adu construction process (in pictures)
DESCRIPTION
Building an Accessory Dwelling Unit is not procedurally different than building a new house. This slideshow shows the building process step by step.TRANSCRIPT
Accessory Dwelling Unit:
Construction
Start to FinishApril 2011-Septemeber 2011
3D Model
Excavation
Excavation
Excavation
Excavation
Concrete Forms
Concrete Foundation Walls
Gravel
Vapor Barrier
Rigid Foam, Rebar, and Pex Tubing for Radiant Heat
Concrete Slab
Utilities: Sewer and drainage pipes
Utilities: Water
Utilities: Electrical
Utilities: Gas
Platform Framing
Balloon Framing
Framing: Windows
Framing: Stairs
Framing: Roof
Framing: Sheathing
Roofing
Weather and Air Resistant Barrier
Rough Plumbing
Mechanical: (eg. Heat Recovery Ventilator)
Mechanical: Tankless Water Heater
COLD WATER IN
HOT WATER OUT
Mechanical: Radon Mitigation
Lighting and Electric
Air Sealing
Insulation: Batts
Insulation: Closed Cell Spray Foam
Insulation: Blown in
Drywall (aka Sheetrock)
Drywall: Mudding, Sanding, Priming
Shingles & Rain Screen
Siding
Staining and Sealing Concrete Flooring
Reused Flooring
Tiling
Painting
Cabinets & Shelving
Finish Plumbing
Finish Electrical and Lighting
Certificate of Occupancyand Moving In
Modifications