alice-lhcc review may 14, 2001 thomas c. meyer/ep-ait1 tpc field cage progress report project...

17
ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT 1 TPC Field Cage Progress TPC Field Cage Progress Report Report Project Schedule Technical Progress & Prototyping Contractual Matters

Upload: juliet-philippa-butler

Post on 20-Jan-2016

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 1

TPC Field Cage Progress ReportTPC Field Cage Progress ReportTPC Field Cage Progress ReportTPC Field Cage Progress Report

Project ScheduleTechnical Progress &

PrototypingContractual Matters

Page 2: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 2

Field Cage: Project ScheduleField Cage: Project ScheduleField Cage: Project ScheduleField Cage: Project Schedule

Page 3: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 3

Tests & PrototypingTests & PrototypingTests & PrototypingTests & Prototyping

HV– High ionization behavior (83Kr)

Temperature stabilization– Resistor chain cooling

Construction material– Compatibility and leaks

Electrical network– “From strip to central electrode”

Page 4: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 4

High Voltage StabilityHigh Voltage StabilityHigh Voltage StabilityHigh Voltage Stability

History:– Field cage was exposed to >16 x expected

average charged particle intensity in CERES beam (~ 6000/cm2 s).

– Field cage was operated at 1.78 x nominal drift field (~700 V/cm) in pure CO2.

Surface charge phenomena appearing at 60 kV (≥ 400 V/cm).– Insulation gap safe at ≥ 100 kV.

Page 5: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 5

High Intensity High Intensity 8383Kr TestKr TestHigh Intensity High Intensity 8383Kr TestKr Test

Inject 83Kr with 300 MBq total intensity into field cage (May 2001)

Separate tests for drift and insulation volume.

Page 6: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 6

Temperature StabilityTemperature StabilityTemperature StabilityTemperature Stability

History:– Require:T everywhere ≤ 0.1 ºC– Resistor rod produces 60 W waste heat.

– Liquid cooling (H2O) proven very efficient with negligible gradient inside rod but…

H2O unsuitable at HV (dissociation), Inert liquids dangerous in case of leaks.

New approach: Gas cooling

Page 7: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 7

Resistor Rod: Gas CoolingResistor Rod: Gas CoolingResistor Rod: Gas CoolingResistor Rod: Gas Cooling

Unlike liquid cooling, T inside rod always > 0.1 ºC.– --> must insulate rod!

Foam for test Double wall for ALICE.

T [ºC]

z [m]Ambient level2.5

Page 8: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 8

Gas Cooling: ResultsGas Cooling: ResultsGas Cooling: ResultsGas Cooling: Results Inside of rod achieve tmin of 7 ºC

with 20 m3/h of air:Air Temperature along the rod vs. Flow

0

5

10

15

20

25

30

35

40

45

0 2 4 6 8

Temperature [Celsius]

20m 3̂/h 15m 3̂/h 10m 3̂/h 5m 3̂/h

Gas Flow

Tin = 16 ºC

7 ºC

Page 9: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 9

Gas Cooling: ResultsGas Cooling: ResultsGas Cooling: ResultsGas Cooling: Results

Outside of rod achieve required T of ≤ 0.1 ºC within a few cm from rod:

Numbers are given in units of 1/100 ºC;

Blue numbers indicate zone around rod with

T < 0.1 ºC

Page 10: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 10

Material testsMaterial testsMaterial testsMaterial tests

Drying

-250

-200

-150

-100

-50

0

50

-250

-200

-150

-100

-50

0

50

0 100 200 300 400 500

TEMPERATURE STABILIZATION : +/- 0.4 CPRECISION OF MEASUREMENT : +/- 10 μm

L/L

m/m

]T[ h]

Macrolon

Carbon Fiber

Kevlar Fiber

Glass Fiber

Wet

Leak test of full-size end plate sector with “CERES” gasket

Humidity tests of FC material

Page 11: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 11

Voltage Divider: Central ElectrodeVoltage Divider: Central ElectrodeVoltage Divider: Central ElectrodeVoltage Divider: Central Electrode

Focus on “stretched foil” version High modulus carbon-fiber frames

NA48 Example

Page 12: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 12

Voltage Divider: Rods & StripsVoltage Divider: Rods & StripsVoltage Divider: Rods & StripsVoltage Divider: Rods & Strips

Ongoing prototyping of all rod types– Resistor rod– HV supply rod– Laser rod– Regular support rod

Verification of strip tension and mounting scheme– Vertical or horizontal?

Page 13: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 13

ToolingToolingToolingTooling

Modification of DELPHI support frame– Needed for construction & assembly of FC– Major handling tool for all operations– Finished by end of 2001

Page 14: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 14

Infrastructure: SXL2Infrastructure: SXL2Infrastructure: SXL2Infrastructure: SXL2

Preparation of dedicated clean area for TPC assembly in LHC interaction region 2:– Finished by December 2001

Clean zone in hall SXL2

Page 15: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 15

Contracting: FC CylindersContracting: FC CylindersContracting: FC CylindersContracting: FC Cylinders First „Invitation to Tender“ (IT-2726) was

launched on schedule in 2000, but...– all offers (4) were above funding level.

Changed scope of tender:– Only production of individual parts

(panels & flanges)– Procurement by and assembly at CERN

New tender (IT-2999) sent April 2001– 6 months delay in schedule

Page 16: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 16

Contracting: End PlatesContracting: End PlatesContracting: End PlatesContracting: End Plates

First „Price Inquiry“ was made in 2000.– Lowest bid exceeded funding by large factor.

Try to achieve savings by…– splitting production process

(raw material, welding, machining), and– design changes.

New tenders to be launched this month– only if expected savings materialize!

Overall production delay ≥ 6 months.

Page 17: ALICE-LHCC Review May 14, 2001 Thomas C. Meyer/EP-AIT1 TPC Field Cage Progress Report Project Schedule Technical Progress & Prototyping Contractual Matters

ALICE-LHCC Review May 14, 2001

Thomas C. Meyer/EP-AIT 17

Contracts: Consequences for CERNContracts: Consequences for CERNContracts: Consequences for CERNContracts: Consequences for CERN

Higher manpower load on CERN (TA2) Higher risks in terms of…

– technical failure, quality control, liability, warrenty!

– schedule slippage, – capital loss.

We expect to catch up on the baseline schedule during the internal assembly of the FC (2002/3).