Page 1: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better CommunitiesTransportation Solutions Building Better Communities

PREPARED BY MCMAHON ASSOCIATES

Alderfer Road (T-423) Bridge Replacement Project

Lower Salford TownshipMontgomery County, PA

December 2, 2020

Page 2: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 2

• Project Purpose and Need• Project Funding Sources• Overview of the Existing

Conditions• Overview of the Proposed

Improvements• Construction Staging• Traffic Control During

Construction & Detour Plan• Project Schedule including

Construction

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

Page 3: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 3

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

PROJECT PURPOSE & NEEDTotal Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives:

1. Replace the existing structurally deficient bridge that is in poor condition;Structurally Deficient Definition: Bridge is restricted to light vehicles, closed to traffic or requires

rehabilitation. There are elements of the bridge that need to be monitored and/or repaired and the bridge must be inspected and maintained.

2. Improve horizontal and vertical roadway geometry in the vicinity of the bridge;

3. No rise in water surface elevation during the base flood event. The project site is located in a FEMA Zone AE w/floodway.

AE: High-risk areas have at least a 1% annual chance of flooding. Area inundated by the Base Flood with Base Flood Elevations (BFE) determined. BFE: The elevation of surface water resulting from a flood that has a 1% chance of equaling or exceeding that level in any given year.

Page 4: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 4

Township Owned Structure – Township is responsible for maintenance and improvements. PennDOT completes annual inspections on behalf of the municipality for structures with a 20-foot span or greater. (Structures with a span between 8’ to 20’ are solely Twp responsibility).

Lower Salford received an award through the 2018 PA Municipal Bridge Retro-Reimbursement Program (MBRP)• Includes Federal and State funding as part of the Transportation Improvement Program

(TIP); a regionally agreed upon list of transportation projects as required by federal law;• MBRP is a reimbursement program that allows the Township to submit for reimbursement of

up to 80% of the total project cost;• The reimbursement is made at the end of the project construction;• The reimbursement can include project development, construction, and inspection

services.

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

PROJECT FUNDING SOURCES

Page 5: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 5

Existing Structure Type• Two-span, 40’ long reinforced concrete slab

bridge; • Built in 1940; • Currently posted for 15 Tons;• Supported on a concrete pier and

concrete abutments with integral wingwalls.• Inspected annually by PennDOT.

Regular Flooding Events• May 29, 2019 Storm Event (Photos);• Existing structure cannot pass the 2-year

storm event.

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

EXISTING CONDITIONS

Page 6: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 6

Proposed Structure Type• 51’-6” span, prestressed concrete composite adjacent box beam bridge;• Opening large enough to pass the 100-year storm event;• No change in elevation to the 100 year flood plain as result of the construction;• Bridge parapet walls and guide rail meeting current requirements;• Architectural treatment will be provided on parapet walls and safety wings;• Structural Adequacy approval is required by PennDOT, even though this is a Township structure.

• Existing Bridge

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

PROPOSED IMPROVEMENTS

Architectural treatment example only; Henry Woods Bridge

Existing Bridge

Proposed Bridge

Page 7: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 7

Roadway Geometry• Maintain 10’ travel lanes plus adding 5’ shoulders within limits of work;• Horizontal geometric improvements to meet posted speed design criteria; superelevation for the

travel lanes; • Vertical profile adjustments to allow for large enough bridge opening; Includes raising the low

section of the roadway approximately 5 feet.

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

PROPOSED IMPROVEMENTS

EXISTING

PROPOSED

Page 8: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 8

Environmental Studies & Permitting • Chapter 105 Joint Permit issued by DEP for the structure replacement and work area

Stream Channel Grading

Adjustments to Adjacent Properties• Access adjustments, include re-profiling to tie into the new roadway elevation;• Shared-use path replacement;• Grading modifications.

Utility Relocations • Cooperation and coordination with the Lower Salford Township Authority (LSTA), PECO Gas, PECO

Electric, North Penn Water Authority (NPWA)

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

PROPOSED IMPROVEMENTS CONT’D

Page 9: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 9

Four Stages of Construction• Coordinated with Bridge, Roadway, and Erosion and Sedimentation Control requirements

Stage 1 – West Side of the Bridge (Sta. 7+50 to Sta. 12+10)Duration: 10 Weeks

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

CONSTRUCTION STAGING

Page 10: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 10

Stage 2 – East Side of the Bridge (Sta. 12+10 to Sta. 13+20)Duration: 10 Weeks

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

CONSTRUCTION STAGING

Page 11: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 11

Stage 3 – East Side of the Bridge (Sta. 12+20 to Sta. 16+50 & Wyndham Court) Duration: 10 Weeks

Stage 4 – Final Improvements (Final Paving, Markings, etc.) Duration 2 Weeks

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

CONSTRUCTION STAGING

Page 12: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 12

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

FINAL CONDITION

Page 13: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 13

Bridge and Roadway will be constructed under a Detour• Local access to properties and businesses along

Alderfer Road will be maintained during construction;• Detour Route will be Ruth Road, Clemens Road, Main

Street;• Advance notice variable message boards will also

be provided by the Township alerting public of upcoming detour;

• Detour approved by PennDOT.

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

TRAFFIC CONTROL AND DETOUR PLAN

And Remember This:

Page 14: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 14

Project Development (2018-2020)• MBRP Application, preliminary engineering, environmental studies and permitting, hydraulic and hydrology

analysis, final design, structural approvals, utility coordination, property owner coordination/Right-of-Way and Temporary Construction Easement acquisition.

Project Advertisement/Letting (January 2021 – March 2021)• Publicly advertised using PennBID which simplifies the municipal letting process;• Bid package available to large amount of qualified contractors• Anticipated Award March 3, 2021 BOS Meeting

Project Construction (April 2021 – November 2021)• Anticipated Pre-Construction Meeting Mid-Late March 2021• Notice-to-Proceed April 2021 • Construction Duration Approximately 8 Months, Utility Coordination Schedule is Critical

ALDERFER ROAD (T-423) BRIDGE REPLACEMENT PROJECT

PROJECT SCHEDULE

Page 15: Alderfer Road (T-423) Bridge Replacement Project...Total Replacement of the bridge carrying Alderfer Road over the West Branch of Skippack Creek. 3 primary design objectives: 1. Replace

Transportation Solutions Building Better Communities Page 15

QUESTIONS?CONTACT INFORMATION:

Stephanie L. Butler, P.E., Senior Project ManagerMcMahon Associates, Inc. [email protected], Ext. 1256

Christopher Seaman, P.E., CBI, Senior Project Manager (Structures)McMahon Associates, Inc. [email protected]