agata pre-processing team report agata week, july 2008

18
AGATA Pre-processing team report AGATA Week, July 2008

Upload: marshall-walsh

Post on 13-Jan-2016

221 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: AGATA Pre-processing team report AGATA Week, July 2008

AGATA Pre-processing team report

AGATA Week, July 2008

Page 2: AGATA Pre-processing team report AGATA Week, July 2008

Overview of talk

• The team• Progress on carrier • Progress on mezzanines• Some problems fixed since AGATA week• Readiness for triple cluster tests

(October)• Finances• Timescales• Conclusion

Page 3: AGATA Pre-processing team report AGATA Week, July 2008

Reminder of team and responsibilities

• IPN Orsay– Carrier VHDL design (FPGA2- trigger distribution)– Carrier VHDL production code– Carrier commissioning (production run of 34 cards)– Original carrier design

• INFN Padua – Carrier rework (prototype and pre-production)– Carrier VHDL (release 0 for initial tests)– Carrier VHDL (FPGA 0- data readout)– Delivery of 6 tested carriers for October tests– GTS Mezzanine

• CSNSM Orsay– Segment mezzanine (hardware and VHDL)– Core mezzanine (hardware and VHDL)– Production run of core and segment mezzanines

• IPHC Strasbourg– Supply of MWD code for use in core and segment mezzanines in “black box”

format• STFC RAL and LPC CAEN

– VHDL code for carrier readout (PCIe and proprietry “FASTER” protocols)• Team size

– On average between 10 and 15 people are working on this project at the moment.

Page 4: AGATA Pre-processing team report AGATA Week, July 2008

Progress since last AGATA week-

Carrier • Carrier rework

– commissioning of prototype finished November 2007

– small revisions made to PCB layout Dec07/Jan08

– pre-production version manufactured. Delivered early April 2008

– pre-production version commissioned April; ready to use May 2008Photo- INFN Padova

Page 5: AGATA Pre-processing team report AGATA Week, July 2008

Progress since last AGATA week-

Carrier– JTAG test code written

(R.Matson, RAL)– VHDL code

development (Orsay and Padua)

– Test system set-up (Orsay)

– Carrier production run.• 5 cards from Padua-

PCB received, assembly started (due end July)

• Remaining cards (Orsay)- purchasing started. Problems with location of funding being resolved

Photo- INFN Padova

Page 6: AGATA Pre-processing team report AGATA Week, July 2008

Progress since last AGATA week-

Mezzanines

• Segment and Core Mezzanine rework– Commissioning of prototype v2.0

finished December 2007.– small revisions made to PCB layout

Dec07/Jan08 (v2.0 to v2.1)– Final v2.0 prototype tests on carrier

using BERT to validate high speed links Feb 2008 Padua.

– Pre-production version (v2.1) manufacturing started Feb 2008, Delivered April 2008 (3x core), May 2008 (10x segment)

– Commissioning for 1st pre-production version (v2.1) segment cards completed mid-May 2008

– pre-production version (v2.1) commissioning for core and 4 more segment cards due for completion end July 2008.

Photos- CSNSM Orsay

Page 7: AGATA Pre-processing team report AGATA Week, July 2008

Progress since last AGATA week-

Mezzanines

• Core and segment mezzanine production run.– Despite successful February BERT

tests, some improvements to MGT clock jitter have been found.

– Power supplies and clock routing are being modified before the full production run.

– Modifications tested on pre-production cards

• 10 more of the existing segment card design are being made now for October tests (€16k) They will be modified to include the same changes as will be made to the other cards

Photos- CSNSM Orsay

Page 8: AGATA Pre-processing team report AGATA Week, July 2008

Testing pre-production cards

• May– Carrier and 2 segment mezzanines available for test.– Digitiser set up in Padova

• Last week of May– first traces with pulser through digitiser and pre-processing

Page 9: AGATA Pre-processing team report AGATA Week, July 2008

Carefully attended by the LLP team, on May 22, 2008,

THE FIRST AGATA TRACEmade its way from the digitiser to theATCA-carrier, via segment mezzanine.

Page 10: AGATA Pre-processing team report AGATA Week, July 2008

Digitized, optically-transmitted

and pre-processed AGATA traces

May 28, 2008

Page 11: AGATA Pre-processing team report AGATA Week, July 2008

Testing pre-production cards

• May– Carrier and 2 segment mezzanines available for test.– Digitiser set up in Padova

• Last week of May– first traces with pulser through digitiser and pre-processing

• June– Investigate the 2 “unusual” traces

• End June- – Taking spectra with 1 segment card (6 ch) on 1 carrier using

AGATA detector and digitiser• Early July (now)-

– Connect 2 carrier cards and exchange trigger data• End July

– build up to full configuration (2 carrier cards, 6 segment cards, 1 core card, 1 GTS) for tests with 1 crystal and full digitiser.

Page 12: AGATA Pre-processing team report AGATA Week, July 2008

Progress since last AGATA week- fixing problems

• Fast serial- parallel readout mezzanine to carrier– Synchronisation problems

fixed- now working at full speed.

• Intermittent connection to carrier DPRAM– Used to test JTAG (blind test-

found faulty pin)– Discussions held with

assembly company to prevent recurrence

• Trace corruption seen in first results– Tracked down to a VHDL

error- now fixed– Resulted in stringent jitter

testing and improvements to mezzanines

Eye opening VS Patterns

0.00%

10.00%

20.00%

30.00%

40.00%

50.00%

60.00%

70.00%

80.00%

90.00%

Prbs7 Prbs23

Pattern

Eye

op

en

ing

(%

of

UI) Xilinx evb FX100

#1 v2.0 original

#2 v2.0 clk patch & PSfilter

#5 v2.1 clk patch

#5 v2.1 clk patch & PSfilter

#4 v2.1 clk patch

Plot from INFN Padova and CSNSM Orsay

Page 13: AGATA Pre-processing team report AGATA Week, July 2008

Readiness for Tests with Triple cluster in October.

Card Number needed

Existing Extra cards to be built

Funding Notes

Carrier 6 2 5 OK (Italy) PCB manufacture now; all assembled by late July (1 spare)

Seg mezz

18 10 10 Germany and GANIL

Delivery due early September. Tested cards due early October. Includes 2 spares.

Core mezz

3 3 0 n/a Testing now- due to complete testing end of July

GTS 3 5 (rev 2) 0 (final)

0 (rev 2) 3 (final)

OK (Italy) Rev 2 card is OK for these tests

TCLK 3 0 3 OK (IPN) Being manufactured now. 3 assembled boards due end July.

Page 14: AGATA Pre-processing team report AGATA Week, July 2008

Cost Savings

• Investigated using slower (cheaper) FPGAs on the mezzanines. Decided against this due to risk and also revised FPGA pricing.

• FPGA- Xilinx assisted pricing obtained. About 30% savings.

• Cut out segment offset fibres for LNL phase (€10k saving)

Page 15: AGATA Pre-processing team report AGATA Week, July 2008

Funding for production run

• Carrier– 2 pre-production + 5 cards funded from Italy, built in Italy– Remaining 34 cards (including 3 spares) will be built in France– Cost €178k– Some funds available in France– Missing funds coming from

• Germany (FPGA order) (complete)• Sweden funds transfer plus orders for PCBs and other FPGAs (not complete)

• Core and segment mezzanines– All 140 (108 segment + 18 core + spares) will be built in France– Cost €310k – Some funds available in France – Missing funds coming from

• Germany (FPGA Order) (complete)• Loan from GANIL (EXOGAM) against future funds transfer, (loan complete)

Page 16: AGATA Pre-processing team report AGATA Week, July 2008

Compare to planned timescales

Jan 2007 Report

Nov 2007 Report July 2008 Report

Carrier update Layout Phase Done Q1 2007

Segment & core mezzanine update

Start of layout phase

Done Q1 2007

Expect to get prototypes of both by July 2007

Deliver prototypes July 2007

Delivered July 2007 (Carrier and segment mezzanine*)

Test prototypes Autumn 2007 Expected to complete Nov. 2007

Completed Nov- Dec 2007

Designs finalised Dec 2007 Expected to complete Nov - Dec. 2007

Dec 2007-Jan 2008

Production beginning 2008 (phased delivery)

Phased, starting beginning of 2008

Pre-production cards early 2008

Pre-production cards delivered April/May 2008

Pre-production tests complete March 2008 May 2008

Build up system- test 1 cluster

July 2008

1st Phase production (triple cluster)

Commissioning Apr 2008 onwards

Manufacture now. Commissioning July-Sept 2008

2nd Phase production (5 triple clusters)

Ready now- depends on funds. End 2008?

VHDL and software 1st Release Autumn 08

1st Release Autumn 08* Core mezzanine prototype assembly was delayed until tests were complete on segment mezzanine. Designs were ready for delivery in July 2007 if required.

Page 17: AGATA Pre-processing team report AGATA Week, July 2008

Conclusions

• Timescales are tight but with continued hard work the triple cluster test date Oct 2008 is achievable (but there is no schedule contingency)

• Funding has been a big problem- its in the wrong place and significant effort has been diverted into moving it to where it can be used.

• Bigger spend on travel than expected.• Huge amount of work by the whole pre-processing

team:– Long periods spent away from home by some people

working in Padua.– Long hours were worked over the last 18 months by some

members of the pre-processing team.• Significant progress has been made with end to end

tests, but we’ve still got more to do so we need to keep up or even increase the effort.

Page 18: AGATA Pre-processing team report AGATA Week, July 2008

Thanks

• Thank you to the pre-processing team for their very hard work!