  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    1/86

    A Boeing Licensed 3rdParty STC Provider

    MD80SF, MSN 49470, N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    2/86

    Conversion Progress, MSN 49470, N73444

    Jul 15, 2011

    These images show replacement skins being installed on the upper,forward and aft jambs.

    replacement skin.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    3/86

    Conversion Progress, MSN 49470, N73444

    Jul 15, 2011

    Inside view of the replacement skins being riveted.

    The first image shows the cavernous interior of the.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    4/86

    Conversion Progress, MSN 49470, N73444

    Jul 22, 2011Mechanics are in the process of installing the lower replacement skin.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    5/86

    Conversion Progress, MSN 49470, N73444

    Jul 22, 2011Work continues to fasten the replacement skin to framesand stringers.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    6/86

    Conversion Progress, MSN 49470, N73444

    Jul 29, 2011Mechanics have completed the installation of the Main Cargo Doorsurround skins.

    .

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    7/86

    Conversion Progress, MSN 49470, N73444

    Jul 29, 2011The new upper header and frames are being installed.

    The image on the right shows the area just below the.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    8/86

    Conversion Progress, MSN 49470, N73444

    Au ust 5, 2011The Main Cargo Door surround skin replacement is now complete.

    Mechanics have installed the upper jamb and are currently installing.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    9/86

    Conversion Progress, MSN 49470, N73444

    Au ust 5, 2011The left image shows a detailed image of the upper jamblooking forward.

    area where the new lower jamb will go.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    10/86

    Conversion Progress, MSN 49470, N73444

    Au ust 12, 2011The Main Cargo Door surround skin replacement is now complete.

    Mechanics have installed the upper jamb and are currently installing.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    11/86

    Conversion Progress, MSN 49470, N73444

    Au ust 19, 2011The Surround Skin Installation 90% complete pendingFS455 splices.

    -skins) pending BL0 intercostal.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    12/86

    Conversion Progress, MSN 49470, N73444

    Au ust 19, 2011The Lower jamb installation 80% complete, floor beam splicescomplete, lower jamb frames installed.

    ,1-2 weeks (excluding inner skins).

    Main Cargo Door Hinge has been received, will start install nextweek.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    13/86

    Conversion Progress, MSN 49470, N73444

    Au ust 26, 2011The hinge installation to upper jamb has started.

    Upper jamb is complete with the exception of the S-1.

    Surround Skin installation is 90% complete with theexception of a few splices which are in work.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    14/86

    Conversion Progress, MSN 49470, N73444

    Au ust 26, 2011The side jamb installation is 90% complete with the exception of theintercostals in window belt area.

    .

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    15/86

    Conversion Progress, MSN 49470, N73444

    Se tember 2, 2011The Main Deck Cargo Door opening has now been cut.

    Upper and side jambs are now complete.

    .

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    16/86

    Conversion Progress, MSN 49470, N73444

    Se tember 2, 2011Mechanics are beginning work on the installation of the centerlineseat track.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    17/86

    Conversion Progress, MSN 49470, N73444

    Se tember 9, 2011The Main Deck Cargo Door opening has now been cut.

    Window plugs have been manufactured and will be.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    18/86

    Conversion Progress, MSN 49470, N73444

    Se tember 9, 2011Mechanics are beginning work on the installation of the centerlineseat track.

    .

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    19/86

    Conversion Progress, MSN 49470, N73444

    Se tember 16, 2011Lower jamb, shear plate and door area seat track installationcompleted.

    .

    Centerline seat track installation started.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    20/86

    Conversion Progress, MSN 49470, N73444

    Se tember 23, 2011Centerline seat track installation is 90% complete.

    Final work being completed on the upper, lower jamb and skin,

    installation conformity.

    Heavy maintenance check on aircraft has started, fuel tank workbeing accomplished.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    21/86

    Conversion Progress, MSN 49470, N73444

    Se tember 30, 2011Window plug installation is nearing completion.

    Air ducts are being reinstalled.

    .

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    22/86

    Conversion Progress, MSN 49470, N73444

    Se tember 30, 2011Centerline seat track is now installed.

    Fwd cargo hold frame modification is now complete.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    23/86

    Conversion Progress, MSN 49470, N73444

    October 7, 2011Window plug installation is completed.

    Interior hat channel clips being installed.

    .

    Cabin air shutoff valve has been installed.Upper, lower, side jamb, surround skin no change.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    24/86

    Conversion Progress, MSN 49470, N73444

    October 7, 2011Floor panels are being modified for center seat track.

    Fwd lower frame modification has been completed.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    25/86

    Conversion Progress, MSN 49470, N73444

    October 14, 2011Interior ceiling support angles are being installed.

    Interior sidewall channels are being installed.

    .

    Seat track installation is complete.Duct modification is complete.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    26/86

    Conversion Progress, MSN 49470, N73444

    October 14, 2011Window plug installation is complete.

    Smoke detection and cabin light wiring harness installation is.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    27/86

    Conversion Progress, MSN 49470, N73444

    October 21, 2011Main Deck Cargo Door surround structure conformity in progress.

    Main Deck ceiling support installation is complete.

    .

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    28/86

    Conversion Progress, MSN 49470, N73444

    October 21, 2011Fwd lower cargo hold frame modification is now complete.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    29/86

    Conversion Progress, MSN 49470, N73444

    October 28, 2011Main deck vent panels being installed.

    Main Deck Ceiling support installation is now complete.

    .

    Floor panels being reinstalled

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    30/86

    Conversion Progress, MSN 49470, N73444

    October 28, 2011Smoke detector and cabin light harness installation complete.

    Blow out panel covers installed.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    31/86

    Conversion Progress, MSN 49470, N73444

    November 4, 2011Main Deck Cargo Door surround structure is now complete.

    The Main Deck Cargo Door will be installed the week of Novemberth.

    Interior sub structure is now complete, we will begin to install the sidewall liner and ceiling panels the week of November 7th.

    i

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    32/86

    Conversion Progress, MSN 49470, N73444

    November 4, 2011Floor beam strain gage testing is now complete.

    Testing was successful and yielded better than expected results.

    C i P MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    33/86

    Conversion Progress, MSN 49470, N73444November 11, 2011

    Main Deck Surround is now complete.

    Mechanics will begin installing the cargo door early next week.

    C i P MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    34/86

    Conversion Progress, MSN 49470, N73444November 11, 2011

    Interior liner and ceiling support is now complete.

    Mechanics will begin installing the liner later next week.

    C i P MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    35/86

    Conversion Progress, MSN 49470, N73444November 18, 2011

    Main Deck Cargo Door is now being installed.

    Window plugs are being sealed.

    Con ersionProgress MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    36/86

    Conversion Progress, MSN 49470, N73444November 18, 2011

    Main Deck Cargo Door outer skin is being installed.

    Main Deck air outlets are being installed.

    ConversionProgress MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    37/86

    Conversion Progress, MSN 49470, N73444December 2, 2011

    Main Deck Cargo Door installation continues.

    ConversionProgress MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    38/86

    Conversion Progress, MSN 49470, N73444December 9, 2011

    Main Deck Cargo Door has been removed and is being used to fitcheck the door tooling at Universal Cargo Door, AEIs primarymanufacturin facilit in Miami.

    Window plugs have been externally sealed.

    Overhauled landing gear has been reinstalled.

    ConversionProgress MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    39/86

    Conversion Progress, MSN 49470, N73444December 9, 2011

    Main Deck air distribution outlets have been installed.

    Main Deck aft compartment close out structure has been installed.

    ,power will be energized next week.

    ConversionProgress MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    40/86

    Conversion Progress, MSN 49470, N73444December 16, 2011

    Main Deck Cargo Door has been removed and is being used to fitcheck the door tooling at Universal Cargo Door, AEIs primarymanufacturin facilit in Miami.

    Mechanics have begun to install the decompression covers.

    ConversionProgress MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    41/86

    Conversion Progress, MSN 49470, N73444December 16, 2011

    Main Deck Cargo Door is being checked on the manufacturingtooling.

    the smoke detectors and the new LED lights.

    ConversionProgress MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    42/86

    Conversion Progress, MSN 49470, N73444December 30, 2011

    Main Cargo Door has been reattached.

    All Main Cargo Door tooling has been checked with the as built parts.

    ConversionProgress MSN49470 N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    43/86

    Conversion Progress, MSN 49470, N73444December 30, 2011

    Main Deck ceiling panels have been installed.

    Each ceiling panel contains one smoke detector and one LED flood.

    Liner support has been installed around the over wing emergencyexits.

    ConversionProgress,MSN49470,N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    44/86

    Conversion Progress, MSN 49470, N73444Januar 6, 2012

    The prototype MD80SF is now being prepared for paint.

    Mechanics are sealing the exterior seams with sealant.

    ConversionProgress,MSN49470,N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    45/86

    Conversion Progress, MSN 49470, N73444Januar 6, 2012

    Main Deck Cargo Door inner skins are being located and drilled.

    Ceiling panel installation is now complete.

    continues.

    The Ancra Cargo Loading System has now arrived in Miami and iscurrently being inspected.

    ConversionProgress,MSN49470,N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    46/86

    Conversion Progress, MSN 49470, N73444Januar 13, 2012

    9G attachment hardware installation is now complete.

    Main Cargo Door inner skins are being installed.

    .

    Main Cargo Door wiring and hydraulic installation has begun.

    ConversionProgress,MSN49470,N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    47/86

    Conversion Progress, MSN 49470, N73444Januar 13, 2012

    Main Deck cargo liner installation has begun.

    Main Deck ceiling panel installation is now complete.

    Conversion Progress, MSN 49470, N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    48/86

    g , ,Januar 13, 2012

    Floor reinforcement in the door area continues.

    Main Deck emergency over wing door surround structure is now.

    Conversion Progress, MSN 49470, N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    49/86

    g , ,Januar 20, 2012

    Main Deck Cargo Door floor reinforcement is still in work.

    Main Deck vent door assembly is being installed.

    ,rigging is now being installed.

    Main Deck Cargo door collective locking mechanism is beinginstalled.

    Conversion Progress, MSN 49470, N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    50/86

    g , ,Januar 20, 2012

    Main Deck interior liner has been fitted and is being installed.

    Secondary main landing gear switch has been installed.

    .

    Conversion Progress, MSN 49470, N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    51/86

    gJanuar 27, 2012

    Main Deck Cargo Door Hydraulics are being installed.

    9G Solid barrier floor attach points are installed.

    .

    Main Deck floor reinforcements are being completed.

    Conversion Progress, MSN 49470, N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    52/86

    Januar 27, 2012

    Aft liner close outs are being completed.

    Over wing emergence exit close outs are now complete.

    Conversion Progress, MSN 49470, N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    53/86

    Februar 3, 2012

    Main Deck Cargo Door Hydraulics have been installed and tested.

    Main Deck interior close out continues.

    Conversion Progress, MSN 49470, N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    54/86

    Februar 3, 2012

    Solid 9G barrier is in the process of being installed.

    Main Deck Cargo Door Vent Door installation continues.

    Conversion Progress, MSN 49470, N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    55/86

    Februar 10, 2012

    Main Deck Cargo Door operating hydraulically.

    9G barrier is now installed.

    Conversion Progress, MSN 49470, N73444

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    56/86

    Februar 10, 2012

    Main Deck Cargo Door collective locking system installed.

    Main Deck Cargo Door indicating system installed.

    .

    Conversion Progress, MSN 49470, N73444b 20 2

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    57/86

    Februar 17, 2012

    Work on cargo door systems continues.

    Inspection hole covers being installed.

    .

    View ports are now installed.

    Main Deck Cargo Door electrical is now complete.

    Conversion Progress, MSN 49470, N73444Fb 17 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    58/86

    Februar 17, 2012

    Supernumerary area seat is being located.

    Entry door covers are being reinstalled.

    Conversion Progress, MSN 49470, N73444Fb 24 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    59/86

    Februar 24, 2012

    Main Deck Cargo Door locking, latching and vent door systemscomplete.

    .

    Conversion Progress, MSN 49470, N73444Fb 24 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    60/86

    Februar 24, 2012

    9Gg barrier sliding door is being installed.

    Supernumerary area sidewall and door trim is being installed.

    .

    Over wing doors are being covered.

    Conversion Progress, MSN 49470, N73444March2 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    61/86

    March 2, 2012

    Main Deck Cargo Door hydraulics are now complete.

    Main Deck Cargo Door latch cover is manufactured and awaiting.

    Conversion Progress, MSN 49470, N73444March2 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    62/86

    March 2, 2012

    Main Deck liner and ceiling panels are installed.

    Supernumerary area is in the final design phase.

    Conversion Progress, MSN 49470, N73444March9 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    63/86

    March 9, 2012

    Main Deck Cargo Door is nearing completion.

    Main Deck ceiling panels have been taken down to allow for.

    Conversion Progress, MSN 49470, N73444March9 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    64/86

    March 9, 2012

    Hydraulic panel has been installed just aft of the L1 door along thefuselage.

    of the 9G barrier.

    The 9G sliding door has been installed. This image allows you to seethe decompression vent system that has been installed in the door.

    Conversion Progress, MSN 49470, N73444March16 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    65/86

    March 16, 2012

    Main Deck floors are being closed and sealed.

    Main Deck Cargo Door is now completed.

    Conversion Progress, MSN 49470, N73444March16 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    66/86

    March 16, 2012

    9G barrier is now complete.

    Ancra Cargo Loading System is scheduled to be installed next week.

    .

    Conversion Progress, MSN 49470, N73444March23 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    67/86

    March 23, 2012

    Main Deck floors are now closed and sealed.

    Ancra Cargo Loading System is now installed and conformed.

    .

    Conversion Progress, MSN 49470, N73444March23 2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    68/86

    March 23, 2012

    Forward section of the Ancra Cargo Loading System.

    Conversion Progress, MSN 49470, N73444March30,2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    69/86

    March 30, 2012

    Supernumerary area ceiling and side wall panels are being installed.

    Main Deck wiring conformity is nearing completion.

    Conversion Progress, MSN 49470, N73444A

    ril 20,2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    70/86

    A ril 20, 2012

    Engines have been installed on the Worlds First MD80SF andtechnicians are preparing for the test flight which is expected to take

    lace in the next two to three weeks.

    Conversion Progress, MSN 49470, N73444A

    ril 20,2012

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    71/86

    A ril 20, 2012

    The MD80SF Main Deck Cargo Door is now operating under its ownpower and has successfully completed extensive cycle testing.

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    72/86

    AEI MD80SF

    12 Pallet ConfigurationFreighter Conversion

    72

    AEI MD80SF 12 Pallet ConfigurationFrei hter Conversion Ima

    es

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    73/86

    73

    AEI MD80SF 12 Pallet ConfigurationFrei hter Conversion Details

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    74/86

    74

    AEI MD80SF 12 Pallet ConfigurationFrei hter Conversion Details

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    75/86

    12 POSITION

    88 L X 108 W X 78H

    CONTAINER/PALLETS

    8 POSITION

    125L X 88 W X 78H

    NETTED PALLETS

    75

    AEI MD80SF 12 Pallet ConfigurationULD Details

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    76/86

    78 78

    108 88or

    8 POSITION

    AEI MD-80SF 88 x 125 ULD 459 cuft

    PALLETS

    12 POSITION

    AEI MD-80SF 88 x 108 ULD 378 cuft

    CONTAINERS/PALLETS

    76

    AEI MD80SF 12 Pallet ConfigurationSu

    ernumerar Area

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    77/86

    Conversion price includes two

    supernumerary seats located

    near the L1doorTwo addition supernumeraryseats may be added on thefwd side of the 9G for anadditional fee

    w ry ava ory an cur a nare added

    Fwd galley retained

    L1 and R1 slides removedCockpit Door retained

    77

    AEI MD80SF 12 Pallet ConfigurationCar

    o Loadin S

    stem

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    78/86

    Ancra International is the exclusive supplier of MD80SF 12 PalletConfiguration Cargo Loading Systems (CLS) to AEI. The basic CLS, Ancra partnumber 84130-10 is included in the conversion rice, additionalconfigurations are available for an additional fee.

    PN 84130-10, (12) 88X108 Basic CLS

    78

    AEI MD80SF 12 Pallet ConfigurationCar

    o Loadin S

    stem

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    79/86

    PN 84130-11, (12) 88X108 + (8) 125X88 full time

    - ,

    79

    AEI MD80SF 12 Pallet ConfigurationFrei hter Position Wei hts and Container Sizes

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    80/86

    an ar x a n ec argo ompar men os ons

    P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12

    Netted Pallet 88X108 88X108 88X108 88X108 88X108 88X108 88X108 88X108 88X108 88X108 88X108 88X108

    Dimensions 77"H 77"H 77"H 77"H 77"H 77"H 77"H 77"H 77"H 77"H 77"H 77"H

    Container

    Dimensions

    88X108

    78"H

    88X108

    78"H

    88X108

    78"H

    88X108

    78"H

    88X108

    78"H

    88X108

    78"H

    88X108

    78"H

    88X108

    78"H

    88X108

    78"H

    88X108

    78"H

    88X108

    78"H

    88X108

    78"H

    80

    AEI MD80SF 12 Pallet ConfigurationFrei hter Wei hts and Ran

    es

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    81/86

    MD-82SF MD-83SF MD-88SF

    MAXIMUM TAKEOFF WEIGHT POUNDS 149,500 160,000 149,500

    KILOGRAMS 67,812 72,575 67,812

    ZERO FUEL WEIGHT POUNDS 122,000 122,000 122,000

    , , ,

    OPERATING WEIGHT EMPTY POUNDS 74,976 76,686 74,976

    (ESTIMATED) KILOGRAMS 34,009 34,785 34,009

    MAXIMUM STRUCTURAL PAY LOAD POUNDS 47,024 45,314 47,024

    (ESTIMATED) KILOGRAMS 21,330 20,554 21,330

    USABLE FUEL CAPACITY U.S. GALLONS 5,846 6,981 5,846

    LITERS 22,129 26,426 22,129

    . , , ,

    KILOGRAMS 17,766 21,216 17,766

    81

    AEI MD80SF 12 Pallet ConfigurationFrei hter Wei hts and Volumes

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    82/86

    MD-82SF MD-83SF MD-88SF

    OPERATING WEIGHT EMPTY POUNDS 74,976 76,686 74,976

    (ESTIMATED) KILOGRAMS 34,009 34,785 34,009

    MAXIMUM STRUCTURAL PAY LOAD POUNDS 47,024 45,314 47,024

    (ESTIMATED) KILOGRAMS 21,330 20,554 21,330

    CARGO VOLUME LOWER CUBIC FEET 1,253 1,013 1,253

    LOWERCOMPARTMENTS - BULK CUBIC METERS 35.50 28.70 35.50

    CARGO VOLUME MAIN DECK

    ULD'S (88X108 CONTAINER) QTY 12 12 12

    AVG ULD WEIGHT POUNDS 3,919 3,776 3,919

    , , ,

    ULD'S (88X125 NETTED PALLET) QTY 8 8 8

    AVG ULD WEIGHT POUNDS 5,878 5,664 5,878

    TOTAL VOLUME CUBIC FEET 3,564 3,564 3,564

    82

    AEI MD80SF 12 Pallet ConfigurationFrei hter Pa

    load / Ran

    e Chart

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    83/86

    83

    AEI MD80SF 12 Pallet ConfigurationFrei hter Certification

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    84/86

    84

    AEI MD80SF 12 Pallet ConfigurationSummar

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    85/86

    12 position 88x108 Container or Netted Pallet

    8 position 125 x 88 ULDs longitudinally oriented

    8 position 125 x 96 ULDs longitudinally oriented

    4,000-5,000 lb average position weight limit

    48,000 lbs typical payload

    83x136 Main Deck Cargo door

    9g rigid cargo barrier / smoke barrier with hinged door

    Low profile, 1.25 Ancra International cargo loading system

    Minimal floor reinforcement required

    Main deck converted to Class E Cargo Compartment, with independentsmoke detection system

    Cabin windows replaced with lightweight aluminum window plugs

    High reliability, 28VDC, independent hydraulic systemUp to 4 Supernumerary Seats

    *Preliminary Specifications, subject to change.

    85

    Contact Information

  • 7/22/2019 AEI MD80SF Conversion Progress.pdf

    86/86