AGM CONSTRUCTION REPORTFOR PERIOD ENDING xxxxx
Contract Title:
Contract Number
Contractor
Director
MBTA Project Manager:
Design Consultant (if applic.):
Contract Scope Summary Description:
NTP Actual Date Substantial Completion Date at NTP (Base)
Original Contract Duration Substantial Completion Date Forecast
Original Construction Value
Forecast Construction Value $0.00 Actual % Complete
Schedule Summary
Milestone Dates@ Award Current Milestone Dates
![Page 2: AGM REPORT Construction Excel Revised 2.22.12](https://reader036.vdocuments.mx/reader036/viewer/2022083011/5695cf761a28ab9b028e32b2/html5/thumbnails/2.jpg)
rev.1
AGM CONSTRUCTION REPORTFOR PERIOD ENDING xxxxx
Contract Title:
Schedule Exposure
Recovery Action
Describe Major Work in Progress
Issues/Action
Safety Issues or Incident that Occurred within Reporting Period
Outstanding Non Conformance Report
DBE Paid through Last %
![Page 3: AGM REPORT Construction Excel Revised 2.22.12](https://reader036.vdocuments.mx/reader036/viewer/2022083011/5695cf761a28ab9b028e32b2/html5/thumbnails/3.jpg)
rev.1
AGM CONSTRUCTION REPORTFOR PERIOD ENDING xxxxx
Contract Title:
$ -
$ -
$ -
$ - $ -
Total $ -
BUDGET SUMMARY
Task Budgets Cost-to-Complete
Design and Engineering $0 $0 $0 $0 $0 $0
Construction Contract(s) $0 $0 $0 $0 $0 $0
Construction Contingency $0 $0 $0 $0 $0 $0
Non-Contract Construction $0 $0 $0 $0 $0 $0
Land Acquisition $0 $0 $0 $0 $0 $0
Flagging/Force Account $0 $0 $0 $0 $0 $0
Inspection $0 $0 $0 $0 $0 $0
Project Administration $0 $0 $0 $0 $0 $0
Indirect Costs $0 $0 $0 $0 $0 $0
Credit $0 $0 $0 $0 $0 $0
Escalation $0 $0 $0 $0 $0 $0
Project Subtotal $0 $0 $0 $0 $0 $0
Project Contingency $0 $0 $0 $0 $0 $0
Total $0 $0 $0 $0 $0 $0
Grant(s):
Original Authorized
Budget
Current Authorized Budget
Forecast-to-Complete
Expenditures through 8/9/2011
Remaining Budget
![Page 4: AGM REPORT Construction Excel Revised 2.22.12](https://reader036.vdocuments.mx/reader036/viewer/2022083011/5695cf761a28ab9b028e32b2/html5/thumbnails/4.jpg)
rev.1
AGM CONSTRUCTION REPORTFOR PERIOD ENDING xxxxx
Contract Title:
CONSTRUCTION COST TO COMPLETE BUDGET WORKSHEET
Original Contract Award Value:
Executed Change Orders/CQV's in CMS
Pending Change Orders/CQV's in CMS
Total with executed & Pending Change Orders/CQV's in CMS $ -
Pending Change Orders not in CMS (list separately)
COR # Description
$
$
$
$
$
$
PENDING CHANGE ORDERS TOTAL VALUE $0.00
Pending Claims not in CMS
Claim # Description Anticipated Cost
$
$
$
$
PENDING CLAIM TOTAL VALUE $0.00
SUBTOTAL OF PENDING CHANGE ORDERS & CLAIMS NOT IN CMS $0.00
Forecast Cost to Complete Total $0.00
![Page 5: AGM REPORT Construction Excel Revised 2.22.12](https://reader036.vdocuments.mx/reader036/viewer/2022083011/5695cf761a28ab9b028e32b2/html5/thumbnails/5.jpg)
rev.1
AGM CONSTRUCTION REPORTFOR PERIOD ENDING xxxxx
Contract Title:
DESIGN COST TO COMPLETE BUDGET WORKSHEET
Original Contract Award Value: $
Executed Supplemental Agreements in CMS $
Pending Supplemental Agreements in CMS $
Total with executed & Pending Amendments in CMS $ -
Pending Amendments not in CMS (list separately)
SA# Description Anticipated Cost
$
$
$
$
$
PENDING AMENDMENTS TOTAL VALUE $0.00
Pending Claims not in CMS
Claim # Description Anticipated Cost
$
$
$
PENDING CLAIM TOTAL VALUE $0.00
SUBTOTAL OF PENDING AMENDMENTS /CLAIMS NOT IN CMS $0.00
Forecast Cost to Complete Total $0.00
![Page 6: AGM REPORT Construction Excel Revised 2.22.12](https://reader036.vdocuments.mx/reader036/viewer/2022083011/5695cf761a28ab9b028e32b2/html5/thumbnails/6.jpg)
rev.1
AGM CONSTRUCTION REPORTFOR PERIOD ENDING xxxxx
Contract Title:
CONSTRUCTION SCHEDULE REVIEW LOG
Project Name: Status Code*
1- Accepted
Contract #: 2- Accepted with Comments3- Revise & Resubmit
Schedule File Name Rev# Date Received Date Returned *Status Pymt#Spec / Submittal#
Description [ 90-day/
Baseline/ Update#]
Due Date by Contract
Accepted (Yes/ No)