    Alcatel BSS

    Replace X BTS with Y BTS,

    Same Abis Port

    O&M Documentation

    Scenario

    3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    2/38

    Status RELEASED

    Short title MPI 74 / 02 7

    All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel.

    BLANK PAGE BREAK

    2 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    3/38

    Contents

    Contents

    Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

    1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9

    1.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.1.1 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 101.1.2 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.1.3 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.1.4 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

    1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131.2.1 Prerequisites . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131.2.2 Site Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131.2.3 External Tasks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

    1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 141.4 Telecom / Supervision Outage and Operating Impact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 161.5 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

    1.5.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18

    1.5.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 191.5.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19

    2 Scenario . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

    2.1 Before Going On-site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 222.2 Before You Start . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 222.3 Scenario Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

    2.3.1 Initial Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.3.2 Add New BTS(s) on Another Abis Link (C6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 232.3.3 Create PRC for Moving Cells . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 242.3.4 New BTS Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272.3.5 BTS Replacement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 272.3.6 Check and Finishing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32

    2.4 Reverse Procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 342.4.1 BTS Replacement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 342.4.2 Check and Finishing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37

    3BK 17416 0742 RJZZA Ed.03 3 / 38

  • 7/31/2019 add new BTS

    4/38

    Figures

    Figures

    Figure 1: Replace X BTS with Y BTS, Same Abis Port . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12

    4 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    5/38

    Tables

    Tables

    Table 1: Sites / Personnel / Duration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

    Table 2: Traffic / Supervision Outage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

    3BK 17416 0742 RJZZA Ed.03 5 / 38

  • 7/31/2019 add new BTS

    6/38

    Tables

    6 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    7/38

    Preface

    Preface

    Purpose This scenario gives the procedure for replacing one or several BTS with one orseveral other BTS, using the same Abis ports of Alcatel BSC. BSC must be attechnical release level B7.2, and connected to Alcatel 1353-RA OMC-R in B7.2.

    Audience This scenario is intended for:

    Field service technicians

    Specialists

    Project managers

    Foremen

    Assumed Knowledge The reader must have a general knowledge of:

    For planning purpose:

    Network architecture and reshuffling principles

    Basic knowledge for scheduling.

    For realization purpose:

    Alcatel operations and maintenance concepts for BSS

    Alcatel 1353-RA OMC-R

    Equipment (BSC, BTS, ... ) hardware configurations

    Windows environment

    3BK 17416 0742 RJZZA Ed.03 7 / 38

  • 7/31/2019 add new BTS

    8/38

    Preface

    8 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    9/38

    1 Overview

    1 Overview

    This chapter gives information needed for project managers and foremen, forpresentation to the customer and site planning.

    3BK 17416 0742 RJZZA Ed.03 9 / 38

  • 7/31/2019 add new BTS

    10/38

    1 Overview

    1.1 Presentation

    This scenario is applicable if:

    Abis characteristics are unchanged (no chain to ring change, no

    terrestrial to via satellite change, ...).

    The new BTSs will be placed on the same Abis link like the replaced ones.

    The scenario covers also the case when the new BTSs have more TREs

    and sectors than the replaced BTSs and is necessary to use a additional

    free Abis link to place one or several new BTSs.

    The new BTSs offer the same functional capabilities as the replaced BTSs

    (i.e. signaling link multiplexing, full/dual rate, ciphering, antenna

    diversity, ... are unchanged).

    If new BTSs have, in total, more or less sectors and TREs than the replaced

    BTSs, then the impacted cells are changed during the scenario. For

    instance, create new cell or change normal cell to shared cell. The methoddoesnt cover the changing of cell type. This action must be done after

    replacing of BTSs using the appropriate method.

    If Abis links are via satellite:

    BTS must be without GPRS,

    BTS must not be G1 or G2 BTS,

    Ater link must not be via satellite.

    1.1.1 CasesThe following cases apply:

    C1: New antennas for the new BTSs (at least for the new sectors)

    C2: Old antennas reused for new BTSs (at least for some sectors)

    C3: Changed configuration (i.e. the new BTSs have, in total, more/less

    sectors/TREs than the replaced BTSs)

    C4: Replaced BTS have downstream BTSs

    C5: Replaced and/or new BTS have shared cell(s)

    C5a: Replaced BTS have shared cell(s) (2 PRCs are needed forlogical reconfiguration)

    C5b: New BTS have shared cell(s) (additional PRC is needed for

    reverse procedure)

    C6: Not enough resources on same Abis for all new BTSs

    (i.e.synchronized BTSs).

    Note: Several cases could be combined at the same time.

    Replaced BTS could have upstream BTS too.

    10 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    11/38

    1 Overview

    1.1.2 Options

    The following options apply :

    O1: BTS software download is done locally into the new BTS, to minimizeoutage, in case of EVOLIUM BTS (A9100 BTS or A910 Micro BTS)

    3BK 17416 0742 RJZZA Ed.03 11 / 38

  • 7/31/2019 add new BTS

    12/38

    1 Overview

    1.1.3 Restrictions

    The following restrictions apply:

    All synchronized BTSs must be replaced at the same time, i.e. this method

    does not cover case of replacing only part of synchronized BTS.

    Cell type change or cell merging (900 & 1800) to multiband cell, is not

    allowed during this scenario.

    If new BTS is G1 or G2 BTS, this scenario do not foreseen transmission

    parameters update inside the BTS (as Qmux address and TS). Correct

    values must be used during Abis and BTS creation from OMC-R.

    1.1.4 Grouped Task Sequence

    Initial Checks

    OMCR Site BTS Site

    C6: Add new BTS(s)

    on another Abis link

    Shutdown Cells

    Create PRC for

    Moving Cells

    New BTS(s)

    Preparation

    BTSReplacement

    (Outage)

    Preparation

    BTS Replacement

    Check and Finishing

    Figure 1: Replace X BTS with Y BTS, Same Abis Port

    Note: Respect the synchronization points. Everything above and contained by thesynchronization point must be completed before continuing.

    12 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    13/38

    1 Overview

    1.2 Preparation

    1.2.1 Prerequisites

    The following prerequisites apply:

    Enough resources on the BSS (BSC, Ater, MFS, ...) to support the new

    BTS and its cells.

    The new BTSs are already installed, powered and commissioned in

    B7.2 (enough place on BTS site for replaced BTSs + new BTSs). If new

    antennas are not already connected on the new BTS, these have to be

    foreseen with loads. If needed, clock synchronization cables are already

    installed and connected.

    Replaced BTSs are co-localized (replaced and new BTSs on the same

    BTS site).

    When the same Abis is not enough for all new BTSs, then the second Abis

    link must be already installed, tested and connected (if is a new link).

    1.2.2 Site Specific Information

    The following specific information is needed to complete the scenario:

    At OMC-R, availability of a workstation, with servers "User Name" and

    password, allowing network configuration

    Input: Customers reports about the final Abis, BTS and cells configuration

    (free Abis port to be used if there are not enough resources on the same

    Abis, Qmux parameters, BTS name, LAC / CI, power for cells, HO &

    adjacency, GPRS parameters for new cells, ... )

    If new BTSs are G1 or G2 BTS, this scenario do not foreseen transmission

    parameters update inside the BTS (as Qmux address and TS). Correct

    values must be known for Abis and BTS creation from OMC-R.

    1.2.3 External Tasks

    The following external tasks are needed during the scenario:

    For C3 case (if new or deleted cell), during PRC activation, MSC staff has

    to update MSC data base

    At the end, replaced BTS dismounting and shift new BTS to final place

    (could be done later by another team).

    3BK 17416 0742 RJZZA Ed.03 13 / 38

  • 7/31/2019 add new BTS

    14/38

    1 Overview

    1.3 Scheduling

    Time based on Technical constraintsThe number of resources in following table does not take into account individualcustomer or safety requirements.

    Grouped Task OMC-R BTS Time / Task

    Initial Checks 1 op

    20

    20

    C6: Add New BTSs onAnother Abis Link

    1 op

    C6: +15

    C6: +15

    Create PRC for Moving

    Cells

    1 op

    20

    C3: up to +18/Cell +2/Adj

    20

    C3: up to +18/Cell +2/Adj

    New BTS Preparation

    (parallel task)

    1 com team

    3/BTS

    C1: +13/Sect

    O1: +8/BTS

    (3/BTS)

    ( C1: +13/Sect)

    (O1: +8/BTS)

    Shut Down Cells 1 op

    6

    C4, C6:+4

    6

    C4, C6: +4

    New BTS Creation onSame Abis

    1 op

    3 +1/Cell +1/SS +15/BTS

    3 +1/Cell +1/SS+15/BTS

    End PRC Preparationand Activate PRC

    1 op

    7 +1/Cell +1/SS

    7 +1/Cell +1/SS

    Cabling BTS andUnlock Traffic onDownstream BTSs

    (parallel task)

    6+ 2(if O1)+ 15 (exceptO1)

    C2:+5

    C4: +3

    1 com team

    10/Abis

    C2: +2+18/SectC6:10

    (6+10/Abis+ 2(if O1)+15(except O1))

    C2: +7 +18/Sect

    C4: +3

    C6: +10

    Unlock Cells 1 op

    3

    3

    Check 1 op

    5/Cell

    1 com team

    5/Cell

    5/Cell

    Finishing 1 op

    17

    17

    14 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    15/38

    1 Overview

    Grouped Task OMC-R BTS Time / Task

    1 com team

    2

    2Replaced BTS PowerOff

    (parallel task)

    Add about 2h per BTS, for replaced BTSdismounting

    TOTAL TIME 90 +7/Cell +2/SS+1/BTS

    C2: add 7 +18/Sect

    C3: add up to +18/Cell +2/Adj

    C4: add 7

    C6: add 10

    O1: subtract 13 (BTS software downloaded locally)

    Table 1: Sites / Personnel / Duration

    Durations are given in minutes

    op = OMC-R operator, com team = commissioning team

    Sect = Sector, SS= Secondary Sector, Adj = Adjacency link

    Example 1 For C3 +C2+C6 (replace 1 BTS 3x4 with 2 BTS 3x6 and oldantennas reused) total duration is about 3h 10(considering that tasks are donein parallel and cells with FH and GPRS, without BTS dismounting).

    Example 2 For C3+C2 (replace 2 BTS 3x6 with 2 BTS 3x8 and old antennas

    reused) total duration is about 3h (considering that tasks are done in paralleland cells with FH and GPRS, without dismounting).

    Note: Parallel tasks:

    Grouped Task Create PRC for Moving Cells (Section 2.3.3) could be

    performed in parallel with New BTS Preparation (Section 2.3.4), in order

    to reduce total duration.

    Grouped Tasks New BTS Creation on Same Abis(Section 2.3.5.2) andEnd

    PRC Preparation and Activate PRC (Section 2.3.5.3) must be performed in

    parallel with Cabling BTS and Unlock Traffic on Downstream BTSs (Section

    2.3.5.4 ), in order to reduce outage duration.

    3BK 17416 0742 RJZZA Ed.03 15 / 38

    http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-
  • 7/31/2019 add new BTS

    16/38

    1 Overview

    1.4 Telecom / Supervision Outage and Operating Impact

    Following table describes the traffic outage and loss of supervision causedby the concerned Grouped tasks.

    Out.Ref. Grouped Task Tel/GPRS Out 1

    Tel/GPRSOut 2 (if C4) Sup. Out Oper. Impact Impacts ...

    Initial Checks - - -

    C6:Not enoughresources onsame Abis link

    - - -

    Create PRC forMoving Cells

    - - -

    New BTS

    Preparation(parallel task)

    - - -

    1

    2

    Shut Down Cells 6

    C4: +4

    C4:+4 2

    C4:+1

    1

    2

    New BTSCreation onSame Abis

    2 +1/Cell +1/SS+15/BTS

    2 +1/Cell+1/SS+15/BTS

    2+1/Cell+1/SS+15/BTS

    1

    2

    End PRC

    Preparation andActivate PRC

    7+1/Cell +1/SS 7+1/Cell

    +1/SS

    7+1/Cell

    +1/SS

    1

    2

    Cabling BTS andUnlock Trafficon DownstreamBTSs

    (parallel task)

    (6+10 /Abis)+15

    C2: +7 +18/Sect

    C4: +3

    C6: +10

    (6+10/Abis)

    C4: +3

    C6: +10

    (6+10/Abis)

    C4: +3

    C6: +10

    Supervisionoutage duringAbis cabling(from lock tounlock BTSO&M)

    1 Unlock Cells 3 - - -

    Traffic outageon all cellsof replacedBTSs and ondownstreamBTSs (fromShut DownCells toUnlock Cells)

    Check - - -

    Finishing - - -

    16 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    17/38

    1 Overview

    Out.Ref. Grouped Task Tel/GPRS Out 1

    Tel/GPRSOut 2 (if C4) Sup. Out Oper. Impact Impacts ...

    Replaced BTSPower Off

    - - -

    TOTAL Outage 1:

    33 +2/Cell +2/SS +15/BTS

    C2: +7 +18/Sect

    C4: +7

    C6: +10

    O1: -13

    Outage 2:

    16 +2/Cell +2/SS+15/BTS

    C2: +1/Sect

    C6: +10

    Supervision Outage:

    18 +2/Cell +2/SS+15/BTS

    C2: +1/Sect

    C6: +10

    Table 2: Traffic / Supervision Outage

    Durations are given in minutes (with case C1, without option)

    Sect = Sector, SS= Secondary Sector, Adj= Adjacency link

    Outage 1: on replaced BTS cells

    Outage 2: on downstream BTS cells (if C4)

    Example 1 For C3+C2 (replace 1 BTS 3x4 with 2 BTS 3x6 and old antennasreused) outage duration is about 1h (considering that tasks are done in parallel)

    Example 2 For C3+C2 (replace 2 BTS 3x6 with 2 BTS 3x8 and old antennasreused) outage duration is about 1h (considering that tasks are done in parallel).

    3BK 17416 0742 RJZZA Ed.03 17 / 38

  • 7/31/2019 add new BTS

    18/38

    1 Overview

    1.5 Resources

    1.5.1 Tools

    Following tables describe the needed hardware, software tools and forms.

    Hardware tools

    Item Part Number Use at ...

    BTS terminal (PC with CD drive and cables) - BTS

    Installation tools (for Abis cabling and antennaconnection)

    - BTS

    Mobile phone, eventually biband, for calls test - BTS

    Software Tools

    Item Part Number Use at ...

    BTS Terminal software B7.2 - BTS

    A9100 / A910 BTS software files (for O1option)

    - BTS

    INSPATxx CD, where xx is the versionassociated to current document edition.

    Remember that this document must not beused with a paper version. It is an on-linedocumentation, using hyper-text links towardsbelow applicable documents (all these aresupported on the same CD-ROM). All wordsin italic are hyper-text links.

    BTS, OMC-R

    Forms

    Item Part Number Use at ...

    None

    18 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    19/38

    1 Overview

    1.5.2 Supplies

    Following table describes the needed supplies.

    Item Part Number Contents Use at ...

    Topology regarding operation Must be provided by thecustomer

    OMC-R, BTS

    1.5.3 Applicable Documents

    You need the following documents to complete this scenario:

    B7.2 BSS Methods Handbook

    A1353-RA Surveillance Handbook

    A1353-RA Configuration Handbook

    Network Reconfiguration Recommendations

    BTS Terminal User Guide

    3BK 17416 0742 RJZZA Ed.03 19 / 38

  • 7/31/2019 add new BTS

    20/38

    1 Overview

    20 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    21/38

    2 Scenario

    2 Scenario

    This chapter presents all checks needed before beginning the scenario, and alldetailed tasks to be performed on each site.

    3BK 17416 0742 RJZZA Ed.03 21 / 38

  • 7/31/2019 add new BTS

    22/38

    2 Scenario

    2.1 Before Going On-site

    Before going on-site, you must check the following information and suppliesare available:

    All Prerequisites (Section 1.2.1) are fulfilled

    The customer has been informed:

    Date

    Time

    Site name

    Site address

    Purpose of operation has been indicated.

    Personnel are available and ready for operation (Refer to Scheduling

    (Section 1.3))

    Site Specific Information (Section 1.2.2) is available and ready for operation

    Tools (Section 1.5.1) are available and ready for operation

    Supplies (Section 1.5.2) are available and ready for operation

    Applicable Documents (Section 1.5.3) is available and ready for operation

    Ensure that the method used at the BSS site is at the same level as at OMC-R.

    2.2 Before You Start

    Perform:

    Check that all Prerequisites (Section 1.2.1) are fulfilled

    Well check the availability of all necessary tools and material

    Inform the operator.

    Required Knowledge You must be familiar with the following:

    Safety Rules and Precautions

    Telecom / Supervision Outage and Operating Impact (Section 1.4)

    Reverse Procedure

    Grouped Task Sequence (Section 1.1.4)

    BSS Operating Hints

    How to document Faults and Anomalies.

    22 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    23/38

    2 Scenario

    2.3 Scenario Description

    The detailed tasks for Replacing X BTS with Y BTS, using same Abis ports onBSC, are described below.

    2.3.1 Initial Checks

    Note Task Description Site To do Outage

    Perform an Audit Alarm State on theimpacted BSS

    OMC-R 10 None

    View Status of Managed Objects andAlarms on the impacted BTSs (replacedand downstream BTS, if any). Display CellReport for the impacted cells. Print thereports.

    OMC-R 8 None

    Perform Checking for Sufficient Resourceson Abisto be sure final configuration couldbe supported.

    OMC-R 2 None

    2.3.2 Add New BTS(s) on Another Abis Link (C6)

    Note Task Description Site To do Outage

    OMC-R 6 NoneC6

    Input

    If there are not available resources on

    other Abis link, then Create Abis Chain /Ring

    Parameters:

    Set TRE Allocation Mode to Automatic

    Change Abis Connection Type to Via

    satellite, if needed.

    If created Abis has to support G1 or G2

    BTS, set Qmux TS

    In case of ring set S Bit_TS and R

    Bit_TS

    Wait for transmission programming flag changesfrom Abis to Idle

    OMC-R 8 NoneC6

    Input

    Create BTSor Copy and Paste a BTS (forthe Paste action do not forget to changethe BTS name and the Qmux address).

    If error message appears, performChecking for Sufficient Resources on Abis

    Wait for transmission programming flag changesfrom Abis to Idle

    C6

    Input

    Check added BTS appears in RadioConfiguration Browser (SC).

    Set Commercial Usage of BTS, if needed

    OMC-R 1 None

    3BK 17416 0742 RJZZA Ed.03 23 / 38

  • 7/31/2019 add new BTS

    24/38

    2 Scenario

    If new BTS is G1 or G2 BTS, this scenario do not foreseen transmissionparameters update inside the BTS (as Qmux address and TS). Correct valuesmust be used during Abis and BTS creation from OMC-R.

    2.3.3 Create PRC for Moving Cells

    Note: This grouped task could be done in parallel with New BTS Preparation (Section2.3.4) grouped task, to reduce total duration.

    2.3.3.1 PRC Preparation

    Note Task Description Site To do Outage

    Create PRC (Backup PRC) OMC-R 1 None

    Input Copy OMC Cells to PRC for the impactedcells, from SC to Backup PRC. AttachedBTSs (to be replaced) are also copied

    OMC-R 1 None

    Display Adjacencies Report for eachimpacted cells, and take note of adjacentcells.

    Then Copy OMC Cells to PRCand CopyExternal Cells to PRC (Backup PRC) forall these adjacent cells (to keep trace ofall adjacencies)

    OMC-R 5 None

    Check PRC(check all, without forcing celladministrative state) on Backup PRC

    OMC-R 2 None

    Close PRC (Backup PRC) OMC-R 1 None

    Create PRC (PRC1) OMC-R 1 None

    Copy OMC Cells to PRC and CopyExternal Cells to PRC for all cells fromBackup PRC to PRC1

    OMC-R 1 None

    Create PRC (PRC2) OMC-R 1 None

    Copy OMC Cells to PRC for the movedcells, from PRC1 to PRC2

    OMC-R 1 None

    Delete OMC Cell from PRC (in PRC2)for all cells mapped on replaced BTSs

    OMC-R 1 None

    Check PRC(check all, without forcing celladministrative state) on PRC2

    OMC-R 2 None

    C5a In PRC1, Unlink a Cell from a SecondaryBTS Sector for each shared cell, from thereplaced BTSs.

    OMC-R 1 None

    24 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    25/38

    2 Scenario

    Note Task Description Site To do Outage

    In PRC1, Unmap Cell from a BTS Sector,for all impacted cells, from the replacedBTSs.

    OMC-R 1 None

    In PRC1Remove BTS from PRC(replaced BTSs)

    OMC-R 2 None

    2.3.3.2 PRC Preparation in case of Delete TRX(s) (C3)

    Following tasks are also applicable to delete a secondary sector.

    Note Task Description Site To do Outage

    C3

    Input

    For each TRX to be deleted, Delete TRX(in PRC1)

    OMC-R 1/Cell None

    C3

    Input

    Modify Frequency Hopping System orDelete Frequency Hopping System (inPRC1) to be coherent with deleted TRXs,if needed

    OMC-R 1/Cell None

    C3

    Input

    Delete Radio Frequency (in PRC1) to becoherent with deleted TRXs

    OMC-R 1/Cell None

    OMC-R 1 NoneC3 Click on [Apply and Check] to save cellmodifications in PRC1, then click on

    [Close] to exit the Edit cell window.

    If error message appears, check andcorrect the cell parameters.

    If the cell has secondary TRX, an error messageappears because there is no secondary sectorlinked with the cell. Do not take care about it.

    2.3.3.3 PRC Preparation in case of Delete Cell(s) (C3)

    Note Task Description Site To do Outage

    C3

    Input

    If the new BTSs have less cells than thereplaced BTSs, Delete OMC Cell from

    PRC in PRC1

    OMC-R 1/Cell None

    2.3.3.4 PRC Preparation in case of Add Cell(s) or Add TRX(s) (C3)

    Following tasks are also applicable to add a secondary sector.

    Note Task Description Site To do Outage

    C3

    Input

    Create Provisioning Cell or Duplicate Cell(in PRC1), if new cells.

    OMC-R 2/Cell None

    3BK 17416 0742 RJZZA Ed.03 25 / 38

  • 7/31/2019 add new BTS

    26/38

    2 Scenario

    Note Task Description Site To do Outage

    OMC-R 5/Cell NoneC3

    Input

    Set Cell Telecom Parameters (in PRC1),if new cell

    Notice: To have GPRS on the cell GPRS

    Pref.mark must be different from 0.Also, there are some parameters to be set (thatare not filled when GPRS is created on the cell):

    Routing Area Color

    Routing Area Code

    Max_PDCH (must be different from 0 to have

    GPRS on cell).

    The operator can also modifies Min_PDCH andMax_Pdch_High_Load parameters.

    C3

    Input

    Create Radio Frequency (in PRC1) OMC-R 1/Cell None

    C3

    Input

    Create Frequency Hopping System orModify Frequency Hopping System inPRC1, if needed

    OMC-R 2/Cell None

    C3

    Input

    Create TRX(in PRC1). Change status toSecondary, if needed.

    OMC-R 1/Cell None

    C3

    Input

    Configure Logical Channels (in PRC1) OMC-R 1/Cell None

    C3

    Input

    Configure TRX Channel Hopping Law inPRC1, if needed

    OMC-R 1/Cell None

    C3

    Input

    Specify TRX Preference (in PRC1) OMC-R 1/Cell None

    C3

    Input

    Create Adjacency in PRC1, includingadjacency parameters, if new cell

    OMC-R 2/Adj None

    OMC-R 1 NoneC3 Click on [Apply and Check] to save cellmodifications in PRC1, then click on[Close] to exit the Edit cell window.

    If error message appears, check andcorrect the cell parameters.

    If the cell has secondary TRX, an error messageappears because there is still no secondary sectorlinked with the cell. Do not take care about it.

    26 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    27/38

    2 Scenario

    2.3.4 New BTS Preparation

    Note: This grouped task could be done in parallel with Create PRC for Moving Cells(Section 2.3.3) grouped task, to reduce total duration.

    Note Task Description Site To do Outage

    BTS 3/BTS NoneInput

    Exch

    If new BTS is EVOLIUM BTS (A9100 /A910), set SUM parameters using:

    Initial Settings(for Qmux address)

    Set the SUM Board Configuration (for

    OMU TS selection)

    Set values communicated by OMC-R team.

    C1 If not already done during commissioning,connect new antennas (in place of loads)to the new BTS

    BTS 8/Sect None

    BTS 8/BTS NoneO1

    Exch

    Locally Load SW on A9100 / 910 BTS

    Check software version to be downloaded, withOMC-R, using Display BSS Software Information

    C1 If new BTS is EVOLIUM BTS(A9100/A910), Measure VSWR:

    If result is lower or equal than 1.3,

    choose VSWR Threshold Alarm

    Definition with 0.6 margin, then click on

    [Confirm thresholds] to update RI.

    If result is higher than 1.3, test with a

    50 Ohms load and check feeder and

    antenna.

    BTS 2/Sect None

    Exch Inform OMC staff new BTSs are ready BTS / OMC-R 1 None

    If new BTS is G1 or G2 BTS, this scenario do not foreseen transmissionparameters update inside the BTS (as Qmux address and TS). Correct valuesare used during Abis and BTS creation from OMC-R.

    2.3.5 BTS Replacement

    2.3.5.1 Shut Down Cells

    Note Task Description Site To do Outage

    Shut Down Cell Traffic (WTC=3) on allreplaced BTSs

    OMC-R 3 START 1

    OMC-R 3 START 2C4

    C6

    Shut Down Cell Traffic (WTC=3) on alldownstream BTSs, including downstreamBTSs for the new added BTS(s) on the

    second Abis link

    Perform all shutdown actions in parallel, in order

    to reduce telecom outage

    3BK 17416 0742 RJZZA Ed.03 27 / 38

  • 7/31/2019 add new BTS

    28/38

    2 Scenario

    Note Task Description Site To do Outage

    If GPRS on cells Lock GPRS Traffic onCell for all cells on replaced BTSs and onall downstream BTSs

    OMC-R 1 Outage 1

    Outage 2

    Lock BTS O&M Capabilityon all replacedBTSs

    OMC-R 1 Outage 1

    Outage 2

    C4

    C6

    Lock BTS O&M Capability on alldownstream BTSs, including downstreamBTSs for the new added BTS(s) on thesecond Abis link

    OMC-R 1 Outage 1

    Outage 2

    Exch Inform staff on BTS sites to start Abis linkconnection

    OMC-R 1 Outage 1

    Outage 2

    2.3.5.2 New BTS Creation on Same Abis

    Note: This grouped task must be done in parallel with Cabling BTS andUnlock Trafficon Downstream BTSs (Section 2.3.5.4 ) grouped task, to reduce outageduration.

    Note Task Description Site To do Outage

    Activate PRC(PRC2) without forcing celladministrative state

    OMC-R 1 +1/Cell+1/SS

    Outage 1

    Outage 2

    OMC-R 7/BTS Outage 1

    Outage 2

    Input Delete BTS from OMC-R(replaced BTSs).Delete first slave BTSs then master BTSsin case of synchronized BTSs

    Wait for transmission programming flag changesfrom Abis to Idle

    OMC-R 8/BTS Outage 1

    Outage 2

    Input Create BTSor Copy and Paste a BTS,then set BTS name, Qmux address andSlave status, if needed, for each new BTS.Create first master BTSs then slave BTSs,in case of new synchronized BTSs.

    Wait for transmission programming flag changesfrom Abis to Idle

    C6

    Input

    Modify BTS Characteristics to reconfigurenew BTS to Slave status, if needed

    OMC-R 1 Outage 1

    Outage 2

    Input Check new BTSs appear in RadioConfiguration Browser (SC).

    Set Commercial Usage of BTS if needed.

    OMC-R 1 Outage 1

    Outage 2

    28 / 38 3BK 17416 0742 RJZZA Ed.03

    http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-
  • 7/31/2019 add new BTS

    29/38

    2 Scenario

    2.3.5.3 End PRC Preparation and Activate PRC

    Note: This grouped task must be done in parallel with Cabling BTS andUnlock Trafficon Downstream BTSs (Section 2.3.5.4 )\ grouped task, to reduce outageduration.

    Note Task Description Site To do Outage

    Copy BTS to PRC. Copy the new BTSs,(including the BTSs created on anotherAbis link), from SC to PRC1

    OMC-R 1 Outage 1

    Outage 2

    Input In PRC1, Map Cell to a BTS Sector foreach unmapped cell, to the new BTSs

    OMC-R 1 Outage 1

    Outage 2

    C5b

    Input

    In PRC1, Link a Cell to a SecondaryBTS Sector for each shared cell, to thenew BTSs

    OMC-R 1 Outage 1

    Outage 2

    Check PRC(check all, without forcing celladministrative state) on PRC1

    OMC-R 2 Outage 1

    Outage 2

    Activate PRC(PRC1) without forcing celladministrative state

    OMC-R 1 +1/ Cell+1/SS

    (SecondarySector)

    Outage 1

    Outage 2

    Exch During PRC activation, inform MSC staffabout deleted and created cells, if any, forMSC data base update.

    OMC-R /MSC

    1 Outage 1

    Outage 2

    2.3.5.4 Cabling BTS and Unlock Traffic on Downstream BTSs

    Note: This grouped task must be done in parallel with New BTS Creation on SameAbis(Section 2.3.5.2 ) and End PRC Preparation and Activate PRC (Section2.3.5.3 ) grouped tasks, to reduce outage duration.

    Note Task Description Site To do Outage

    BTS 1/Sect Outage 1

    Outage 2

    C2 Disable SBLs Other Than BTS_TEL (RA)on replaced BTSs, when old antennas are

    reused

    Perform all Disable RA in parallel in order toreduce outage duration.

    BTS Disconnection (Abis links fromreplaced BTSs)

    BTS 5/Abis Outage 1

    Outage 2

    BTS Connection(Abis links to new BTSs) BTS 5/Abis Outage 1

    Outage 2

    3BK 17416 0742 RJZZA Ed.03 29 / 38

    http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-
  • 7/31/2019 add new BTS

    30/38

    2 Scenario

    Note Task Description Site To do Outage

    C6 Jumper Disconnection if the added BTSis introduced in the middle of an existingAbis link

    BTS 5 Outage 1

    Outage 2

    C6 BTS Connection (added BTS) BTS 5 Outage 1

    Outage 2

    OMC-R 1 Outage 1

    Outage 2

    Allow Alarm Reporting on Abis TP of theimpacted Abis links, and Acknowledge thealarms (due to Abis disconnection)

    Perform following unlock O&M actions, beforeallowing alarm on Abis between BTSs

    OMC-R 2 Outage 1

    Outage 2

    C4

    C6Synchro

    When Abis connection is done (Abis linkno more in alarm state), Unlock BTS O&M

    Capability, then Unlock Cell Traffic for alldownstream BTSs , including downstreamBTSs for the new added BTSs on thesecond Abis link

    Perform all Unlock actions in parallel, in order toreduce outage duration.

    C4

    C6

    If GPRS on cells Unlock GPRS Traffic onCell for all cells on downstream BTSs

    OMC-R 1 END 2

    OMC-R 2 Outage 1Synchro When Abis connection is done (Abis linkno more in alarm state), Unlock BTS O&MCapability on all new BTSs Perform all Unlock actions in parallel, in order to

    reduce outage duration.

    Note:If the BTSs were not already locallydownloaded (O1), wait 15 for BTS SW download(G2 BTS max 24).

    OMC-R automatically triggers a HW andalarm audit. All the boards of the BTSappears on OMC-R BSS equipment view

    OMC-R 5 Outage 1

    C2

    Exch

    Disable SBLs Other Than BTS_TEL (RA)on new BTSs

    OMC_R/BTS 1/Sect Outage 1

    C2 Disconnect antennas from replaced BTSsand connect them to new BTSs (in placeof loads)

    BTS 10/Sect Outage 1

    BTS 1/Sect Outage 1C2 Initialize SBLs (RA) on new BTSs

    Perform all Initialize RA actions in parallel in orderto reduce outage duration

    30 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    31/38

    2 Scenario

    Note Task Description Site To do Outage

    C2 If new BTS is EVOLIUM BTS (A9100 /A910) and if is necessary to measurethe VSWR, then send message Modify

    Hardware Configuration using the BTSTerminal

    Measure VSWR on ANX or ANC whereantennas are just connected:

    If result is lower or equal than 1.3,

    choose VSWR Threshold Alarm

    Definition with 0.6 margin, then click on

    [Confirm thresholds] to update RI

    If result is higher than 1.3, test with a

    50 Ohms load and check feeder and

    antenna.

    At the end perform:Modify HardwareConfiguration (End Modification ofHardware Configuration)

    Check the detected configuration, thenclick on [YES] to accept it

    BTS 2+5/Sect Outage 1

    Exch Inform OMC-R team you have finishedyour job

    BTS / OMC-R 1 Outage 1

    C2 OMC-R automatically triggers a HW and

    alarm audit

    OMC-R 5 Outage 1

    2.3.5.5 Unlock Cells on new BTSs

    Note Task Description Site To do Outage

    OMC-R 2 Outage1Synchro When PRC1 activation is finished,perform Unlock Cell Traffic for all newBTSs Unlock all cells in parallel, in order to reduce

    outage duration.

    If GPRS on cellsUnlock GPRS Traffic onCellfor all cells on newBTSs.

    OMC-R 1 END 1

    3BK 17416 0742 RJZZA Ed.03 31 / 38

  • 7/31/2019 add new BTS

    32/38

    2 Scenario

    2.3.6 Check and Finishing

    2.3.6.1 Check

    Note Task Description Site To do Outage

    BTS 5/Cell NoneExch When cells are unlocked, perform CallTest and inform OMC team about result

    Note: Task must be done in parallel with the nextone.

    Unlock cell from Call Test detailed task notnecessary here.

    OMC-R 5/Cell NoneCheck During call test, Display USD Detailed CellInformation for impacted cells, and cellsmapped on downstream BTSs, if any.

    For GSM: Observe different cell report,

    refresh regularly the view. If B appear,test succeed.

    For GPRS: Observe different cell report,refresh regularly the view. If G appear,test succeed.

    If cell traffic is unsuccessful, and maintenanceaction cannot solve it, ask TAC and perform theReverse Procedure (Section 2.4)

    2.3.6.2 Finishing

    Note Task Description Site To do Outage

    Close PRC (PRC1 and PRC2) OMC-R 1 None

    Delete PRC (Backup PRC, PRC1 andPRC2).

    OMC-R 1 None

    Perform an Audit Alarm Stateon BSS. OMC-R 10 None

    OMC-R 5 NoneView Status of Managed Objects andAlarms on impacted BTSs (new anddownstream BTSs, if any). Display CellReport for the impacted cells.

    Compare with printed initial reports. Check ifdifference appears.

    32 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    33/38

    2 Scenario

    2.3.6.3 Replaced BTS Power Off

    Note: This grouped task could be done in parallel, with the previous one ( Finishing(Section 2.3.6.2 ) )

    Note Task Description Site To do Outage

    Exch If successfully BTS replacement, switchoff replaced BTSs

    BTS 2 None

    Perform replaced BTS dismounting andshift new BTS to final place (could be donelater, with another team).

    BTS 2h/BTS None

    3BK 17416 0742 RJZZA Ed.03 33 / 38

    http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-
  • 7/31/2019 add new BTS

    34/38

    2 Scenario

    2.4 Reverse Procedure

    The reverse procedure describes how to go back to initial BTS and cellconfigurations.

    2.4.1 BTS Replacement

    2.4.1.1 PRC Preparation

    Note Task Description Site To do Outage

    Create PRC (PRC3) OMC-R 1

    Copy OMC Cells to PRC. Copy theimpacted cells, from SC to PRC3.

    OMC-R 1

    Delete OMC Cell from PRCin PRC3, forall cells mapped on new BTSs

    OMC-R 1

    Check PRC(check all, without forcing celladministrative state) on PRC3

    OMC-R 2

    2.4.1.2 Shut Down Cells

    Note Task Description Site To do Outage

    C6 Inhibit Alarm Reporting on Abis TP of thenew Abis links created for added BTS, ifany

    OMC-R 1

    Shut Down Cell Traffic (WTC=3) on allnew BTSs

    OMC-R 3

    C4

    C6

    Shut Down Cell Traffic (WTC=3) on alldownstream BTSs, including downstreamBTSs for the new added BTS(s) on thesecond Abis link

    OMC-R 3

    If GPRS on cells Lock GPRS Traffic onCell for all cells on new BTSs and on alldownstream BTSs

    OMC-R 1

    Lock BTS O&M Capability on all newBTSs

    OMC-R 1

    C4

    C6

    Lock BTS O&M Capability on alldownstream BTSs, including downstreamBTSs for the new added BTS(s) on thesecond Abis link

    OMC-R 1

    Exch Inform staff on BTS sites to start Abis linkconnection.

    OMC-R 1

    34 / 38 3BK 17416 0742 RJZZA Ed.03

  • 7/31/2019 add new BTS

    35/38

    2 Scenario

    2.4.1.3 Delete/Create BTS and Activate PRC

    Note: Probably automatic BTS numbering from BSC has changed compared withinitial state. To update this in Backup PRC, is necessary to create the previousBTSs again and to copy them in the Backup PRC.

    Note Task Description Site To do Outage

    Activate PRC (PRC3) without forcing celladministrative state

    OMC-R 1 +1/Cell+1/SS

    OMC-R 7/BTSDelete BTS from OMC-R (new BTSs).Delete first slave BTSs then master BTSsin case of synchronized BTSs Wait for transmission programming flag changes

    from Abis to Idle

    OMC-R 8/BTSCreate BTSor Copy and Paste a BTS (forthe Paste action do not forget to changethe BTS name and the Qmux address).Set also the Slave status, if needed, foreach previous BTS. Create first masterBTSs then slave BTSs.

    Wait for transmission programming flag changesfrom Abis to Idle

    Check replaced (created again) BTSappears in Radio Configuration Browser(SC).

    Set Commercial Usage of BTS, if needed

    OMC-R 1

    Open PRC (Backup PRC) OMC-R 1

    C5a In Backup PRC, Unlink a Cell from a

    Secondary BTS Sector for each sharedcell, from the replaced (previous) BTSs

    OMC-R 1

    In Backup PRC Unmap Cell from a BTSSector, for all impacted cells, from thereplaced (previous) BTSs

    OMC-R 1

    Remove BTS from PRC (Backup PRC)for replaced (previous) BTSs

    OMC-R 2

    Copy BTS to PRC. Copy the replacedBTSs (created again) from SC to Backup

    PRC

    OMC-R 1

    In Backup PRC, Map Cell to a BTSSector for the unmapped cells, to thereplaced BTSs (created again)

    OMC-R 1

    C5a In Backup PRC, Link a Cell to aSecondary BTS Sector for the shared cellto the replaced BTSs (created again)

    OMC-R 1

    Check PRC(check all, without forcing celladministrative state) on Backup PRC

    OMC-R 2

    3BK 17416 0742 RJZZA Ed.03 35 / 38

  • 7/31/2019 add new BTS

    36/38

    2 Scenario

    Note Task Description Site To do Outage

    Activate PRC (Backup PRC) withoutforcing cell administrative state

    OMC-R 1 +1/Cell+1/SS

    (Secondary

    Sector)

    Exch During PRC activation, inform MSC staffabout go back action, if needed, for MSCdata base update

    OMC-R /MSC

    1

    2.4.1.4 Cabling BTS

    This grouped task must be done in parallel with Delete/Create BTS and ActivatePRC(Section 2.4.1.3 ) grouped task, to reduce outage duration.

    Note Task Description Site To do Outage

    BTS 1/SectC2 Disable SBLs Other Than BTS_TEL (RA)on new BTSs, when old antennas arereused Perform all Disable RA actions in parallel in order

    to reduce outage duration

    BTS 5/AbisBTS Disconnection (new BTSs)

    Disconnect Abis links from replaced BTSs

    BTS 5/AbisBTS Connection (replaced BTSs)

    Connect Abis links to replaced (previous) BTSs

    C6 BTS Disconnection (added BTS) BTS 5

    C6 Jumper Connection, if the added BTS wasintroduced in the middle of an existingAbis link

    BTS 5

    C2 Disconnect antennas from new BTSs andconnect them to replaced BTSs.

    BTS 5/Sect

    BTS 1/SectC2 Initialize SBLs(RA) on replaced BTS

    Perform all Initialize RA actions in parallel in orderto reduce outage duration

    2.4.1.5 Unlock Cells

    Note Task Description Site To do Outage

    Acknowledge alarms from Abis (due toAbis disconnection)

    OMC-R 1

    36 / 38 3BK 17416 0742 RJZZA Ed.03

    http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-
  • 7/31/2019 add new BTS

    37/38

    2 Scenario

    Note Task Description Site To do Outage

    Synchro When Abis connection is done (Abis linkno more in alarm state), Unlock BTS O&MCapabilityon all replaced (old) BTSs

    OMC-R 1

    C4

    C6

    Unlock BTS O&M Capability on alldownstream BTSs, including downstreamBTSs for the new added BTS(s) on thesecond Abis link

    OMC-R 1

    OMC-R automatically triggers a HW andalarm audit. All the boards of the BTSappears on OMC-R BSS equipment view

    OMC-R 5

    OMC-R 2C4

    C6

    Unlock Cell Traffic for downstream BTSs,including downstream BTSs for the newadded BTS(s) on the second Abis link Perform all unlock actions in parallel, in order to

    reduce outage duration

    C4

    C6

    If GPRS on cells Unlock GPRS Traffic onCell on all downstream BTSs, includingdownstream BTSs for the new addedBTS(s) on the second Abis link

    OMC-R 1

    OMC-R 2When Backup PRC activation is finished,perform Unlock Cell Traffic for all cells onreplaced (previous) BTSs Perform all unlock actions in parallel, in order to

    reduce outage duration

    If GPRS on cells Unlock GPRS Traffic onCell for all cells on replaced (previous)BTSs

    OMC-R 1

    2.4.2 Check and Finishing

    2.4.2.1 Check

    Note Task Description Site To do Outage

    BTS 5/CellExch When cells are unlocked, perform CallTest and inform OMC team about result

    Note: Task must be done in parallel with the nextone.

    Unlock cell from Call Test detailed task notnecessary here.

    3BK 17416 0742 RJZZA Ed.03 37 / 38

  • 7/31/2019 add new BTS

    38/38

    2 Scenario

    Note Task Description Site To do Outage

    OMC-R 5/CellDuring call test, Display USD Detailed CellInformation for cells mapped on replaced(old) BTS and downstream BTSs, if any.

    For GSM: Observe different cell report,refresh regularly the view. If B appear,test succeed.

    For GPRS: Observe different cell report,refresh regularly the view. If G appear,test succeed.

    If cell traffic is unsuccessful, and maintenance

    action cannot solve it, ask TAC

    2.4.2.2 Finishing

    Note Task Description Site To do Outage

    Close PRC (Backup PRC, PRC1,PRC2 and PRC3)

    OMC-R 1

    Delete PRC (Backup PRC, PRC1,PRC2 and PRC3)

    OMC-R 1

    OMC-R 7C6 Delete BTS from OMC-R (added BTS), ifneeded

    Wait for Transmission programming flag changesfrom Abis to Idle

    OMC-R 7C6 Delete Abis Chain / Ring (new Abiscreated for added BTS), if needed

    Wait for Transmission programming flag changesfrom Abis to Idle

    Perform an Audit Alarm State on BSS OMC-R 10

    OMC-R 5View Status of Managed Objects andAlarms on impacted BTSs (old BTSs anddownstream BTSs, if any). Display CellReport for the impacted cells.

    Compare with printed initial reports. Check ifdifference appears.

    2.4.2.3 New BTS Power Off

    Note Task Description Site To do Outage

    Switch off new BTSs, if needed. BTS 2