aide memoir 21 nov 13

Upload: ranish-p-kurian

Post on 04-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 Aide Memoir 21 Nov 13

    1/5

    ide Mem oire

    As on Date: 07-Dec-13

    Subject:DEL EGC Project, Qatar

    1. Project : Export Gas Compression Facilities Upgrade Project, Ras Laffan2.

    Client : Dolphin Energy Limited

    3. Feed : JGC Corporation4. Project Scope : Upgrading Export Gas Facilities from current 2.2 BSCFD to 3.2 BSCFD5. Zero Date : 05 September 20126. Contractual Completion Date : 07 January 2015 (RFSU)7. Time Elapsed : 15 Months and 2 days8. Balance Duration: : 13 Months (Ready for Start-up)9. Detailed Engineering : L&T ChiyodaMumbai

  • 8/13/2019 Aide Memoir 21 Nov 13

    2/5

    ide Mem oire

    a) Executive Summary1) Cumulative Safe Man-hours : 1.37 Million Man Hours without LTI till 06.12.132) Equipment Status :

    Compressors and Turbines

    All 3 compressors and Turbines skids and accessories received at site.

    Alignment of Compressors and Turbines is in progress

    Module assembly of Roof Module, Filter Module and Structure Modules for Train 7 is in progress

    HRSG

    Train 7 Modules received at site, Erected, welding is in progress

    Train 8 and 9 Modules received at site on 07.12.13

    Air Fin Coolers

    Air Fin cooler received at site on 04.12.13

    Inventory taking is in progress

    Assembly on ground for Train 7 will start on 12.12.13

    3) Planned Quantity v/s ActualsDESCRIPTION UOM

    Cumulative Qty.

    Planned Actual

    Civil

    Foundation CUM 3102 3025

    Building CUM 752 1276

    Pre-casting of Members at Vendor Shop Nos. 496 509

    Installation of Pre casting Members Nos. 414 152

    Cast in situ of Column and Beams CUM 415 39

    Piping

    AG Piping Fabrication ID 14719 8584

    4) Construction Progress Summary (As on 05 December 2013)SL.

    NO.

    DESCRIPTION WTD.

    VALUE

    CUMMULATIVE

    SCH ACT.

    1 HSE & S 1.0% 0.51% 0.48%

    2 Survey, Mobilisation and Temporary Facilities 25.0% 19.55% 24.76%

    3 Construction 74.0% 2.00% 16.30%

    3.1 Civil 27.00% 14.040% 13.789%

    a) Excavation 0.04% 0.034% 0.031%

    b) Backfilling 0.24% 0.029% 0.016%

    c) Foundation 5.28% 3.916% 3.819%

    d) Building 11.41% 4.815% 8.170%

    e) Pre casting of Column and Beams 3.06% 2.179% 2.237%

    f) Installation of Pre casting 4.00% 2.375% 0.873%

    g) Cast in situ for wet joints 1.15% 0.449% 0.000%

    h) Paving 0.72% 0.000% 0.000%

    i) Road Work 0.49% 0.000% 0.000%

  • 8/13/2019 Aide Memoir 21 Nov 13

    3/5

    ide Mem oire

    SL.

    NO.

    DESCRIPTION WTD.

    VALUE

    CUMMULATIVE

    SCH ACT.

    j) Other Civil 0.60% 0.243% 0.000%

    3.2 Structure 3.75% 1.355% 0.000%

    a) Structure Fabrication 1.32% 0.565% 0.000%

    b) Structure Erection 2.01% 0.790% 0.000%

    c) Grating Installation 0.41% 0.000% 0.000%

    3.3 Piping 23.25% 2.625% 0.45%

    a) AG Piping Fabrication 4.64% 1.16% 0.68%

    b) AG Piping Erection (IM) 8.78% 0.15% 0.00%

    c) AG Piping Erection (ID) 3.62% 0.00% 0.00%

    d) Mechanical Completion 1.17% 0.00%

    e) Hydro Testing 2.93% 0.00%

    f) UG Piping Fabrication and Laying 2.11% 1.31% 0.00%

    3.4 Mechanical 12.75% 3.278% 2.10%

    3.5 Electrical 3.00% 0.01% 0.00%

    3.6 Instrumentation 3.25% 0.02% 0.00%

    3.7 Painting and Insulation 1.00% 0.01 0.01%

    Total 100.00% 46.38% 3.278%

    5) Construction S Curve

    6) NDT statusPeriod Welded

    RT to be

    TakenRT Completed Rejection %

    05.12.13 738 661 601 0.17

    Progress as on 21-November-13

    Schedule: 44.81 % Actual: 41.55 %

    Progress as on 05-December-13 (2nd

    Week of Dec. 13)

    Schedule: 51.64 % Actual: 43.19 %

  • 8/13/2019 Aide Memoir 21 Nov 13

    4/5

    ide Mem oire

    7) Construction work volume:S. No Discipline UOM Original Scope

    (Proposal)

    Revised

    Scope

    %

    Variation

    1 Civil Foundation CUM 5352 4179 -21.92%

    2 Civil Building Work CUM 1516 1782 +17.55%

    3 Civil Column and Beams Nos. 885 697 -21.24%

    4 Paving Sq. m 1317 1317 0%

    5 Piping Fabrication ID 61300 61300 0%

    6 Piping Erection (Field Welding) ID 40860 40860 0%

    7 Piping Erection IM 231000 231000 0%

    8) Milestone StatusSr No Construction Mile Stones Baseline

    Date

    Actual

    Date

    Zero Date 05-Sep-13 05-Sep-13

    1 MS-4 Subcontract Award for Temporary Facilities (D+ 2 M) 07-Nov-13 07 Nov-13

    2 MS-5 Construction of Temporary Facilities Start (D + 4 M) 23-Nov-13 23-Nov-13

    3 MS-8 Construction Subcontract Award (D + 6 M) 19-Feb-13 07-Jan-13

    4 MS-12 Construction Start (D + 7 M) 05-Apr-13 09-Mar-13

    5 MS-19 Foundation Work Start (D + 11 M) 05-Apr-13 20-Mar-13

    6 MS-22 Civil Pipe rack Installation Start (D + 14 M) 27-Jun-13 28-Sept-13

    7 MS-25 A/G Piping Pre-fabrication Start (D + 17 M) 27-Aug-13 26-Aug-13

    8 MS-23 Start U/G Piping Installation (D + 14 M) 04-Oct-13

    9 MS-26 Piping Installation on Pipe Rack Start ( D + 19 M) 11-Nov-13 06-Nov-13

    10 MS-28 EGC Erection Complete (D + 21 M) 21-May-14

    11 MS-27 HRSG Erection Complete - All 3 Units (D + 22 M) 17-May-14

    12 MS-30 Air Fin Cooler Erection Complete (D + 21 M) 17-Jun-14

    13 MS-29 SS32/ITR Building Civil Works Complete (D + 21 M) 13-May-14

  • 8/13/2019 Aide Memoir 21 Nov 13

    5/5

    ide Mem oire

    9) Welder StatusTotal Welders Available : 37 nos

    Total Qualified : 37 Nos

    Under Mechanical Testing : 00 Nos

    Under Training : 00 Nos

    10) Critical Issues:General

    a) Availability of Visas for mobilization of work force.b) HMDI staff deputation for various disciplines as listed below:

    Execution Coordinator for Rotary Equipment. Material Controller E&I Coordinator

    c) Piping GAD for erectiond) Balance Pipe support Materialse) Prefabricated structure supply at site

    Mobilization of staff from HCPI:

    a) Construction Manager (Piping).b) Time- office staff.c) Resource Staff to mobilize the resources.d) Quantity Surveyor (Civil).e)

    Costing Engineer.f) Mobilization of balance equipment as per S3 i.e. 160 MT (1no) , 50MT (2 nos.) crane.

    g) Scaffold Materials, Scaffolding Incharge and Inspector11) Critical Drawings required from HMD

    Electrical SS-32 Equipment Layout

    Electrical Cable Tray/Trench layout for SS-32

    Electrical Power Layout for SS-32

    Electrical Earthing & Lightning protection Layout for SS-32 & ITR-32

    Electrical Power Layout for Unit -200

    Electrical Earthing & Lightning protection Layout for Unit-200

    Electrical Lighting Layout/ Street Lighting Layout for Unit-200

    SS ITR Building SS32/ITR32 SubstationGround Floor Plan

    SS ITR Building SS32/ITR32 SubstationFirst Floor Plan

    SS ITR Building SS32/ITR32 SubstationRoof Plan

    SS ITR Building SS32-ITR SubstationElevations

    SS ITR Building SS32/ITR32 SubstationSection Details (1/2)

    SS ITR Building SS32/ITR32 SubstationMiscellaneous Details (2/3)

    SS ITR Building SS32/ITR32 SubstationTransformer Foundation