allen park presbyterian church
DESCRIPTION
Allen Park Presbyterian Church. Facility Study 2007-08. Facility Study 2007-08 History. Doug Pretty introduces Bill McCarthy, McCarthy & Smith, to Pastor Doug Blaikie. - PowerPoint PPT PresentationTRANSCRIPT
Allen Park Presbyterian Church
Facility Study 2007-08
Facility Study 2007-08 History
Doug Pretty introduces Bill McCarthy, McCarthy & Smith, to Pastor Doug Blaikie.
Doug Pretty and Bill McCarthy met with members of Building Committee in July 2007 to explain what and how a Facility Study could be accomplished.
Facility Study 2007-08 History
August 2007 - Building Committee hires architects Wilkie & Zanley and construction manager McCarthy & Smith to conduct Facility Study which will lead to conceptual drawings, estimated costs and schedule.
Facility Study 2007-08 History
Summer/Fall 2007 Onsite investigating, discussions with city conducted by Wilkie & Zanley.
Preliminary concepts presented in September 2007 to Building Committee. Committee directs team to further study additions option.
Facility Study 2007-08 History
McCarthy & Smith prepares cost estimates and schedule options.
Team presents report to Building Committee on December 19, 2007.
Building Committee Concerns
Fellowship Hall (Old Building)– Barrier-free access to lower and main levels– Multi-purpose space, air-conditioned
Church services in summerSocial/fellowship activitiesYouth group activities
– Additional columbarium space and inventory– Develop shower space for annual outreach
programs– Develop designated storage areas– Upgrade electrical service to facilities
Building Committee Concerns
Main Church (New Building)– Barrier-free restroom facilities
Scenarios to Consider
Scenario #1– Construct barrier-free addition and
associated site work– Construct columbarium addition and
associated basement storage– Barrier-free restrooms (Main Church)
$1,300,000Alternate for Development of Office Area $30,000
Options to Consider
Scenario #2– Construct the multi-use addition at a later
time.$1,300,000
Alternate for shower room facilities $20,000
Cost is based on 2008 construction dollars. Average price escalation per year is 4-5%.
Options to Consider
Scenario #3– Construct both scenarios at the same
time.
(Represents a cost savings achieved through less redundant general condition and supervision costs.)
$2,500,000
Schedule
Project Review and Approvals– Present to session committee 1/16/08– Present to congregation at annual
meeting 1/20/08– Congregation to vote on project
2/10/08?
Schedule
Design– Design Phase– Review and approval
(5-1/2 months)2/11/08 -
7/30/08
Schedule
Bid/Award– Bid/Award Phase
(1 month) 8/1/08 - 8/29/08
Schedule
Construction– Scenario #1
Barrier-free entrance additionColumbarium additionAssorted interior remodeling
(6 months) Barrier-free restrooms (main church) 9/15/08 - 3/27/09
Schedule
Construction– Scenario #2
Multi-use addition(8 months) TBD
Schedule
Construction– Scenario #3
Additions, entrance & multi-purposeColumbarium additionInterior remodeling
9/15/08 - 5/30/09
AcknowledgementsAllen Park Presbyterian Church Building Committee
Ken Lieber, Co-chairJohn DamShirley SlatkaJim KinardFern Brandt
Doug Blakie, Pastor
John Wilkie
Bill McCarthy
Jim Bebe, Co-chairBarry DavisKelly EllisLarry Templin
Melody Jones, Associate Pastor
Dave Zanley
Steve Banchero
Wilkie-Zanley, Architects
McCarthy & Smith, Construction Managers
Allen Park Presbyterian Church
Facility Study 2007-08