Stations• One fully accessible main entrance (elevators and escalators)
• One secondary entrance
• Cannot provide multiple secondary entrances (& multiple accessible entrances) at all stations for budgetary reasons
Potential South Side Entrance forEglinton West/Allen Road Station• Final Decision to include an additional secondary entrance on the south
side of Eglinton will be made based on cost, community input & engineering factors over coming months
• Must get input from local community tonight and going forward
• Final Decisions on project scope & budget will be made by Metrolinx who is funding transit expansion
The Eglinton Crosstown LRT
10km Underground Central Section
10 km central underground: Keele – Laird
The Eglinton Crosstown LRT
Crosstown Plan
• Underground from Keele Street to Laird Drive in Leaside
• Dedicated transit lane from Laird Dr to Kennedy Station in Scarborough
• 60% faster than bus service today (e.g. only 15 minutes Keele to Yonge)
Design Philosophy
• Integrate with surrounding neighbourhood
• Preserve space for future re-development
• Enhance the local “sense of place”
• Long-term sustainability
• Safe and enjoyable user experience
• Accessibility
6
Pedestrian Challenges
Eglinton Avenue - looking West
•Eglinton looking West
•No Crosswalk Today
• New Crosswalk proposed at Strathearn, discussions with City Transportation
Pedestrian Challenges
Allen Road - looking South
Context: Eglinton West Allen Station
Eglinton West Station – Current PlanTwo Crosstown Station Entrances on North SideSouth Entrance Dependent on Future Development at Police Station
• Walkway connecting northside station entrances will allow pedestrians to cross Allen Road underground
• Existing crossings at street level will remain
• Existing entrance to Eglinton West Subway Station remains
• New Crosswalk Proposed at Strathearn
Pedestrian ImprovementsNew Walkway & Sunken Garden under Allen Rd
12Eglinton West Station - Preliminary Design Overview
1/25/2012
Eglinton West (Allen Rd) Station Interchange Station• Two north side entrances to Crosstown Station
• North West entrance is fully accessible
• Underground Walkway between Entrances
• Fare lines below street level allows crossing underground (with or without using the TTC
• Existing Eglinton West Station Entrance remains
• Accessible Transfer to Subway
• 95 metre passenger platform
• Temporary and Long Term Bicycle Storage
• Potential Secondary Entrance, on South side of Eglinton Avenue
Longitudinal Section Detail
INTERIOR VIEW: CONCOURSE LEVELS INTERIOR VIEW: UPPER CONCOURSE
PERSPECTIVE SECTION VIEW ALONG EGLINTON AVENUE
North East Entrance New Crosswalk Proposed at Strathearn
Eglinton West Subway Station Plaza Entrance + Sunken Garden Area
North West Entrance
Current Site withPotential Locations for South Entrance
Potential South Side Entrance Locations
Option 0 – No South Entrance (current design)
Artistic Interpretation of Study AreaArtistic Interpretation of Study Area
South Station Entrance Options
Potential South Entrance Options:
Option 1 – Ben Nobleman Park Pavilion
Artistic Interpretation of Study AreaArtistic Interpretation of Study Area
Potential South Entrance Options:
Option 1 – Ben Nobleman Park PavilionConsists of a pavilion type entrance located at the north west corner of Ben Nobleman Park.
The concept is to have a structure that is very open; almost transparent. It has continuous glazing on three sides permitting visibility from the street to the park, and from the park to the street.
It serves as an entrance to the park, through a loggia in front of the entrance, and permits an easy connection to the existing east to west cross path in the park.
The structure is located as far northwest as possible to limit impacts to the Park and Community Orchard as much as possible.
Consists of a pavilion type entrance located at the north west corner of Ben Nobleman Park.
The concept is to have a structure that is very open; almost transparent. It has continuous glazing on three sides permitting visibility from the street to the park, and from the park to the street.
It serves as an entrance to the park, through a loggia in front of the entrance, and permits an easy connection to the existing east to west cross path in the park.
The structure is located as far northwest as possible to limit impacts to the Park and Community Orchard as much as possible.
Potential South Entrance Options:
Option 1 – Ben Nobleman Park Pavilion
Potential South Entrance Options:
Option 1 – Ben Nobleman Park Pavilion
STAIR TO BELOW
ROOF ABOVE
AUTOMATIC DOOR
LOWER CONCOURSE
FARE LINE AT LOWER CONCOURSE
STREET/LOWER CONCOURSE OVERLAY PLAN
Potential South Entrance Options:
Option 1 – Ben Nobleman Park Pavilion
Potential South Entrance Options:
Option 2 – Ben Nobleman Park Green Roof
Artistic Interpretation of Study AreaArtistic Interpretation of Study Area
Potential South Entrance Options:
Option 2 – Ben Nobleman Park Green RoofConsists of a green roof structure designed so as to appear to grow out of the park’s topography.
It follows the pavilion concept in providing an entrance to the park and visibility to and from the park. The green roof’s sloped structure will appear to be continuous with the park, but controls will be put in place to limit access onto the roof structure.
Consists of a green roof structure designed so as to appear to grow out of the park’s topography.
It follows the pavilion concept in providing an entrance to the park and visibility to and from the park. The green roof’s sloped structure will appear to be continuous with the park, but controls will be put in place to limit access onto the roof structure.
Potential South Entrance Options:
Option 2 – Ben Nobleman Park Green Roof
Potential South Entrance Options:
Option 2 – Ben Nobleman Park Green Roof
STAIR TO BELOW
ROOF ABOVE
AUTOMATIC DOOR
LOWER CONCOURSE
FARE LINE AT LOWER CONCOURSE
STREET/LOWER CONCOURSE OVERLAY PLAN
Potential South Entrance Options:
Option 2 – Ben Nobleman Park Green Roof
Potential South Entrance Options:
Option 2a – Ben Nobleman Park Green Roof - Facing Everden
Potential South Entrance Options:
Option 2a – Ben Nobleman Park Green Roof – Facing Everden
Option 2a consists of the green roof structure, reoriented to open to the west at Everden Road, rather than to the east.
This design eliminates the logia and entrance to the park in favour of a more compact footprint, and less impact to the park. It still provides the amenities of a south side entrance; the cost benefits of a more economical entrance; all the while integrating into the park to be much less noticeable from within the park.
Option 2a consists of the green roof structure, reoriented to open to the west at Everden Road, rather than to the east.
This design eliminates the logia and entrance to the park in favour of a more compact footprint, and less impact to the park. It still provides the amenities of a south side entrance; the cost benefits of a more economical entrance; all the while integrating into the park to be much less noticeable from within the park.
Potential South Entrance Options:Option 2a – Ben Nobleman Park Green Roof – Facing Everden
Potential South Entrance Options:
Option 2b – Ben Nobleman Park Glass Box
Artistic Interpretation of Study AreaArtistic Interpretation of Study Area
Potential South Entrance Options:
Option 2b – Ben Nobleman Park Glass BoxOption 2b consists of a simple rectangular‐volume entrance located at the north west corner of Ben Nobleman Park.
The concept is to have a structure that is very open; almost transparent. It has continuous glazing on four sides permittingvisibility from the street to the park, and from the park to the street. The mullions recall the arboreal nature of the park.
The structure is located as far north west as possible to avoid impacting the existing Community Orchard as much as possible.Entry is directly from the Everden Road sidewalk located on the west side of the building as shown in the rendering below.
Option 2b consists of a simple rectangular‐volume entrance located at the north west corner of Ben Nobleman Park.
The concept is to have a structure that is very open; almost transparent. It has continuous glazing on four sides permittingvisibility from the street to the park, and from the park to the street. The mullions recall the arboreal nature of the park.
The structure is located as far north west as possible to avoid impacting the existing Community Orchard as much as possible.Entry is directly from the Everden Road sidewalk located on the west side of the building as shown in the rendering below.
Potential South Entrance Options:
Option 2b – Ben Nobleman Park Glass Box
Update with Glass box from pA
Potential South Entrance Options:
Option 2b – Ben Nobleman Park Glass Box
STAIR TO BELOW
ROOF ABOVE
AUTOMATIC DOOR
LOWER CONCOURSE
FARE LINE AT LOWER CONCOURSE
STREET/LOWER CONCOURSE OVERLAY PLAN
Potential South Entrance Options:
Option 2b – Ben Nobleman Park Glass Box
Potential South Entrance Options:
Option 3 – Division 13 Police Station Parking Lot
Artistic Interpretation of Study AreaArtistic Interpretation of Study Area
Potential South Entrance Options:
Option 3 – Division 13 Police Station Parking Lot
Option 3 consists of a south side entrance – similar in design and material to the east and west entrances – within the Division 13 Police Station parking lot. The entrance is located further south than the park side options due to the presence of utilities running on the south of Eglinton Avenue that must be avoided. The concept is similar to the North East Entrance in that it provides an entrance structure that can be easily incorporated into any future development of the site.
Option 3 consists of a south side entrance – similar in design and material to the east and west entrances – within the Division 13 Police Station parking lot. The entrance is located further south than the park side options due to the presence of utilities running on the south of Eglinton Avenue that must be avoided. The concept is similar to the North East Entrance in that it provides an entrance structure that can be easily incorporated into any future development of the site.
Potential South Entrance Options:
Option 3 – Division 13 Police Station Parking
Potential South Entrance Options:
Option 3 – Division 13 Police Station Parking
ROOF ABOVE
LOWER CONCOURSE
STAIR TO BELOW
AUTOMATIC DOOR
FARE LINE AT LOWER CONCOURSE
STREET/LOWER CONCOURSE OVERLAY PLAN
Potential South Entrance Options:
Option 3 – Division 13 Police Station Parking
Potential South Entrance Options:
Option 4 – Division 13 Police Station Glass Box
Artistic Interpretation of Study AreaArtistic Interpretation of Study Area
Potential South Entrance Options:
Option 4 – Division 13 Police Station Glass BoxConsists of a Glass Box design for the south entrance. The minimal sized entrance can be easily removed in the future so as to offer greater flexibility in design for future developments on the site – while still maintaining an entrance.Consists of a Glass Box design for the south entrance. The minimal sized entrance can be easily removed in the future so as to offer greater flexibility in design for future developments on the site – while still maintaining an entrance.
Potential South Entrance Options:
Option 4 – Division 13 Police Station Glass Box
Potential South Entrance Options:
Option 4 – Division 13 Police Station Glass Box
ROOF ABOVE
LOWER CONCOURSE
STAIR TO BELOW
AUTOMATIC DOOR
FARE LINE AT LOWER CONCOURSE
STREET/LOWER CONCOURSE OVERLAY PLAN
Potential South Entrance Options:
Option 4 – Division 13 Police Station Glass Box
Potential South Entrance Options:OPTION O - No South Side Entrance
Option 0No South Entrance
Advantages1.No interference with existing utilities2.More available space for the proposed utility relocates
and construction staging area.3.No impact in Ben Nobleman Park or 13 Division Police
parking lot.
Disadvantages1.No Southern Entrance into Eglinton West (Allen)
Station. 2.Pedestrians must cross Eglinton West to enter station
West (Allen) Station.
Prelim Additional Construction Cost based on Concept –Excludes Contractor fees/overhead None – no south entrance
Potential South Entrance Options:Options 1, 2/2A & 2b – Ben Nobleman Park Options
Ben Nobleman Park Options Option 1Park Pavilion88 sq. M. ground floor area120 sq. m. stair construction
Option 2/2aPark Green Roof Pavilion88 sq. M. ground floor area120 sq. m. stair construction
Option 2bPark Glass Box60 sq. M. ground floor area150 sq. m. stair construction
Advantages (all Park Options)1. Excellent access for people from south side of Eglinton West. 2. This location should capture 100% of the pedestrians south of
Eglinton West. The green roofs in Option 2&2A integrate the building into the park. 2A and 2B face Everden. 2B smallest surface footprint
3. Entrance potentially serves as additional amenity to the community. 4. No major interference with existing or relocated utilities. 5. Lighting, safety, and security potentially improved within Ben
Nobleman Park.
Disadvantages (all Park Options)1. Requires public park land at Ben Nobleman2. Tree impacts TBD (replacement would be done based on City policy.)Prelim Construction Cost based on Concept –Excludes Contractor fees/overheadOption 1 – 2.6MMOption 2/2a – 2.4MMOption 2b – 2.6MM
Potential South Entrance Options:Options 3 &4 - Police Station Parking LotDivision 13 Police Station ParkingOption 313 Division South Entrance81 sq. M. ground floor area146 sq. m. stair construction
Option 413 Division Glass Box81 sq. M. ground floor area146 sq. m. stair construction
Advantages1. Provides south entrance without impacting Ben Nobleman Park. 2. Excellent south access into station. 3. Allows for future development to have access to station.
Disadvantages1. Significant conflict between proposed stairwell and relocated
sanitary and storm sewers.2. 3 parking spots lost for Option 3 and 14 spots lost for option 4. 3. Severe police mobility disadvantage for option 3 due to elimination
of police vehicles direct access to Eglinton West Ave.
Prelim Construction Cost based on Concept –Excludes Contractor fees/overheadOption 3 – 3.4MMOption 4 – 3.2MM
The Crosstown TeamPlease Get in Touch with Us!
Community Office Hours — 2012Monday, Wednesday, Friday: 9:00 a.m. – 5:00 p.m.
Tuesday & Thursday –Please contact us for an appointment
Franca Di Giovanni, Devin Horne,Denise Jayawardene
E-mail: [email protected] Online: www.thecrosstown.caTel: 416-338-6310Fax: 416-397-8193TTY: 416-481-2523
Please Visit our Community Office At 1848 Eglinton Avenue West (at Dufferin)(
Thank you!
Allen Road