aei md80sf conversion progress.pdf
TRANSCRIPT
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
1/86
A Boeing Licensed 3rdParty STC Provider
MD80SF, MSN 49470, N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
2/86
Conversion Progress, MSN 49470, N73444
Jul 15, 2011
These images show replacement skins being installed on the upper,forward and aft jambs.
replacement skin.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
3/86
Conversion Progress, MSN 49470, N73444
Jul 15, 2011
Inside view of the replacement skins being riveted.
The first image shows the cavernous interior of the.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
4/86
Conversion Progress, MSN 49470, N73444
Jul 22, 2011Mechanics are in the process of installing the lower replacement skin.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
5/86
Conversion Progress, MSN 49470, N73444
Jul 22, 2011Work continues to fasten the replacement skin to framesand stringers.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
6/86
Conversion Progress, MSN 49470, N73444
Jul 29, 2011Mechanics have completed the installation of the Main Cargo Doorsurround skins.
.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
7/86
Conversion Progress, MSN 49470, N73444
Jul 29, 2011The new upper header and frames are being installed.
The image on the right shows the area just below the.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
8/86
Conversion Progress, MSN 49470, N73444
Au ust 5, 2011The Main Cargo Door surround skin replacement is now complete.
Mechanics have installed the upper jamb and are currently installing.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
9/86
Conversion Progress, MSN 49470, N73444
Au ust 5, 2011The left image shows a detailed image of the upper jamblooking forward.
area where the new lower jamb will go.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
10/86
Conversion Progress, MSN 49470, N73444
Au ust 12, 2011The Main Cargo Door surround skin replacement is now complete.
Mechanics have installed the upper jamb and are currently installing.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
11/86
Conversion Progress, MSN 49470, N73444
Au ust 19, 2011The Surround Skin Installation 90% complete pendingFS455 splices.
-skins) pending BL0 intercostal.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
12/86
Conversion Progress, MSN 49470, N73444
Au ust 19, 2011The Lower jamb installation 80% complete, floor beam splicescomplete, lower jamb frames installed.
,1-2 weeks (excluding inner skins).
Main Cargo Door Hinge has been received, will start install nextweek.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
13/86
Conversion Progress, MSN 49470, N73444
Au ust 26, 2011The hinge installation to upper jamb has started.
Upper jamb is complete with the exception of the S-1.
Surround Skin installation is 90% complete with theexception of a few splices which are in work.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
14/86
Conversion Progress, MSN 49470, N73444
Au ust 26, 2011The side jamb installation is 90% complete with the exception of theintercostals in window belt area.
.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
15/86
Conversion Progress, MSN 49470, N73444
Se tember 2, 2011The Main Deck Cargo Door opening has now been cut.
Upper and side jambs are now complete.
.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
16/86
Conversion Progress, MSN 49470, N73444
Se tember 2, 2011Mechanics are beginning work on the installation of the centerlineseat track.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
17/86
Conversion Progress, MSN 49470, N73444
Se tember 9, 2011The Main Deck Cargo Door opening has now been cut.
Window plugs have been manufactured and will be.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
18/86
Conversion Progress, MSN 49470, N73444
Se tember 9, 2011Mechanics are beginning work on the installation of the centerlineseat track.
.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
19/86
Conversion Progress, MSN 49470, N73444
Se tember 16, 2011Lower jamb, shear plate and door area seat track installationcompleted.
.
Centerline seat track installation started.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
20/86
Conversion Progress, MSN 49470, N73444
Se tember 23, 2011Centerline seat track installation is 90% complete.
Final work being completed on the upper, lower jamb and skin,
installation conformity.
Heavy maintenance check on aircraft has started, fuel tank workbeing accomplished.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
21/86
Conversion Progress, MSN 49470, N73444
Se tember 30, 2011Window plug installation is nearing completion.
Air ducts are being reinstalled.
.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
22/86
Conversion Progress, MSN 49470, N73444
Se tember 30, 2011Centerline seat track is now installed.
Fwd cargo hold frame modification is now complete.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
23/86
Conversion Progress, MSN 49470, N73444
October 7, 2011Window plug installation is completed.
Interior hat channel clips being installed.
.
Cabin air shutoff valve has been installed.Upper, lower, side jamb, surround skin no change.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
24/86
Conversion Progress, MSN 49470, N73444
October 7, 2011Floor panels are being modified for center seat track.
Fwd lower frame modification has been completed.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
25/86
Conversion Progress, MSN 49470, N73444
October 14, 2011Interior ceiling support angles are being installed.
Interior sidewall channels are being installed.
.
Seat track installation is complete.Duct modification is complete.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
26/86
Conversion Progress, MSN 49470, N73444
October 14, 2011Window plug installation is complete.
Smoke detection and cabin light wiring harness installation is.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
27/86
Conversion Progress, MSN 49470, N73444
October 21, 2011Main Deck Cargo Door surround structure conformity in progress.
Main Deck ceiling support installation is complete.
.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
28/86
Conversion Progress, MSN 49470, N73444
October 21, 2011Fwd lower cargo hold frame modification is now complete.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
29/86
Conversion Progress, MSN 49470, N73444
October 28, 2011Main deck vent panels being installed.
Main Deck Ceiling support installation is now complete.
.
Floor panels being reinstalled
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
30/86
Conversion Progress, MSN 49470, N73444
October 28, 2011Smoke detector and cabin light harness installation complete.
Blow out panel covers installed.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
31/86
Conversion Progress, MSN 49470, N73444
November 4, 2011Main Deck Cargo Door surround structure is now complete.
The Main Deck Cargo Door will be installed the week of Novemberth.
Interior sub structure is now complete, we will begin to install the sidewall liner and ceiling panels the week of November 7th.
i
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
32/86
Conversion Progress, MSN 49470, N73444
November 4, 2011Floor beam strain gage testing is now complete.
Testing was successful and yielded better than expected results.
C i P MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
33/86
Conversion Progress, MSN 49470, N73444November 11, 2011
Main Deck Surround is now complete.
Mechanics will begin installing the cargo door early next week.
C i P MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
34/86
Conversion Progress, MSN 49470, N73444November 11, 2011
Interior liner and ceiling support is now complete.
Mechanics will begin installing the liner later next week.
C i P MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
35/86
Conversion Progress, MSN 49470, N73444November 18, 2011
Main Deck Cargo Door is now being installed.
Window plugs are being sealed.
Con ersionProgress MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
36/86
Conversion Progress, MSN 49470, N73444November 18, 2011
Main Deck Cargo Door outer skin is being installed.
Main Deck air outlets are being installed.
ConversionProgress MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
37/86
Conversion Progress, MSN 49470, N73444December 2, 2011
Main Deck Cargo Door installation continues.
ConversionProgress MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
38/86
Conversion Progress, MSN 49470, N73444December 9, 2011
Main Deck Cargo Door has been removed and is being used to fitcheck the door tooling at Universal Cargo Door, AEIs primarymanufacturin facilit in Miami.
Window plugs have been externally sealed.
Overhauled landing gear has been reinstalled.
ConversionProgress MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
39/86
Conversion Progress, MSN 49470, N73444December 9, 2011
Main Deck air distribution outlets have been installed.
Main Deck aft compartment close out structure has been installed.
,power will be energized next week.
ConversionProgress MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
40/86
Conversion Progress, MSN 49470, N73444December 16, 2011
Main Deck Cargo Door has been removed and is being used to fitcheck the door tooling at Universal Cargo Door, AEIs primarymanufacturin facilit in Miami.
Mechanics have begun to install the decompression covers.
ConversionProgress MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
41/86
Conversion Progress, MSN 49470, N73444December 16, 2011
Main Deck Cargo Door is being checked on the manufacturingtooling.
the smoke detectors and the new LED lights.
ConversionProgress MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
42/86
Conversion Progress, MSN 49470, N73444December 30, 2011
Main Cargo Door has been reattached.
All Main Cargo Door tooling has been checked with the as built parts.
ConversionProgress MSN49470 N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
43/86
Conversion Progress, MSN 49470, N73444December 30, 2011
Main Deck ceiling panels have been installed.
Each ceiling panel contains one smoke detector and one LED flood.
Liner support has been installed around the over wing emergencyexits.
ConversionProgress,MSN49470,N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
44/86
Conversion Progress, MSN 49470, N73444Januar 6, 2012
The prototype MD80SF is now being prepared for paint.
Mechanics are sealing the exterior seams with sealant.
ConversionProgress,MSN49470,N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
45/86
Conversion Progress, MSN 49470, N73444Januar 6, 2012
Main Deck Cargo Door inner skins are being located and drilled.
Ceiling panel installation is now complete.
continues.
The Ancra Cargo Loading System has now arrived in Miami and iscurrently being inspected.
ConversionProgress,MSN49470,N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
46/86
Conversion Progress, MSN 49470, N73444Januar 13, 2012
9G attachment hardware installation is now complete.
Main Cargo Door inner skins are being installed.
.
Main Cargo Door wiring and hydraulic installation has begun.
ConversionProgress,MSN49470,N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
47/86
Conversion Progress, MSN 49470, N73444Januar 13, 2012
Main Deck cargo liner installation has begun.
Main Deck ceiling panel installation is now complete.
Conversion Progress, MSN 49470, N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
48/86
g , ,Januar 13, 2012
Floor reinforcement in the door area continues.
Main Deck emergency over wing door surround structure is now.
Conversion Progress, MSN 49470, N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
49/86
g , ,Januar 20, 2012
Main Deck Cargo Door floor reinforcement is still in work.
Main Deck vent door assembly is being installed.
,rigging is now being installed.
Main Deck Cargo door collective locking mechanism is beinginstalled.
Conversion Progress, MSN 49470, N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
50/86
g , ,Januar 20, 2012
Main Deck interior liner has been fitted and is being installed.
Secondary main landing gear switch has been installed.
.
Conversion Progress, MSN 49470, N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
51/86
gJanuar 27, 2012
Main Deck Cargo Door Hydraulics are being installed.
9G Solid barrier floor attach points are installed.
.
Main Deck floor reinforcements are being completed.
Conversion Progress, MSN 49470, N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
52/86
Januar 27, 2012
Aft liner close outs are being completed.
Over wing emergence exit close outs are now complete.
Conversion Progress, MSN 49470, N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
53/86
Februar 3, 2012
Main Deck Cargo Door Hydraulics have been installed and tested.
Main Deck interior close out continues.
Conversion Progress, MSN 49470, N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
54/86
Februar 3, 2012
Solid 9G barrier is in the process of being installed.
Main Deck Cargo Door Vent Door installation continues.
Conversion Progress, MSN 49470, N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
55/86
Februar 10, 2012
Main Deck Cargo Door operating hydraulically.
9G barrier is now installed.
Conversion Progress, MSN 49470, N73444
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
56/86
Februar 10, 2012
Main Deck Cargo Door collective locking system installed.
Main Deck Cargo Door indicating system installed.
.
Conversion Progress, MSN 49470, N73444b 20 2
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
57/86
Februar 17, 2012
Work on cargo door systems continues.
Inspection hole covers being installed.
.
View ports are now installed.
Main Deck Cargo Door electrical is now complete.
Conversion Progress, MSN 49470, N73444Fb 17 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
58/86
Februar 17, 2012
Supernumerary area seat is being located.
Entry door covers are being reinstalled.
Conversion Progress, MSN 49470, N73444Fb 24 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
59/86
Februar 24, 2012
Main Deck Cargo Door locking, latching and vent door systemscomplete.
.
Conversion Progress, MSN 49470, N73444Fb 24 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
60/86
Februar 24, 2012
9Gg barrier sliding door is being installed.
Supernumerary area sidewall and door trim is being installed.
.
Over wing doors are being covered.
Conversion Progress, MSN 49470, N73444March2 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
61/86
March 2, 2012
Main Deck Cargo Door hydraulics are now complete.
Main Deck Cargo Door latch cover is manufactured and awaiting.
Conversion Progress, MSN 49470, N73444March2 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
62/86
March 2, 2012
Main Deck liner and ceiling panels are installed.
Supernumerary area is in the final design phase.
Conversion Progress, MSN 49470, N73444March9 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
63/86
March 9, 2012
Main Deck Cargo Door is nearing completion.
Main Deck ceiling panels have been taken down to allow for.
Conversion Progress, MSN 49470, N73444March9 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
64/86
March 9, 2012
Hydraulic panel has been installed just aft of the L1 door along thefuselage.
of the 9G barrier.
The 9G sliding door has been installed. This image allows you to seethe decompression vent system that has been installed in the door.
Conversion Progress, MSN 49470, N73444March16 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
65/86
March 16, 2012
Main Deck floors are being closed and sealed.
Main Deck Cargo Door is now completed.
Conversion Progress, MSN 49470, N73444March16 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
66/86
March 16, 2012
9G barrier is now complete.
Ancra Cargo Loading System is scheduled to be installed next week.
.
Conversion Progress, MSN 49470, N73444March23 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
67/86
March 23, 2012
Main Deck floors are now closed and sealed.
Ancra Cargo Loading System is now installed and conformed.
.
Conversion Progress, MSN 49470, N73444March23 2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
68/86
March 23, 2012
Forward section of the Ancra Cargo Loading System.
Conversion Progress, MSN 49470, N73444March30,2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
69/86
March 30, 2012
Supernumerary area ceiling and side wall panels are being installed.
Main Deck wiring conformity is nearing completion.
Conversion Progress, MSN 49470, N73444A
ril 20,2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
70/86
A ril 20, 2012
Engines have been installed on the Worlds First MD80SF andtechnicians are preparing for the test flight which is expected to take
lace in the next two to three weeks.
Conversion Progress, MSN 49470, N73444A
ril 20,2012
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
71/86
A ril 20, 2012
The MD80SF Main Deck Cargo Door is now operating under its ownpower and has successfully completed extensive cycle testing.
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
72/86
AEI MD80SF
12 Pallet ConfigurationFreighter Conversion
72
AEI MD80SF 12 Pallet ConfigurationFrei hter Conversion Ima
es
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
73/86
73
AEI MD80SF 12 Pallet ConfigurationFrei hter Conversion Details
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
74/86
74
AEI MD80SF 12 Pallet ConfigurationFrei hter Conversion Details
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
75/86
12 POSITION
88 L X 108 W X 78H
CONTAINER/PALLETS
8 POSITION
125L X 88 W X 78H
NETTED PALLETS
75
AEI MD80SF 12 Pallet ConfigurationULD Details
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
76/86
78 78
108 88or
8 POSITION
AEI MD-80SF 88 x 125 ULD 459 cuft
PALLETS
12 POSITION
AEI MD-80SF 88 x 108 ULD 378 cuft
CONTAINERS/PALLETS
76
AEI MD80SF 12 Pallet ConfigurationSu
ernumerar Area
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
77/86
Conversion price includes two
supernumerary seats located
near the L1doorTwo addition supernumeraryseats may be added on thefwd side of the 9G for anadditional fee
w ry ava ory an cur a nare added
Fwd galley retained
L1 and R1 slides removedCockpit Door retained
77
AEI MD80SF 12 Pallet ConfigurationCar
o Loadin S
stem
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
78/86
Ancra International is the exclusive supplier of MD80SF 12 PalletConfiguration Cargo Loading Systems (CLS) to AEI. The basic CLS, Ancra partnumber 84130-10 is included in the conversion rice, additionalconfigurations are available for an additional fee.
PN 84130-10, (12) 88X108 Basic CLS
78
AEI MD80SF 12 Pallet ConfigurationCar
o Loadin S
stem
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
79/86
PN 84130-11, (12) 88X108 + (8) 125X88 full time
- ,
79
AEI MD80SF 12 Pallet ConfigurationFrei hter Position Wei hts and Container Sizes
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
80/86
an ar x a n ec argo ompar men os ons
P1 P2 P3 P4 P5 P6 P7 P8 P9 P10 P11 P12
Netted Pallet 88X108 88X108 88X108 88X108 88X108 88X108 88X108 88X108 88X108 88X108 88X108 88X108
Dimensions 77"H 77"H 77"H 77"H 77"H 77"H 77"H 77"H 77"H 77"H 77"H 77"H
Container
Dimensions
88X108
78"H
88X108
78"H
88X108
78"H
88X108
78"H
88X108
78"H
88X108
78"H
88X108
78"H
88X108
78"H
88X108
78"H
88X108
78"H
88X108
78"H
88X108
78"H
80
AEI MD80SF 12 Pallet ConfigurationFrei hter Wei hts and Ran
es
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
81/86
MD-82SF MD-83SF MD-88SF
MAXIMUM TAKEOFF WEIGHT POUNDS 149,500 160,000 149,500
KILOGRAMS 67,812 72,575 67,812
ZERO FUEL WEIGHT POUNDS 122,000 122,000 122,000
, , ,
OPERATING WEIGHT EMPTY POUNDS 74,976 76,686 74,976
(ESTIMATED) KILOGRAMS 34,009 34,785 34,009
MAXIMUM STRUCTURAL PAY LOAD POUNDS 47,024 45,314 47,024
(ESTIMATED) KILOGRAMS 21,330 20,554 21,330
USABLE FUEL CAPACITY U.S. GALLONS 5,846 6,981 5,846
LITERS 22,129 26,426 22,129
. , , ,
KILOGRAMS 17,766 21,216 17,766
81
AEI MD80SF 12 Pallet ConfigurationFrei hter Wei hts and Volumes
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
82/86
MD-82SF MD-83SF MD-88SF
OPERATING WEIGHT EMPTY POUNDS 74,976 76,686 74,976
(ESTIMATED) KILOGRAMS 34,009 34,785 34,009
MAXIMUM STRUCTURAL PAY LOAD POUNDS 47,024 45,314 47,024
(ESTIMATED) KILOGRAMS 21,330 20,554 21,330
CARGO VOLUME LOWER CUBIC FEET 1,253 1,013 1,253
LOWERCOMPARTMENTS - BULK CUBIC METERS 35.50 28.70 35.50
CARGO VOLUME MAIN DECK
ULD'S (88X108 CONTAINER) QTY 12 12 12
AVG ULD WEIGHT POUNDS 3,919 3,776 3,919
, , ,
ULD'S (88X125 NETTED PALLET) QTY 8 8 8
AVG ULD WEIGHT POUNDS 5,878 5,664 5,878
TOTAL VOLUME CUBIC FEET 3,564 3,564 3,564
82
AEI MD80SF 12 Pallet ConfigurationFrei hter Pa
load / Ran
e Chart
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
83/86
83
AEI MD80SF 12 Pallet ConfigurationFrei hter Certification
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
84/86
84
AEI MD80SF 12 Pallet ConfigurationSummar
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
85/86
12 position 88x108 Container or Netted Pallet
8 position 125 x 88 ULDs longitudinally oriented
8 position 125 x 96 ULDs longitudinally oriented
4,000-5,000 lb average position weight limit
48,000 lbs typical payload
83x136 Main Deck Cargo door
9g rigid cargo barrier / smoke barrier with hinged door
Low profile, 1.25 Ancra International cargo loading system
Minimal floor reinforcement required
Main deck converted to Class E Cargo Compartment, with independentsmoke detection system
Cabin windows replaced with lightweight aluminum window plugs
High reliability, 28VDC, independent hydraulic systemUp to 4 Supernumerary Seats
*Preliminary Specifications, subject to change.
85
Contact Information
-
7/22/2019 AEI MD80SF Conversion Progress.pdf
86/86
Robert T. ConveyVice President Sales & Marketing
Mobile: +1-818-406-3666
86