Design and Construction Review (DCR) Leading transportation innovation - Investing in Communities. We drive quality transportation for all Ada County…Anytime, Anywhere! Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100 - FAX (208) 387-6391 E-mail: [email protected] DESIGN & CONSTRUCTION REVIEW Bogus Basin Rd Improvements January 1, 2020 FY 20 Committed to Service

Upload: others

Post on 10-Sep-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design and Construction Review (DCR)

Leading transportation innovation - Investing in Communities.

We drive quality transportation for all Ada County…Anytime, Anywhere!

Ada County Highway District

3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100 - FAX (208) 387-6391 E-mail: [email protected]

DESIGN & CONSTRUCTION REVIEW

Bogus Basin Rd Improvements January 1, 2020

FY 20

Committed to Service

Page 2: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design and Construction Review (DCR)

January 2020

Project Name Page No.

11th St Maintenance and Bikeway, State St to Heron St 1

13th St Traffic Calming, Fort St to Hill Rd 2

2019 Federal Aid Capital Maintenance - Phase 1 3

2019 Federal Aid Capital Maintenance - Phase 2 4

2019 Federal Aid Capital Maintenance - Phase 3 (Local) 5

2019 Green Stormwater Implementation 6

2020 Arterial and Collector Capital Maintenance - HB312 7

2020 Downtown Boise Implementation - HB312 8

2020 Federal Aid Capital Maintenance - Local 9

2020 Federal Aid Capital Maintenance - Phase 1 10

2020 Federal Aid Capital Maintenance - Phase 2 11

2020 Maintenance Crack Seal - HB312 12

2020 Microseal - HB312 13

2020 Residential Capital Maintenance - HB312 14

2021 Arterial and Collector Capital Maintenance - HB312 15

2021 Federal Aid Capital Maintenance - Local 16

2021 Federal Aid Capital Maintenance - Phase 1 17

2021 Federal Aid Capital Maintenance - Phase 2 18

2021 Residential Capital Maintenance 19

24th St Road and Bridge Project 20

28th Street - Hazel Street to Irene Street 21

32nd St Bridge 1308 22

33rd St Bridge 1318 23

38th St Bridge 1440 24

38th St, Bush Ave to Sunset Ave 25

41st Street Bridge 1437 26

44th St Bridge 1433 27

45th St Bridge 1432 28

Aikens St, Eagle Rd to 2nd St 29

Amity Rd and Maple Grove Rd Roundabout 30

Bogart Ln, State St to Sloan St 31

Broadway Ave and Boise Ave 32

Bryson Ave Bridge 1134 33

Cassia St Bikeway and Pedestrian Improvements 34

Cherry Ln and Meridian Library Pedestrian Crossing 35

Chinden Blvd and Curtis Rd 36

Cloverdale Rd, Columbia Rd to Overland Rd Corridor Preservation 37

Cole Rd and Victory Rd Intersection 38

Columbus St, Overland Rd to Kootenai St 39

Deer Flat Rd and School Ave Pedestrian Crossing 40

Deer Flat Rd, School Ave to Deerhorn Rd 41

Division Ave, Highlands St to Hale St 42

Eagle Rd, Amity Rd to Victory Rd 43

Edgewood Ln, State St to Hill Rd 44

January 2020 DCR TOC TOC 1 of 3

Page 3: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design and Construction Review (DCR)

January 2020

Project Name Page No.

Enhanced School Crossings - Meridian Middle and Capital HS 45

Fairview Ave and Curtis Rd Accessible Pedestrian Signal 46

Fairview Ave and Locust Grove Rd 47

Fairview Ave and Milwaukee St Accessible Pedestrian Signal 48

Five Mile and Seneca Pedestrian Crossing 49

Five Mile and Smoke Ranch Pedestrian Crossing 50

Franklin St, McKinley St to Pierce St 51

Garden St Franklin Rd to Bethel St 52

Gowen Rd Bridge 2110 53

Gowen Rd Bridge 2173 54

Holcomb Rd, Eastgate Dr to Amity Rd 55

Horseshoe Bend Rd and Shadowview Rd Ped Crossing 56

Lake Hazel Rd and Eagle Rd 57

Lake Hazel Rd and Five Mile Rd 58

Lake Hazel Rd, Cloverdale Rd to Five Mile Rd Pedestrian Improvements 59

Linder Rd and Deer Flat Rd 60

Linder Rd, Franklin Rd to Pine Ave 61

Locust Grove Rd and Chinden Blvd Intersection 62

Locust Grove Rd, Victory Rd to Overland Rd 63

Maple Grove Rd, Victory Rd to Overland Rd 64

McMillan Rd and Leather Way Pedestrian Crossing 65

McMillan Rd, Westview Dr to Maple Grove Rd 66

Meridian Rd, Cherry Ln to Ustick Rd 67

Overland Rd and Phillippi St Ped Crossing 68

Phillippi St, Malad St to Targee St 69

Phillippi Street, Targee Street to Overland Road 70

Pierce St, Washington St to Shenandoah Dr 71

Roosevelt St, Rose Hill St to Emerald St (West Side) 72

Royal Blvd, La Pointe St to Lusk St 73

Shamrock Ave Bridge No 1424 74

Shoshone St Bikeway, Canal St to Capital Blvd 75

State St and Pierce Park Ln 76

State St, 16th to 23rd Street Lighting Improvements 77

Ten Mile Rd and Amity Rd 78

Ten Mile Rd and Crenshaw St Pedestrian Crossing 79

Ten Mile Rd and Victory Rd 80

Ten Mile Rd, McMillan Rd to Chinden Blvd 81

Ten Mile Rd, Victory Rd to Overland Rd 82

Ten Mile Road, Ustick Road to McMillan Road 83

Thurman Mill Bridge Projects 84

Ustick Rd and Milwaukee St School Zone 85

Valley St, Lake Hazel Rd to La Grange St 86

Victory Rd and Locust Grove Rd Roundabout 87

Victory Rd and Standing Timber Ave Pedestrian Crossing 88

January 2020 DCR TOC TOC 2 of 3

Page 4: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design and Construction Review (DCR)

January 2020

Project Name Page No.

Vista Ave and Nez Perce St Ped Crossing 89

Warm Springs Ave, Glacier Dr to Glacier Dr 90

January 2020 DCR TOC TOC 3 of 3

Page 5: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS BK218‐01 Contract No

Prj No 819011 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 3 Prj Mgr

Notice to Proceed 12/19/2019 Consultant

Est Completion Date 9/30/2020 Contact

Right of WayEst Start 9/30/2020 ROW Agent

Completion Date 9/15/2021 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 2/8/2022 Proj Inspector

Est Compl Date 5/4/2022

Project Status Notes

Utility Comments

 Developing consultant design scope and schedule and negotating contract. (DJR 

12/16/19)

11th St Maintenance and Bikeway, State St to Heron St

 Implment a bikeway on 11th Street betweeb State Street and Hereon Street as per the 

Concept design adopted by ACHD commission on October 23rd, 2019  The project 

includes:  Roadway Maintenence Between Heron Street and Franklin Street Pavement 

Markings, wayfinding signs, and branding signs Between Heron and Franklin. Enhanced 

Pedestrian Crossings Fort/11th, Hays/11th and Hays/12th. Crossings on 11th will included 

bicyclist push buttons and bulb‐outs. Install a multi‐use path through the Boise High School 

Campus and allway stops at the intersections of Franklin/ Washington  Install Pavement 

markings between Washington Street and the YMCA driveway. Install convetional bike

Dave Rader

Kittelson & Associates

Evan Reed

Dave Serdar

12/31/2019 11:12 AM 2 of 91 

Page 6: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM217‐31 Contract No

Prj No 820007 ITD Key No

Project Description

Current Project Phase 10 Ready DSN

DesignStatus 13 Prj Mgr

Notice to Proceed 1/2/2020 Consultant

Est Completion Date 7/17/2020 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 10/8/2020 Proj Inspector

Est Compl Date 12/22/2020

Project Status Notes

Utility Comments

 12/13 Finalizing SOW/PSA w HDR  SJ   11/25/19

13th St Traffic Calming, Fort St to Hill Rd

 Implement components of the 13th St Traffic Calming Concept Study completed in 2018, 

including bulbouts at Bella St, Hazel St, Heron St, Alturas St or Sherman St, and an 

enhanced pedestrian crossing (RRFB) at Resseguie St.  No ROW required for this project.  

FY20 Design, FY21 Construction. 

Seth Jarsky

HDR Engineering Inc

Cameron Waite

No R/W

12/31/2019 11:12 AM 3 of 91 

Page 7: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS FAO2191 Contract No ITD

Prj No 717030 ITD Key No 13903

Project Description

Current Project Phase 19 Construction

DesignStatus 100 Prj Mgr

Notice to Proceed 8/18/2017 Consultant

Est Completion Date 11/19/2018 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 41 Contractor

Notice to Proceed 8/28/2019 Proj Inspector

Est Compl Date 5/1/2020

Project Status Notes

Utility Comments

Idaho Materials and Construction

Paving complete Fairview Rd, Eagle to Cloverdale Rd, concrete work continues on other 

segments. (CH 11/21 /19)

2019 Federal Aid Capital Maintenance ‐ Phase 1

  Pavement rehabilita on, select pipe replacement, and upgrade of adjacent pedestrian 

ramps on: Annett St, Victory Rd‐Targee St; Division Ave, Boise Ave‐Beacon St; Latah St, 

Overland Rd‐Alpine St; Fairview Ave, Dixie Ln‐Cloverdale Rd.

Cody Homan

Parametrix Inc

Cody Janson

No R/W

12/31/2019 11:12 AM 4 of 91 

Page 8: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS FAO2192 Contract No ITD

Prj No 717031 ITD Key No 20003

Project Description

Current Project Phase 19 Construction

DesignStatus 100 Prj Mgr

Notice to Proceed 9/6/2017 Consultant

Est Completion Date 9/5/2018 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 36 Contractor

Notice to Proceed 8/26/2019 Proj Inspector

Est Compl Date 6/11/2020

Project Status Notes

Utility Comments

Central Paving Co Inc

 Continuing concrete work, roadwork to be done at night in Spring 2020. (CH 12/09 /19) 

2019 Federal Aid Capital Maintenance ‐ Phase 2

 Pavement rehabilita on, select pipe replacement, and upgrade of adjacent pedestrian 

ramps on Emerald St, Cole Rd‐Orchard St; Orchard St, Overland Rd‐Franklin Rd.

Cody Homan

Six Mile Engineering PA

Jeff Jones

No R/W

12/31/2019 11:12 AM 5 of 91 

Page 9: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS FAO219L Contract No

Prj No 717026 ITD Key No 20091

Project Description

Current Project Phase 17 Bid and Award

DesignStatus 100 Prj Mgr

Notice to Proceed 9/27/2017 Consultant

Est Completion Date Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 5/7/2020 Proj Inspector

Est Compl Date 7/6/2020

Project Status Notes

Utility Comments

 R ejected bids, upda ng plans/es mate, plan to re-bid with one of the 2020 Federal Aid 

Capital Maintenance projects. (CH 12/09/19)

2019 Federal Aid Capital Maintenance ‐ Phase 3 (Local)

 Pavement rehabilitation, select pipe replacement, and upgrade of adjacent pedestrian 

ramps on Cherry Ln from Shoshone St to Broxon St, Elder St from Owyhee St to Vista Ave, 

and Owyhee St from Elder St to Cherry Ln.

Cody Homan

Kittelson & Associates

Evan Reed

No R/W

12/31/2019 11:12 AM 6 of 91 

Page 10: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MDR216‐03 Contract No CT220‐05

Prj No 418008 ITD Key No

Project Description

Current Project Phase 19 Construction

DesignStatus 100 Prj Mgr

Notice to Proceed 10/17/2017 Consultant

Est Completion Date 2/21/2019 Contact

Right of WayEst Start 11/26/2018 ROW Agent

Completion Date 8/12/2019 Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 5/29/2020 Proj Inspector

Est Compl Date 9/15/2020

Project Status Notes

Utility Comments

 Bid awarded on 12/4/19. Responsvie low bidder is Clearwater Landscape. (DJR 12-17-

2019)

2019 Green Stormwater Implementation

 This project consists of retrofitting exsisting alley ways in downtown Boise with permeable 

pavers for stormwater management. The alley locations are provided below.

 ‐Between Idaho and Bannock, 4th and 5th

 ‐Between Miller and Myrtle, 9th to 10th

Dave Rader

Civil Survey Consultants

Matt Hart

Becca Randall

12/31/2019 11:12 AM 7 of 91 

Page 11: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS OV220 Contract No

Prj No 519018 ITD Key No

Project Description

Current Project Phase 12 Design In House

DesignStatus 100 Prj Mgr

Notice to Proceed 7/24/2019 Consultant

Est Completion Date 10/8/2019 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 3/13/2020 Proj Inspector

Est Compl Date 7/7/2020

Project Status Notes

Utility Comments

 The project is in the design phase and is on schedule.                  [JT III - 12/13/2019]

  N/A

2020 Arterial and Collector Capital Maintenance ‐ HB312

 Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial 

and collector road segments as part of ACHD's Pavement Management Program. Project 

funded all or in part through House Bill 312 Funding. In‐House Design. Segments include 

the following: Linder Road, Trophy Street to Hubbard Road; Victory Road, McDermott Road 

to Black Cat Road; and Victory Road, Eight Mile Lateral to west of Eagle Road.

Joe Tate

ACHD Design

Pierson Dewit / Jeremy Andree

No R/W

12/31/2019 11:12 AM 8 of 91 

Page 12: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS SM220 Contract No

Prj No 519044 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 70 Prj Mgr

Notice to Proceed 7/1/2019 Consultant

Est Completion Date 5/12/2020 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 2/18/2021 Proj Inspector

Est Compl Date 7/9/2021

Project Status Notes

Utility Comments

 Design underway, geotechnical work delayed by the downtown Boise traffic control 

moratorium. (CH 10/28/19)

2020 Downtown Boise Implementation ‐ HB312

  Pavement rehabilita on: State St, 16th St to 15th St; State St 11th St to 1st St; 9th St, 

Bannock St to State St; 9th St, University Dr to Front St; 10th St, Front St to Idaho St; Grove 

St, 16th St to 9th St.  Additional work: widen State St, 15th St to 12th St; add detached 

sidewalk to State St, 14th St to 12th St; install RRFB crossing State St on the west side of 

14th St; add bulb‐outs to the intersetions of State St at 4th St and 3rd St; replace storm 

drain/irrigation pipes as needed

Cody Homan

Precision Engineering LLC

Joel Grounds

No R/W

12/31/2019 11:12 AM 9 of 91 

Page 13: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS FAO220L Contract No

Prj No 718013 ITD Key No 19847

Project Description

Current Project Phase 11 Design

DesignStatus 100 Prj Mgr

Notice to Proceed 5/10/2018 Consultant

Est Completion Date 4/1/2019 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 6/3/2020 Proj Inspector

Est Compl Date 8/18/2020

Project Status Notes

Utility Comments

 Construction planned for summer 2020.  (BM 12-18-19)

2020 Federal Aid Capital Maintenance ‐ Local

  Pavement rehabili a on and upgrade of adjacent pedestrian ramps on iden fed arterial 

and collector road segments.  Segments include: Owyhee St, Cherry Ln to Overland Rd

Brian McCarthy

HW Lochner Inc

No R/W

12/31/2019 11:12 AM 10 of 91 

Page 14: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS FAO2201 Contract No

Prj No 718042 ITD Key No 18728

Project Description

Current Project Phase 17 Bid and Award

DesignStatus 100 Prj Mgr

Notice to Proceed 8/13/2018 Consultant

Est Completion Date 7/9/2019 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 2/28/2020 Proj Inspector

Est Compl Date 9/23/2020

Project Status Notes

Utility Comments

 Final design complete, project moving towards PS&E 11.26.19 RC

2020 Federal Aid Capital Maintenance ‐ Phase 1

 Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial 

and collector road segments.  Segments inlcude: 13th St, Alturas St to Brumback St, 

Beacon Light Rd, SH‐16 to Ballantyne Ln, Cole Rd, Lake Hazel Rd to Latigo Dr, Edna St, Five 

Mile Rd to Patton Ave, Floating Feather Rd, Lanewood Rd to Linder Rd, Hill Rd Pkwy, 

Horseshoe Bend Rd to Seasman Gulch Rd, Horseshoe Bend Rd, State St to Cemetery 

Entrance, Locust Grove Rd, Ustick Rd to McMillan Rd, Pine St, Linder Rd to Meridian Rd, 

Technology Way, Columbia Rd to SH‐21.

Ryan Cutler

Precision Engineering LLC

Joel Grounds

No R/W

12/31/2019 11:12 AM 11 of 91 

Page 15: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS FAO2202 Contract No

Prj No 718025 ITD Key No 19887

Project Description

Current Project Phase 11 Design

DesignStatus 100 Prj Mgr

Notice to Proceed 6/27/2018 Consultant

Est Completion Date 12/31/2019 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 6/3/2020 Proj Inspector

Est Compl Date 9/25/2020

Project Status Notes

Utility Comments

 The Gowen Rd segment will be seperated out to construct it in FY20.  The Collister Rd 

segment is reprogrammed to FY22.  (BM 12-18-19)

2020 Federal Aid Capital Maintenance ‐ Phase 2

 Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial 

and collector road segments.  Segments include:  Collister Dr, Quail Ridge Dr to North End 

and Gowen Rd, Orchard St to Broadway Ave.

Brian McCarthy

Six Mile Engineering PA

No R/W

12/31/2019 11:12 AM 12 of 91 

Page 16: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MCS220 Contract No CT220‐10

Prj No 520006 ITD Key No

Project Description

Current Project Phase 17 Bid and Award

DesignStatus 100 Prj Mgr

Notice to Proceed 10/1/2019 Consultant

Est Completion Date 11/4/2019 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 2/3/2020 Proj Inspector

Est Compl Date 3/10/2020

Project Status Notes

Utility Comments

  11/22  Submi ed bid docs to Procurement, scheduled Commission approval on 1/22, 

construction NTP 2/6  12/13/19 SMJ

2020 Maintenance Crack Seal ‐ HB312

 Seal cracks in arterial and collector roadways in Preventative Maintenance Zone 2 South 

(south of I‐84, north of Lake Hazel Rd, between McDermott Rd and Five Mile Rd) as part of 

ACHD's Pavement Management Program.  Project funded all or in part through House Bill 

312 funding. 

Seth Jarsky

ACHD Design

Scott Forrey

No R/W

12/31/2019 11:12 AM 13 of 91 

Page 17: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MIC220 Contract No

Prj No 520004 ITD Key No

Project Description

Current Project Phase 10 Ready DSN

DesignStatus 21 Prj Mgr

Notice to Proceed 2/12/2020 Consultant

Est Completion Date 5/18/2020 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 8/20/2020 Proj Inspector

Est Compl Date 9/11/2020

Project Status Notes

Utility Comments

12/13 Working w Six Mile on SOW/PSA, Seth to present w City staff at 1/29 Commission 

mtg  12/13/19  SMJ 

2020 Microseal ‐ HB312

Microseal roadways as part of ACHD's Pavement Management Program.  Project funded all 

or in part through House Bill 312 funding. SegmentsJefferson St ‐ 1st St to 16th St13th St ‐ 

Front St to Main St3rd St ‐ Jefferson St to Front St4th St ‐ State St to S End8th St ‐ Myrtle St 

to Broad StAve A ‐ Myrtle St to Front StBroad St ‐ 9th St to 8th StFront St ‐ 16th St to 13th 

StRiver St ‐ 9th St to Capital Blvd

Seth Jarsky

Six Mile Engineering PA

No R/W

12/31/2019 11:12 AM 14 of 91 

Page 18: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MTL220 Contract No

Prj No 518026 ITD Key No

Project Description

Current Project Phase 12 Design In House

DesignStatus 99 Prj Mgr

Notice to Proceed 7/11/2018 Consultant

Est Completion Date Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 5/7/2020 Proj Inspector

Est Compl Date 9/14/2020

Project Status Notes

Utility Comments

 95% review meeting scheduled for early 12/10/19 . (CH 12/09/19)

2020 Residential Capital Maintenance ‐ HB312

  Gather exis ng roadway condi on informa on and rehabilitee the pavement along with 

upgrading pedestrian ramps on residential streets. Segments inlcude: 10th St, Fort St to 

Heron St; Cunningham Pl, 8th St to 6th St; Heron St, Harrison Blvd to 13th St; Maple Ave, 

Warm Springs Ave to Franklin St; O'Farrell St, 13th St to 4th St; Pierce Ct, Shenandoah Dr to 

North End.

 Part of the ACHD Pavement Management Program, funded all or in part through House 

Bill 312 funding. In‐house design project.

Cody Homan

ACHD Design

Jeremy Andree

No R/W

12/31/2019 11:12 AM 15 of 91 

Page 19: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS OV221 Contract No

Prj No 520002 ITD Key No

Project Description

Current Project Phase 12 Design In House

DesignStatus 29 Prj Mgr

Notice to Proceed 9/25/2019 Consultant

Est Completion Date 8/21/2020 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 7/2/2021 Proj Inspector

Est Compl Date 8/31/2021

Project Status Notes

Utility Comments

 Geotechnical report has been reviewed, met with geotech consultant. Will provide 

another design option. Design to start beginning of February (CD 12/16/19)

2021 Arterial and Collector Capital Maintenance ‐ HB312

 Pavement rehabilita on on Pleasant Vally Rd between Hollolynn Dr and Amyx Rd. project 

funding all or in part through House Bill 312. In‐house design.  

Chris Dayley

ACHD Design

Pierson Dewit

Dave Serdar

12/31/2019 11:12 AM 16 of 91 

Page 20: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS FAO221L Contract No

Prj No 719019 ITD Key No 20159

Project Description

Current Project Phase 11 Design

DesignStatus 100 Prj Mgr

Notice to Proceed 11/26/2018 Consultant

Est Completion Date 9/13/2019 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 6/14/2021 Proj Inspector

Est Compl Date 7/27/2021

Project Status Notes

Utility Comments

 Staff is proposiing 10' travel lanes on NW8th to accomodate a standard width bike lane. 

Will take proposal to the ACHD commission for a work session on  January 15th. DJR 

(12/17/19)

2021 Federal Aid Capital Maintenance ‐ Local

This project provides pavement rehabilitation and upgrade of adjacent pedestrian ramps 

on 8th Street, from Pine Avenue to Cherry Lane.The project includes a total centerline 

roadway length of approximately 0.53 miles. All work associated with this project shall be 

done in accordance with Idaho Transportation Department design and drafting standards 

and follow the Federal‐Aid process 

Dave Rader

Parametrix Inc

Jim Koopman

No R/W

12/31/2019 11:12 AM 17 of 91 

Page 21: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS FAO2211 Contract No

Prj No 719035 ITD Key No 18701

Project Description

Current Project Phase 11 Design

DesignStatus 58 Prj Mgr

Notice to Proceed 7/23/2019 Consultant

Est Completion Date 6/29/2020 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 2/11/2021 Proj Inspector

Est Compl Date 8/24/2021

Project Status Notes

Utility Comments

 Concept review is complete.   Proceeding with environmental submittals.  (BM 11-20-19)

2021 Federal Aid Capital Maintenance ‐ Phase 1

 Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial 

and collector road segments.  Fairview Ave, Maple Grove to Milwuakee St; Curtis Rd, Ustick 

Rd to Fairview Ave; Curtis Rd, Overland Rd to Targee St; Surprise Way, Amity Rd to Hwy 21; 

Linden St, Broadway Ave to Gekeler Ln; Boise Ave, Broadway Ave to Gekeler Ln; Pleasant 

Valley Rd, Hollilynn Dr to Gowen Rd.

Brian McCarthy

Parametrix Inc

No R/W

12/31/2019 11:12 AM 18 of 91 

Page 22: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS FAO2212 Contract No

Prj No 719036 ITD Key No 20129

Project Description

Current Project Phase 11 Design

DesignStatus 39 Prj Mgr

Notice to Proceed 7/8/2019 Consultant

Est Completion Date 8/4/2020 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 4/7/2021 Proj Inspector

Est Compl Date 8/12/2021

Project Status Notes

Utility Comments

  The project is in the design phase and is on schedule.                  [JT III - 12/13/2019 ]

  N/A

2021 Federal Aid Capital Maintenance ‐ Phase 2

 Pavement rehabilitation and upgrade of adjacent pedestrian ramps on identified arterial 

and collector road segments as part of ACHD's Pavement Management Program.  

Segments include the following: Warm Springs Avenue, Starcrest Drive to Starview Drive; 

Warm Springs Avenue, Glacier Drive to Highway 21; and Edna Street, Five Mile Road to 

Patton Avenue.

Joe Tate

Six Mile Engineering PA

Pierson Dewit

No R/W

12/31/2019 11:12 AM 19 of 91 

Page 23: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MTL221 Contract No

Prj No 519017 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 25 Prj Mgr

Notice to Proceed 10/14/2019 Consultant

Est Completion Date 8/25/2020 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 5/6/2021 Proj Inspector

Est Compl Date 9/14/2021

Project Status Notes

Utility Comments

 Field survey underway. DJR (12/17/19)

2021 Residential Capital Maintenance

  Pavement rehabilita on and upgrade of adjacent pedestrian ramps residenital street 

segments. Segments identified as part of ACHD's Pavement Management Program. Project 

funded all or in part of House Bill 312 funding. In House design. Identified Segments are in 

Meridan, Idaho and include:  5th St E ‐ Franklin Rd to Bower St 3rd St. E. ‐ Franklin St to 

Bower St 2nd St E. ‐ Broadway Ave to Carlton Ave Bower St ‐ Maint St to East End 2.5 St E ‐ 

Carlton Ave to Fairview Ave Washington St ‐ 2.5 St to Cathy Ave 4th St E ‐ Washington Ave 

to North End 5th St E ‐ State St to East End Carlton Ave ‐ Main St to 2.5 St Carlton Ave ‐ 

Main St to E 2nd St State Ave ‐ Main St to Ease End 4th St E ‐ Broadway Ave to State Ave

Dave Rader

ACHD Design

Ramon Wells

No R/W

12/31/2019 11:12 AM 20 of 91 

Page 24: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS RD219‐01 Contract No

Prj No 819033 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 84 Prj Mgr

Notice to Proceed 1/23/2019 Consultant

Est Completion Date 9/26/2019 Contact

Right of WayEst Start 9/26/2019 ROW Agent

Completion Date 5/20/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 2/4/2021 Proj Inspector

Est Compl Date 5/11/2021

Project Status Notes

Utility Comments

 Project is in ROW phase.  DJR (12-17-19)

24th St Road and Bridge Project

  Replace bridge #1466, bridge #1467, and bridge #1468 over Boise City Canal as a part of 

ACHD’s Bridge Maintenance Program with a pre‐cast box culverts. Rebuild 24th St between 

Bella and Irene to improve overall pavement condition. 

Dave Rader

Keller Associates Inc

Rob Gronowski

Michele White

12/31/2019 11:12 AM 21 of 91 

Page 25: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM215‐06 Contract No CT220‐06

Prj No 818017 ITD Key No

Project Description

Current Project Phase 19 Construction

DesignStatus 100 Prj Mgr

Notice to Proceed 12/1/2017 Consultant

Est Completion Date 6/22/2018 Contact

Right of WayEst Start 10/3/2018 ROW Agent

Completion Date 6/24/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 6/4/2020 Proj Inspector

Est Compl Date 7/31/2020

Project Status Notes

Utility Comments

 Bid awarded on 12/4/2019. Sunroc Corporation is the responsive low bidder. DJR 

(12/17/19)

28th Street ‐ Hazel Street to Irene Street

 Construct bulb‐outs at the intersections of 28th Street & Irene, 28th and Bella Street, and 

28th and Hazel Street to provide traffic calming.

Dave Rader

Six Mile Engineering PA

Larry White

Becca Randall

12/31/2019 11:12 AM 22 of 91 

Page 26: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MI215‐18 Contract No

Prj No 219025 ITD Key No

Project Description

Current Project Phase 16 Shelved/Bid Ready

DesignStatus 100 Prj Mgr

Notice to Proceed 11/30/2018 Consultant

Est Completion Date 5/20/2019 Contact

Right of WayEst Start 5/20/2019 ROW Agent

Completion Date 7/24/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 1/4/2021 Proj Inspector

Est Compl Date 4/13/2021

Project Status Notes

Utility Comments

 100% design complete, ROW certs complete.  Shelved until FY21 construction.   SJ 

9/30/19

32nd St Bridge 1308

  Replace bridge #1308 over the Boise City Canal on 32nd St as part of ACHD's Bridge 

Maintenance Program with a reinforced concrete pipe (RCP).

Seth Jarsky

Elite Edge Engineers

Lisa Vernon

Michele White

12/31/2019 11:12 AM 23 of 91 

Page 27: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MI215‐17 Contract No

Prj No 219020 ITD Key No

Project Description

Current Project Phase 16 Shelved/Bid Ready

DesignStatus 100 Prj Mgr

Notice to Proceed 11/30/2018 Consultant

Est Completion Date 5/20/2019 Contact

Right of WayEst Start 5/20/2019 ROW Agent

Completion Date 8/26/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 1/25/2021 Proj Inspector

Est Compl Date 5/4/2021

Project Status Notes

Utility Comments

 100% design docs recieved, ROW certification recieved.  Shelve project until FY21.   SJ 

9/16/19 

33rd St Bridge 1318

  Replace bridge #1318 over the Boise City Canal as a part of ACHD’s Bridge Maintenance 

Program with a reinforced concrete pipe (RCP). Design to accommodate future 5’ 

sidewalks. 

Seth Jarsky

Elite Edge Engineers

Bill Nelson

12/31/2019 11:12 AM 24 of 91 

Page 28: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MI216‐12 Contract No

Prj No 219004 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 75 Prj Mgr

Notice to Proceed 10/9/2018 Consultant

Est Completion Date 6/7/2019 Contact

Right of WayEst Start 6/7/2019 ROW Agent

Completion Date 12/31/2019 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 11/2/2020 Proj Inspector

Est Compl Date 2/8/2021

Project Status Notes

Utility Comments

  In ROW phase. One property signed, one le  to sign. License Agreement recorded. 

Floodplain Application to be resubmitted with final plans. (CD 12/16 /19)

38th St Bridge 1440

Replace existing bridge #1440 over Thurman Mill Canal as part of ACHD’s Bridge 

Maintenance Program with a reinforced concrete pipe. Widen existing roadway limits to 50 

feet to accommodate future sidewalks. 

Chris Dayley

Elite Edge Engineers

Lisa Vernon

Michele White

12/31/2019 11:12 AM 25 of 91 

Page 29: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM216‐03 Contract No

Prj No 819021 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 11/26/2018 Consultant

Est Completion Date 7/25/2019 Contact

Right of WayEst Start 7/25/2019 ROW Agent

Completion Date 3/25/2020 Possession % 33

ConstructionStatus 0 Contractor

Notice to Proceed 4/20/2022 Proj Inspector

Est Compl Date 6/30/2022

Project Status Notes

Utility Comments

 99% plans recieved and ROW staking was completed 10/28  (12/2/19 JT)

38th St, Bush Ave to Sunset Ave

  Extend roadway and complete sidewalk on 38th St from Bush Ave to Sunset Ave.  Par al 

roadway reconstruction may be necessary.

Jason Tugby

T-O Engineers Inc

Pat Colwell

Renee Jayo

12/31/2019 11:12 AM 26 of 91 

Page 30: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MI216‐02 Contract No

Prj No 218039 ITD Key No

Project Description

Current Project Phase 12 Design In House

DesignStatus 100 Prj Mgr

Notice to Proceed 1/2/2018 Consultant

Est Completion Date 9/13/2018 Contact

Right of WayEst Start 9/13/2018 ROW Agent

Completion Date 4/22/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 11/30/2020 Proj Inspector

Est Compl Date 4/9/2021

Project Status Notes

Utility Comments

 ROW complete. Construction moved to FY21. (12.04.19 JT)

41st Street Bridge 1437

  Replace bridge #1437 over the Thurman Mill Canal on 41st St as part of ACHD's Bridge 

Maintenance Program.

Jason Tugby

ACHD Design

Jeremy Andree

Becca Randall

12/31/2019 11:12 AM 27 of 91 

Page 31: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MI215‐05 Contract No

Prj No 219005 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 97 Prj Mgr

Notice to Proceed 10/26/2018 Consultant

Est Completion Date 4/23/2019 Contact

Right of WayEst Start 10/1/2018 ROW Agent

Completion Date 11/14/2019 Possession % 82

ConstructionStatus 0 Contractor

Notice to Proceed 3/4/2021 Proj Inspector

Est Compl Date 7/9/2021

Project Status Notes

Utility Comments

 Project is currently in the ROW phase. Cultural scan completed, License agreement 

recieved at Sawtooth law for Thurman Mill Signitures  . Const programed for FY21 [ 

12.04.19 JT)

44th St Bridge 1433

  Replace bridge #1433 over the Thurman Mill Canal on 44th St as part of ACHD's Bridge 

Maintenance Program .

Jason Tugby

ACHD Design

Kraig Wartman

Bill Nelson

12/31/2019 11:12 AM 28 of 91 

Page 32: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MI215‐06 Contract No

Prj No 219003 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 10/26/2018 Consultant

Est Completion Date 4/23/2019 Contact

Right of WayEst Start 4/23/2019 ROW Agent

Completion Date 7/30/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 12/14/2020 Proj Inspector

Est Compl Date 4/22/2021

Project Status Notes

Utility Comments

 100% plans recieved 10/25/2019 Cultural scan completed awaiting copy of license 

agreement from Sawtoothlaw  [ 12.04.19 JT)  

45th St Bridge 1432

  Replace bridge #1432 over the Thurman Mill Canal on 45th St as part of ACHD's Bridge 

Maintenance Program  .

Jason Tugby

ACHD Design

Kraig Wartman

Bill Nelson

12/31/2019 11:12 AM 29 of 91 

Page 33: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS RD209‐11 Contract No

Prj No 517033 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 86 Prj Mgr

Notice to Proceed 2/23/2017 Consultant

Est Completion Date 1/6/2020 Contact

Right of WayEst Start 1/6/2020 ROW Agent

Completion Date 11/6/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 12/6/2021 Proj Inspector

Est Compl Date 7/25/2022

Project Status Notes

Utility Comments

 Updated draft ROW plans submitted for review. Construction moving from 2020 to 2022 

to bid with the State St/Eagle Rd project. (CH 12/05/19 )

Aikens St, Eagle Rd to 2nd St

  Extend Aikens Rd east to 2nd St and add/replace curb, gu er, & sidewalks on both sides of 

Aikens the length of the project in accordance with the Eagle Rd/State St Intersection 

Concept Study. Street section to include parking on the south side of Aikens. 10 foot wide 

sidewalks may be added where feasible with Cost Share with City of Eagle.

Cody Homan

Stanley Consultants

Jim Baker

Becca Randall

12/31/2019 11:12 AM 30 of 91 

Page 34: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN205‐120 Contract No

Prj No 319049 ITD Key No

Project Description

Current Project Phase 06 Study

DesignStatus 11 Prj Mgr

Notice to Proceed 9/4/2019 Consultant

Est Completion Date 10/6/2020 Contact

Right of WayEst Start 10/6/2020 ROW Agent

Completion Date 10/5/2021 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 2/3/2022 Proj Inspector

Est Compl Date 7/26/2022

Project Status Notes

Utility Comments

  Intersec on analysis dra  report submi ed, under review. (CH 12/09 /19)

Amity Rd and Maple Grove Rd Roundabout

  Replace the Amity Rd and Maple Grove Rd with a roundabout or larger signalized 

intersection.

Cody Homan

Six Mile Engineering PA

Jeff Jones

Dave Serdar

12/31/2019 11:12 AM 31 of 91 

Page 35: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM215‐03 Contract No

Prj No 819015 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 11/20/2018 Consultant

Est Completion Date 8/26/2019 Contact

Right of WayEst Start 8/26/2019 ROW Agent

Completion Date 12/16/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 4/25/2022 Proj Inspector

Est Compl Date 7/6/2022

Project Status Notes

Utility Comments

  ROW Cer ficate submi ed. (CD 12/16/19)

Bogart Ln, State St to Sloan St

 Install an attached 7' asphalt pathway with extruded curb on the west side of Bogart Ln 

between Caswell St and Pocono St. Construct a 5' attached sidewalk on the south side of 

Sloan and a 7' attached sidewalk on the east side of Bogart Ln at the parcel and the SEC of 

Bogart St and Sloan St.  I nstall an RRFB across Bogart Ln on the south side of Sloan St.

Chris Dayley

ACHD Design

Matt Degen

Michele White

12/31/2019 11:12 AM 32 of 91 

Page 36: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM213‐58 Contract No

Prj No 819040 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 99 Prj Mgr

Notice to Proceed 2/21/2019 Consultant

Est Completion Date 8/21/2019 Contact

Right of WayEst Start 11/21/2017 ROW Agent

Completion Date 12/26/2019 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 3/26/2020 Proj Inspector

Est Compl Date 6/5/2020

Project Status Notes

Utility Comments

ROW extended into FY20. Offers out to two properties. Construction in Summer. (CD 

12/4/19)   

Broadway Ave and Boise Ave

 Improve safety for pedestrians at the intersec on of Boise Ave and Broadway Ave. Install 

accessible pedestrian signals, remove and replace pedestrian ramps, and relocate lighting.

Chris Dayley

Precision Engineering LLC

Joel Grounds

Michele White

12/31/2019 11:12 AM 33 of 91 

Page 37: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MI218‐05 Contract No

Prj No 220011 ITD Key No

Project Description

Current Project Phase 12 Design In House

DesignStatus 4 Prj Mgr

Notice to Proceed Consultant

Est Completion Date 9/30/2020 Contact

Right of WayEst Start 9/30/2020 ROW Agent

Completion Date 6/7/2021 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 11/1/2021 Proj Inspector

Est Compl Date 2/1/2022

Project Status Notes

Utility Comments

Field topo is complete, beginning development of boundry map. Design to start May 

2020. (CD 12/16/19)

Bryson Ave Bridge 1134

 Replace bridge #1134 over the South Slough‐lateral as a part of ACHD's Bridge 

Maintenance Program. Design to accommodate future 7‐foot attached sidewalks on both 

sides of the roadway.

Chris Dayley

ACHD Design

Pierson Dewit

Dave Serdar

12/31/2019 11:12 AM 34 of 91 

Page 38: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS BK217‐03 Contract No

Prj No 818037 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 54 Prj Mgr

Notice to Proceed 4/1/2019 Consultant

Est Completion Date 4/1/2020 Contact

Right of WayEst Start 4/1/2020 ROW Agent

Completion Date 10/5/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 2/4/2021 Proj Inspector

Est Compl Date 8/3/2021

Project Status Notes

Utility Comments

 50% review meeting was held 10/31/19.  Open House is planned for 1/9/20.  (BM 12-18-

19)

Cassia St Bikeway and Pedestrian Improvements

 Bikeway and pedestrian improvements along Cassia St from Franklin Rd to Kootenai St 

(includes portion of Robert St from Cassia St to Kootenai St). Project includes the following.  

‐Sidewalk on north side and full width pavement rehabilitation from Franklin Park Dr to 

Curtis Rd  ‐Sidewalk on north side, full width pavement rehabilitation, and installation of 

permeable pavers from Latah St to Shoshone St.  ‐Mini roundabout at the intersection of 

Cassia St and Shoshone St.  ‐New bridge crossing at the Ridenbaugh Canal for 

pedestrian/bike pathway connectivity through Cassia Park.  ‐New PHB at Franklin Rd and 

Liberty St ‐Modification/relocation of PHB at Cassia St and Orchard St ‐New RRFB at Cassia

Brian McCarthy

Kittelson & Associates

Becca Randall

12/31/2019 11:12 AM 35 of 91 

Page 39: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM214‐44 Contract No

Prj No 819032 ITD Key No

Project Description

Current Project Phase 10 Ready DSN

DesignStatus 99 Prj Mgr

Notice to Proceed 2/8/2019 Consultant

Est Completion Date 10/25/2019 Contact

Right of WayEst Start 9/30/2019 ROW Agent

Completion Date 2/21/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 6/4/2020 Proj Inspector

Est Compl Date 9/21/2020

Project Status Notes

Utility Comments

99% design completed. IAA signed and returned from MLD for comission signiture on 

November 13 2019. ROW phase awaiting Bill N. for updates ( 12.04.19 JT

Cherry Ln and Meridian Library Pedestrian Crossing

 Install an enhanced pedestrian crossing (Pedestrian Hybrid Beacon) with a Z‐Crossing on 

Cherry Lane midway between W 8th St and Linder Rd across from the library. This will 

require relocating the existing school zone beacon to the west.

Jason Tugby

ACHD Design

JA

Bill Nelson, Dave Serdar

12/31/2019 11:12 AM 36 of 91 

Page 40: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN215‐03 Contract No

Prj No 318006 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 12/11/2017 Consultant

Est Completion Date 9/10/2018 Contact

Right of WayEst Start 7/16/2018 ROW Agent

Completion Date 9/14/2020 Possession % 46

ConstructionStatus 0 Contractor

Notice to Proceed 1/12/2022 Proj Inspector

Est Compl Date 5/12/2022

Project Status Notes

Utility Comments

 99% submittal received September 2018.  R/W phase is programmed for 2019/2020.  

(BM, 12-18-19)

Chinden Blvd and Curtis Rd

  Add a right turn lane to southbound Veterans Memorial Parkway and Cur s Road.   The 

right turn lane will extend through the intersection to Ustick Road.  Project includes new 

curb, gutter, sidewalk, and retaining walls on the east side of Curtis Rd/Veterans Memorial 

Pkwy.

Brian McCarthy

Six Mile Engineering PA

Larry White

Renee Jayo

12/31/2019 11:12 AM 37 of 91 

Page 41: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS 103250 Contract No N/A

Prj No 520029 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 84 Prj Mgr

Notice to Proceed 10/11/2019 Consultant

Est Completion Date 1/3/2020 Contact

Right of WayEst Start 1/3/2020 ROW Agent

Completion Date 6/30/2020 Possession % 0

ConstructionStatus Contractor

Notice to Proceed Proj Inspector

Est Compl Date

Project Status Notes

Utility Comments

  The Project is in the Design Phase and is on schedule.                  [JT III - 12/13/19]

Cloverdale Rd, Columbia Rd to Overland Rd Corridor Preservation

  Acquire right‐of‐way for Idaho Power reloca ons on Cloverdale Road between Columbia 

Road and Overland Road.

Joe Tate

T-O Engineers Inc

Steve Frisbie, 208-631-9655

Michele White

12/31/2019 11:12 AM 38 of 91 

Page 42: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN205‐97 Contract No CT220‐02

Prj No 317005 ITD Key No

Project Description

Current Project Phase 19 Construction

DesignStatus 100 Prj Mgr

Notice to Proceed 1/13/2017 Consultant

Est Completion Date 8/8/2018 Contact

Right of WayEst Start 8/8/2018 ROW Agent

Completion Date 7/24/2019 Possession % 100

ConstructionStatus 9 Contractor

Notice to Proceed 11/14/2019 Proj Inspector

Est Compl Date 10/30/2020

Project Status Notes

Utility Comments

 Construction NTP date was 11-14-19.  Left turn restrictions onto Victory Rd to be 

implemented starting early January.  (BM 12-18-19)

Cole Rd and Victory Rd Intersection

  Design intersec on of Cole Rd and Victory Rd in accordance with the 2016 CIP, widen Cole 

Rd south to McGlochlin St to 5 lanes with bike lanes, sidewalks and/or pathways and 

replace the structure of the Five Mile Creek.

Brian McCarthy

Precision Engineering LLC

Joel Grounds

Michele White

12/31/2019 11:12 AM 39 of 91 

Page 43: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CGS205‐20 Contract No CT219‐12

Prj No 816032 ITD Key No

Project Description

Current Project Phase 22 Complete

DesignStatus 100 Prj Mgr

Notice to Proceed 12/9/2015 Consultant

Est Completion Date 9/15/2016 Contact

Right of WayEst Start 9/15/2016 ROW Agent

Completion Date 2/22/2017 Possession % 100

ConstructionStatus Contractor

Notice to Proceed 2/21/2019 Proj Inspector

Est Compl Date 10/15/2019

Project Status Notes

Utility Comments

Central Paving Co Inc

 Project is substantially complete. 11.16.19 RC

Columbus St, Overland Rd to Kootenai St

   Construct curb, gu er & sidewalk on both sides of Columbus St from Overland Rd to 

Kootenai St in accoradance with the Central Bench Neighborhood Plan. Project will provide 

pedestrian connectivity & reduce the need for safety busing of Hawthorne Elementary 

School.

Ryan Cutler

Six Mile Engineering PA

Jeff Jones

Michele White

12/31/2019 11:12 AM 40 of 91 

Page 44: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM217‐27 Contract No

Prj No 819010 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 98 Prj Mgr

Notice to Proceed 10/25/2018 Consultant

Est Completion Date 3/11/2019 Contact

Right of WayEst Start 7/30/2019 ROW Agent

Completion Date 10/4/2019 Possession % 83

ConstructionStatus 0 Contractor

Notice to Proceed 5/4/2020 Proj Inspector

Est Compl Date 9/10/2020

Project Status Notes

Utility Comments

 100% plans recieved Ready to bid with Addtional projects with JTIII (12.04.19 JT )

Deer Flat Rd and School Ave Pedestrian Crossing

  Install an enhanced pedestrian crossing (Pedestrian Hybrid Beacon) on Deer Flat Rd at 

School Ave.  

Jason Tugby

Precision Engineering LLC

Joel Grounds

Bill Nelson

12/31/2019 11:12 AM 41 of 91 

Page 45: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS 102730 Contract No

Prj No 8200091.0CD ITD Key No

Project Description

Current Project Phase 10 Ready DSN

DesignStatus 25 Prj Mgr

Notice to Proceed 11/18/2019 Consultant

Est Completion Date Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 5/12/2020 Proj Inspector

Est Compl Date 9/18/2020

Project Status Notes

Utility Comments

  NTP for design signed 11/14 (JT 12/04)

Deer Flat Rd, School Ave to Deerhorn Rd

Jason Tugby

Precision Engineering LLC

Joel Grounds

Dave Serdar

12/31/2019 11:12 AM 42 of 91 

Page 46: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS 102640 Contract No

Prj No 820097.0CD ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 39 Prj Mgr

Notice to Proceed 11/26/2019 Consultant

Est Completion Date Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 3/4/2020 Proj Inspector

Est Compl Date 5/5/2020

Project Status Notes

Utility Comments

 30% Concept Design submitted 12-14/19. (12/16/19) 

Division Ave, Highlands St to Hale St

 Install 5' attached sidewalk to match existing with curb/gutter on the east side of Division 

with ADA‐compliant ped ramps at crossings. Will require relocation of irrigation box at SE 

corner of Division/Hale.  

Chris Dayley

Civil Survey Consultants

Matt Hart

Dave Serdar

12/31/2019 11:12 AM 43 of 91 

Page 47: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS RD207‐33 Contract No

Prj No 518040 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 1/29/2018 Consultant

Est Completion Date 6/28/2019 Contact

Right of WayEst Start 6/21/2019 ROW Agent

Completion Date 7/20/2020 Possession % 33

ConstructionStatus 0 Contractor

Notice to Proceed 11/19/2020 Proj Inspector

Est Compl Date 10/6/2021

Project Status Notes

Utility Comments

 Project is in ROW. 11.26.19 RC

Eagle Rd, Amity Rd to Victory Rd

  Widen Eagle Road to 5 lanes with curb, gu er, sidewalk and a Level 3 bike facility in 

accordance with the 2016 CIP.  Project inlcude enhanced pedestrian crossings at the 

pedestrian pathway near the Tenmile Feeder Canal.  In house design.

Ryan Cutler

ACHD Design

Jeremy Andree

Renee Jayo

12/31/2019 11:12 AM 44 of 91 

Page 48: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS 103030 Contract No

Prj No 820095.0CD ITD Key No

Project Description

Current Project Phase 10 Ready DSN

DesignStatus 25 Prj Mgr

Notice to Proceed 1/3/2020 Consultant

Est Completion Date 3/25/2020 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 6/16/2020 Proj Inspector

Est Compl Date 7/22/2020

Project Status Notes

Utility Comments

  12/13 Finalizing SOW/PSA w WH Pacific  12/13/19  SMJ

Edgewood Ln, State St to Hill Rd

  Install 7' detached asphalt pathways on east side of Edgewood to connect exis ng 

infrastructure. Install 7' attached asphalt pathway with extruded curb in front of 220 

Edgewood to connect to existing. Install 7' asphalt pathway on the west side of Edgewood 

approximately 550' north from State St. 

Seth Jarsky

WH Pacific

No R/W

12/31/2019 11:12 AM 45 of 91 

Page 49: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS 101810 Contract No

Prj No 820021 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 57 Prj Mgr

Notice to Proceed 11/14/2019 Consultant

Est Completion Date 4/17/2020 Contact

Right of WayEst Start 4/17/2020 ROW Agent

Completion Date 9/30/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 6/7/2021 Proj Inspector

Est Compl Date 8/16/2021

Project Status Notes

Utility Comments

 The Project is in the Design Phase and is on schedule.                    [JT III - 12-13-19]

Enhanced School Crossings ‐ Meridian Middle and Capital HS

  Install enhanced pedestrian crossings (rectangular rapid flashing beacons) on W 8th St in 

front of Meridain Middle School and on Milwaukee St next to Capital High School at the 

existing crosswalks.

Joe Tate

CH2M Hill Engineers Inc

George Van Horn

Becca Randall

12/31/2019 11:12 AM 46 of 91 

Page 50: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN217‐10 Contract No

Prj No 820018 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 7 Prj Mgr

Notice to Proceed 12/9/2019 Consultant

Est Completion Date 10/9/2020 Contact

Right of WayEst Start 10/9/2020 ROW Agent

Completion Date 4/27/2021 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 8/5/2021 Proj Inspector

Est Compl Date 11/22/2021

Project Status Notes

Utility Comments

  Awai ng NTP and signiture from Keller for contract. (JT 12/04)

Fairview Ave and Curtis Rd Accessible Pedestrian Signal

Jason Tugby

Keller Associates Inc

Rob Gronowski

Dave Serdar

12/31/2019 11:12 AM 47 of 91 

Page 51: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN211‐05 Contract No

Prj No 320012 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 0 Prj Mgr

Notice to Proceed 12/12/2019 Consultant

Est Completion Date 9/30/2020 Contact

Right of WayEst Start 9/30/2020 ROW Agent

Completion Date 9/22/2021 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 1/4/2022 Proj Inspector

Est Compl Date 9/19/2022

Project Status Notes

Utility Comments

  Commission approved design contract on Dec. 11.   Kickoff mee ng to be held early 

January 2020.   (BM 12-18-19)

Fairview Ave and Locust Grove Rd

  Widen and reconstruct the intersec on of Fairview Ave and Locust Grove Rd with 9 lanes 

on Fairview and 7 on Locust Grove.  Project includes a concrete intersection, buffered bike 

lanes, new curb, gutter, sidewalk, and traffic signals.

Brian McCarthy

Precision Engineering LLC

Joel Grounds

Dave Serdar

12/31/2019 11:12 AM 48 of 91 

Page 52: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN217‐09 Contract No

Prj No 820019 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 6 Prj Mgr

Notice to Proceed 12/9/2019 Consultant

Est Completion Date 10/2/2020 Contact

Right of WayEst Start 10/2/2020 ROW Agent

Completion Date 3/9/2021 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 6/25/2021 Proj Inspector

Est Compl Date 10/12/2021

Project Status Notes

Utility Comments

  Awai ng NTP and signiture from Keller for Contract (JT 12/04)

Fairview Ave and Milwaukee St Accessible Pedestrian Signal

Jason Tugby

Keller Associates Inc

Rob Gronowski

Dave Serdar

12/31/2019 11:12 AM 49 of 91 

Page 53: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS 102650 Contract No

Prj No 320093.0CD ITD Key No

Project Description

Current Project Phase 10 Ready DSN

DesignStatus 17 Prj Mgr

Notice to Proceed 11/18/2019 Consultant

Est Completion Date Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 5/12/2020 Proj Inspector

Est Compl Date 9/18/2020

Project Status Notes

Utility Comments

  NTP signed 11-20 Precision Engineers (JT 12/04)

Five Mile and Seneca Pedestrian Crossing

Jason Tugby

Precision Engineering LLC

Joel Grounds

Dave Serdar

12/31/2019 11:12 AM 50 of 91 

Page 54: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS 102342 Contract No

Prj No 320090.0CD ITD Key No

Project Description

Current Project Phase 10 Ready DSN

DesignStatus 18 Prj Mgr

Notice to Proceed 11/18/2019 Consultant

Est Completion Date Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 5/12/2020 Proj Inspector

Est Compl Date 9/18/2020

Project Status Notes

Utility Comments

   NTP signed 11-20 Precision Engineers (JT 12/04) 

Five Mile and Smoke Ranch Pedestrian Crossing

Jason Tugby

Precision Engineering LLC

Joel Grounds

Dave Serdar

12/31/2019 11:12 AM 51 of 91 

Page 55: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM213‐15 Contract No

Prj No 819030 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 99 Prj Mgr

Notice to Proceed 2/19/2019 Consultant

Est Completion Date 8/30/2019 Contact

Right of WayEst Start 9/3/2019 ROW Agent

Completion Date 4/6/2020 Possession % 8

ConstructionStatus 0 Contractor

Notice to Proceed 7/27/2021 Proj Inspector

Est Compl Date 10/6/2021

Project Status Notes

Utility Comments

 95% completed. Additional sidewalks to be designed with supplimental on Haines St with 

storm water midigation. SME completed and in progress  (12.04.19 JT)

Franklin St, McKinley St to Pierce St

  Construct sidewalk on the north side of Franklin Street, between McKinley Street and 

Pierce Street. Sidewalk will provide a safe walking route for students of Roosevelt School 

and provide a connection to a public bus route on Haines St.

Jason Tugby

T-O Engineers Inc

Jeff Werner

Renee Jayo

12/31/2019 11:12 AM 52 of 91 

Page 56: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM217‐29 Contract No

Prj No 819007 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 12/20/2018 Consultant

Est Completion Date 9/13/2019 Contact

Right of WayEst Start 9/13/2019 ROW Agent

Completion Date 8/27/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 2/16/2022 Proj Inspector

Est Compl Date 6/3/2022

Project Status Notes

Utility Comments

 ROW underway. SMJ 12/13/19

Garden St Franklin Rd to Bethel St

  Rebuild road to a 33’ cross sec on including curb, gu er, and sidewalk to Alpine Street. 

Rebuild road to a 36’ cross section including curb, gutter, and sidewalk south of Alpine 

Street. Design project to minimize and not disturb existing railroad crossing.

Seth Jarsky

Parametrix Inc

Harvin Flores

Renee Jayo

12/31/2019 11:12 AM 53 of 91 

Page 57: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MA212‐01 Contract No

Prj No 218049 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 69 Prj Mgr

Notice to Proceed 12/6/2018 Consultant

Est Completion Date 2/11/2020 Contact

Right of WayEst Start 2/11/2020 ROW Agent

Completion Date 9/30/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 2/7/2022 Proj Inspector

Est Compl Date 8/11/2022

Project Status Notes

Utility Comments

 95% design submittal expected in December.  (BM 11-20-19)

Gowen Rd Bridge 2110

 Replace

existing bridge with a single span four lane bridge with curb,

gutter, attached sidewalks, and bike lanes. Install a 5 lane section with bike lanes and 

attached

sidewalk on both approaches, connecting to the intersection of Gowen and

Eisenman to the east and the intersection of Gowen and Exchange on the west.

Replace the pedestrian ramps on Gowen at Eisenman with ADA compliant pedestrian

ramps.

Brian McCarthy

HDR Engineering Inc

Pete Eschbacher

Renee Jayo

12/31/2019 11:12 AM 54 of 91 

Page 58: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MA215‐01 Contract No CT219‐32

Prj No 217015 ITD Key No

Project Description

Current Project Phase 19 Construction

DesignStatus 100 Prj Mgr

Notice to Proceed 1/9/2017 Consultant

Est Completion Date 1/29/2018 Contact

Right of WayEst Start 11/20/2017 ROW Agent

Completion Date 12/18/2017 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 12/2/2019 Proj Inspector

Est Compl Date 5/1/2020

Project Status Notes

Utility Comments

Knife River

Herman

 NTP December 1. Construction started, Bridge removed. (CD 12/16/19)

Gowen Rd Bridge 2173

  Replace aging structure over New York Canal on Gowen Rd as part of ACHD's Bridge 

Maintenance Program.

Chris Dayley

HW Lochner Inc

Vance Henry, Lochner

12/31/2019 11:12 AM 55 of 91 

Page 59: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM211‐57 Contract No CT220‐03

Prj No 816002.008 ITD Key No

Project Description

Current Project Phase 17 Bid and Award

DesignStatus 100 Prj Mgr

Notice to Proceed 12/4/2015 Consultant

Est Completion Date 1/26/2017 Contact

Right of WayEst Start 11/21/2016 ROW Agent

Completion Date 5/31/2018 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 5/4/2020 Proj Inspector

Est Compl Date 7/31/2020

Project Status Notes

Utility Comments

 Bid opening held on 12-18-19. Project will be packaged with Warm Springs, Glacier to 

Glacier. DJR (12/17/19)

Holcomb Rd, Eastgate Dr to Amity Rd

 Construct 5' detached sidewalk on the east side of Holcomb Rd between Mendota Dr and 

Amity Rd in accordance with the Southeast Boise Neighborhood Plan. Stripe Bke lanes and 

install wayfinding signage for a bike facility from Amity Rd to Mimosa Way. Project will  

provide ped/bike connection from Oregon Trail Heights / Coulbia Village to Holcomb 

path/bridge and Southeast Boise. In‐House Design

Dave Rader

ACHD Design

Pierson Dewit

Renee Jayo

12/31/2019 11:12 AM 56 of 91 

Page 60: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM217‐22 Contract No

Prj No 820014 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 52 Prj Mgr

Notice to Proceed 11/21/2019 Consultant

Est Completion Date 3/6/2020 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 4/27/2020 Proj Inspector

Est Compl Date 7/7/2020

Project Status Notes

Utility Comments

  The Project is in the Design Phase as is on schedule.                     [JT III - 12-13-19]

Horseshoe Bend Rd and Shadowview Rd Ped Crossing

  Install curb ramps, a striped pedestrian crossing, and refuge island on Horseshoe Bend Rd 

on the north side of Shadowview St.         In‐house design.

Joe Tate

ACHD Design

Jeremy Andree, David Sasso

Renee Jayo

12/31/2019 11:12 AM 57 of 91 

Page 61: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN216‐01 Contract No

Prj No 320013 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 21 Prj Mgr

Notice to Proceed 9/30/2019 Consultant

Est Completion Date 11/6/2020 Contact

Right of WayEst Start 11/6/2020 ROW Agent

Completion Date 9/30/2021 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 3/6/2023 Proj Inspector

Est Compl Date 9/8/2023

Project Status Notes

Utility Comments

  The project is in the design phase and is on schedule.                    [J Tate III - 12-13-19]

Lake Hazel Rd and Eagle Rd

  Widen and signalize intersec on to 4/5 lanes on Eagle Rd and 3/5 lanes on Lake Hazel Rd 

as per the 2016 CIP. In‐house Design

Joe Tate

ACHD Design

Jeremy Andree

Michele White

12/31/2019 11:12 AM 58 of 91 

Page 62: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN205‐59 Contract No

Prj No 318038 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 99 Prj Mgr

Notice to Proceed 1/17/2018 Consultant

Est Completion Date 3/1/2019 Contact

Right of WayEst Start 2/1/2019 ROW Agent

Completion Date 1/12/2023 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 10/16/2024 Proj Inspector

Est Compl Date 1/2/2025

Project Status Notes

Utility Comments

 Plans have been delivered to the ROW team for acquisition and is on hold. 11.26.19 RC

Lake Hazel Rd and Five Mile Rd

  Reconstruct intersec on to a 7x6 signalized intersec on.

Ryan Cutler

HDR Engineering Inc

Cameron Waite

Becca Randall, Dave Serdar

12/31/2019 11:12 AM 59 of 91 

Page 63: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS 103080 Contract No

Prj No 820098.0CD ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 28 Prj Mgr

Notice to Proceed 12/23/2019 Consultant

Est Completion Date Contact

Right of WayEst Start 10/1/2019 ROW Agent

Completion Date 10/1/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 6/11/2020 Proj Inspector

Est Compl Date 8/7/2020

Project Status Notes

Utility Comments

Lake Hazel Rd, Cloverdale Rd to Five Mile Rd Pedestrian Improvements

Cody Homan

HW Lochner Inc

Justin Schwalbe

No R/W

12/31/2019 11:12 AM 60 of 91 

Page 64: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN211‐01 Contract No

Prj No 313024 ITD Key No 13492

Project Description

Current Project Phase 16 Shelved/Bid Ready

DesignStatus 100 Prj Mgr

Notice to Proceed 5/16/2014 Consultant

Est Completion Date 9/29/2017 Contact

Right of WayEst Start 9/29/2017 ROW Agent

Completion Date 2/4/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 3/31/2020 Proj Inspector

Est Compl Date 9/30/2020

Project Status Notes

Utility Comments

 The ROW Certification was received on 2/4/19. The plans are now shelf-ready. 

Construction is planned for FY20.  [JT III - 12/13/19]

Linder Rd and Deer Flat Rd

  Federal aid project to improve intersec on of Linder Rd and Deer Flat Rd, including curb, 

gutter, sidewalk, and bike facilities.

Joe Tate

Parametrix Inc

Cody Janson

Bill Nelson

12/31/2019 11:12 AM 61 of 91 

Page 65: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS RD213‐16 Contract No CT220‐09

Prj No 516019 ITD Key No

Project Description

Current Project Phase 17 Bid and Award

DesignStatus 100 Prj Mgr

Notice to Proceed 2/1/2016 Consultant

Est Completion Date 12/22/2016 Contact

Right of WayEst Start 12/22/2016 ROW Agent

Completion Date 9/22/2017 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 2/6/2020 Proj Inspector

Est Compl Date 7/2/2020

Project Status Notes

Utility Comments

 Responsive low bidder is Knife River Construction. Bid awarded January 8th. DJR 

(12/17/19)

Linder Rd, Franklin Rd to Pine Ave

 Widen Linder Road to 5 lanes with storm drain, curb, gutter, sidewalk and bike lanes in 

accordance with the 2012 CIP.  Project includes upgrade of the Union Pacific Railroad 

crossing, irrigation crossings and Bridge #131.  Project is the top priority safe routes to 

school request (2015) from the West Ada School District.

Dave Rader

HW Lochner Inc

Vance Henry

Michele White

12/31/2019 11:12 AM 62 of 91 

Page 66: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN209‐06 Contract No

Prj No 318048 ITD Key No 19944

Project Description

Current Project Phase 17 Bid and Award

DesignStatus 97 Prj Mgr

Notice to Proceed 8/1/2018 Consultant

Est Completion Date Contact

Right of WayEst Start 9/4/2018 ROW Agent

Completion Date 6/7/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 1/2/2020 Proj Inspector

Est Compl Date 8/18/2020

Project Status Notes

Utility Comments

 Project to be constructed by ITD beginning January 2020.  (BM 12-18-19)

Locust Grove Rd and Chinden Blvd Intersection

  Widen Locust Grove Rd at the intersec on of Chinden and Locust Grove to three lanes on 

the north side and five lanes on the south side to match the ITD cross‐section at this 

intersection. North of Chinden install attached five foot sidewalks, curb and gutter, and 

bike lanes. South of Chinden, install curb, gutter, and a detached 5' sidewalk on both sides 

of Locust Grove. Purchase ROW for future buildout of a displaced left intersection and two 

southbound receiving lanes. 

Brian McCarthy

Parametrix Inc

Dave Serdar

12/31/2019 11:12 AM 63 of 91 

Page 67: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS RD202‐44 Contract No

Prj No 519034 ITD Key No

Project Description

Current Project Phase 12 Design In House

DesignStatus 61 Prj Mgr

Notice to Proceed 12/5/2018 Consultant

Est Completion Date 5/18/2020 Contact

Right of WayEst Start 5/18/2020 ROW Agent

Completion Date 6/29/2021 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 11/18/2021 Proj Inspector

Est Compl Date 2/3/2022

Project Status Notes

Utility Comments

  Project in beginning phase of design with 50% plans an cipated in August and PIM #1 in 

September. 8.26.19 RC

Locust Grove Rd, Victory Rd to Overland Rd

 Widen Locust Grove Rd to five lanes in accordance with the 2016 Capital Improvements 

Plan. Install 5’ detached sidewalks and buffered bike lanes. Relocate the Pedestrian Hybrid 

Beacon (PHB) at Bassett Street. Install a Pedestrian Hybrid Beacon at Time Zone Dr. 

Relocate impacted utility poles and the utility boxes at Doberman. Replace the bridge 

#2087 over Nine Mile Creek with a stiff leg culvert to accommodate final cross section. 

Ryan Cutler

ACHD Design

Renee Jayo, Dave Serdar

12/31/2019 11:12 AM 64 of 91 

Page 68: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS RD207‐22 Contract No

Prj No 517039 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 12/14/2016 Consultant

Est Completion Date 6/21/2019 Contact

Right of WayEst Start 7/8/2019 ROW Agent

Completion Date 6/16/2020 Possession % 39

ConstructionStatus 0 Contractor

Notice to Proceed 11/4/2020 Proj Inspector

Est Compl Date 9/22/2021

Project Status Notes

Utility Comments

 ROW phase in process. 11.26.19 RC

Maple Grove Rd, Victory Rd to Overland Rd

  Widen Maple Grove Rd to 5 lanes with curb, gu er, sidewalk, & bike lanes in accordance 

with the 2012 CIP. Project includes reconstruction/widening of Maple Grove bridges 

#1237, #1238, and #1242 and installation of enhanced pedestrian crossings at Targee and 

Maple Grove Elementary.

Ryan Cutler

Horrocks Engineers Inc

Heidi Carter

Michele White

12/31/2019 11:12 AM 65 of 91 

Page 69: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM217‐23 Contract No

Prj No 819031 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 10/26/2018 Consultant

Est Completion Date 10/18/2019 Contact

Right of WayEst Start 10/18/2019 ROW Agent

Completion Date 1/20/2020 Possession % 27

ConstructionStatus 0 Contractor

Notice to Proceed 1/22/2020 Proj Inspector

Est Compl Date 4/9/2020

Project Status Notes

Utility Comments

 12/13 ROW underway  SMJ 12/13/19

McMillan Rd and Leather Way Pedestrian Crossing

  Install an enhanced pedestrian crossing (pedestrian hybrid beacon) on McMillan Rd at 

Leather Way. In‐house design .

Seth Jarsky

ACHD Design

Bill Nelson

12/31/2019 11:12 AM 66 of 91 

Page 70: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM214‐01 Contract No

Prj No 816031 ITD Key No

Project Description

Current Project Phase 17 Bid and Award

DesignStatus 100 Prj Mgr

Notice to Proceed 11/5/2015 Consultant

Est Completion Date 9/6/2017 Contact

Right of WayEst Start 9/6/2017 ROW Agent

Completion Date 7/25/2018 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 2/27/2020 Proj Inspector

Est Compl Date 7/20/2020

Project Status Notes

Utility Comments

 12/13 Schedule to bid January, NTP late February  SMJ 12/13/19

McMillan Rd, Westview Dr to Maple Grove Rd

  Complete sidewalk on the south side and an asphalt pathway on the north side of 

McMillan Rd from Westview Dr to Maple Grove Rd.  Project includes installation of an 

enhanced pedestrian crossing (PHB) at Mitchell St. 

Seth Jarsky

ACHD Design

Jeremy Andree

Michele White

12/31/2019 11:12 AM 67 of 91 

Page 71: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS RD207‐23 Contract No CT220‐01

Prj No 516027 ITD Key No

Project Description

Current Project Phase 19 Construction

DesignStatus 59 Prj Mgr

Notice to Proceed 12/7/2015 Consultant

Est Completion Date 12/19/2016 Contact

Right of WayEst Start 12/19/2016 ROW Agent

Completion Date 8/5/2019 Possession % 100

ConstructionStatus 6 Contractor

Notice to Proceed 12/2/2019 Proj Inspector

Est Compl Date 9/1/2020

Project Status Notes

Utility Comments

 Construction to begin November 12/2/19.  Idaho Power has already begun with 

relocations.  Temporary road closure of Meridian Rd to take place in January for 

replacement of the Settlers Canal culvert.  (BM, 12-18-19)

  U lity comments acquired.

 Idaho Power IUE corrridor in project

Meridian Rd, Cherry Ln to Ustick Rd

 Widen Meridian Rd to 5 lanes with curb, gutter, sidewalk and bike lanes in accordance 

with the 2012 CIP. Project includes reconstruction/widening of Meridian Rd Bridges #2045 

and #126X and enhanced pedestrian crossings at James Ct and Woodbury Dr. 

Brian McCarthy

Civil Survey Consultants

Tim Burgess

Renee Jayo

12/31/2019 11:12 AM 68 of 91 

Page 72: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM215‐17 Contract No

Prj No 820016 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 57 Prj Mgr

Notice to Proceed 11/14/2019 Consultant

Est Completion Date 4/17/2020 Contact

Right of WayEst Start 4/17/2020 ROW Agent

Completion Date 9/30/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 6/7/2021 Proj Inspector

Est Compl Date 8/16/2021

Project Status Notes

Utility Comments

  The Project is in the Design Phase and is on schedule.                  [JT III - 12/13/19]

Overland Rd and Phillippi St Ped Crossing

  Install an enhanced crossing (pedestrian hybrid beacon) across Overland Rd at Phillippi St 

as per the Central Bench Neighborhood Plan. In‐house design.

Joe Tate

CH2M Hill Engineers Inc

George Van Horn

Becca Randall

12/31/2019 11:12 AM 69 of 91 

Page 73: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS NE204.01 Contract No

Prj No 816002.017 ITD Key No

Project Description

Current Project Phase 16 Shelved/Bid Ready

DesignStatus 100 Prj Mgr

Notice to Proceed 4/7/2016 Consultant

Est Completion Date 4/12/2017 Contact

Right of WayEst Start 4/12/2017 ROW Agent

Completion Date 8/7/2017 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 1/4/2021 Proj Inspector

Est Compl Date 7/14/2021

Project Status Notes

Utility Comments

 The final submittal was received on 9/28/17 and the project is shelf-ready. [JT III - 

12/13/19]

Phillippi St, Malad St to Targee St

  Complete curb, gu er, & sidewalk improvements on both sides of Phillippi St between 

Malad St and Targee St in accordance with the Central Bench Neighborhood Plan.

Joe Tate

Riedesel Engineering Inc

Pierson Dewit

Michele White

12/31/2019 11:12 AM 70 of 91 

Page 74: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM210‐49 Contract No

Prj No 817021.001 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 100 Prj Mgr

Notice to Proceed 11/4/2016 Consultant

Est Completion Date 7/18/2018 Contact

Right of WayEst Start 9/6/2016 ROW Agent

Completion Date 7/2/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 2/5/2021 Proj Inspector

Est Compl Date 7/28/2021

Project Status Notes

Utility Comments

 Re-design incorporating reduced street section is complete.  Initiating cultural scan.  DJR 

(12/17/19)

Phillippi Street, Targee Street to Overland Road

 Construct curb, gutter & sidewalk on the east side of Phillippi St between Targee St & 

Overland Rd in accordance with the Central Bench Neighborhood Plan. Project includes a 

partial pavement rehabilitation. 

Dave Rader

ACHD Design

Jeremy Andree

Dave Serdar

12/31/2019 11:12 AM 71 of 91 

Page 75: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM211‐34 Contract No CT220‐08

Prj No 818041 ITD Key No

Project Description

Current Project Phase 19 Construction

DesignStatus 100 Prj Mgr

Notice to Proceed 12/29/2017 Consultant

Est Completion Date 9/27/2018 Contact

Right of WayEst Start 9/28/2018 ROW Agent

Completion Date 9/30/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 5/29/2020 Proj Inspector

Est Compl Date 8/31/2020

Project Status Notes

Utility Comments

Compliance Solutions & Contract

 Bids opened Nov 13, Compliance Solutons & Contracting is the apparrent low bidder. 

Commision awarded 12/4/19  (CD 12/16/19)

Pierce St, Washington St to Shenandoah Dr

  Reconstruct

Pierce St from Washington St to Shenandoah Dr, install 5‐foot wide sidewalk on

the west side of Pierce St, install pedestrian curb ramps, small section curb

and gutter, storm drain manholes and piping, catch basins, two seepage beds,

and associated appurtenances. 

Chris Dayley

T-O Engineers Inc

Pat Colwell

Becca Randall, Dave Serdar

12/31/2019 11:12 AM 72 of 91 

Page 76: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM211‐25 Contract No

Prj No 816002.016 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 11/25/2015 Consultant

Est Completion Date 6/22/2017 Contact

Right of WayEst Start 6/22/2017 ROW Agent

Completion Date 9/24/2018 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 12/16/2021 Proj Inspector

Est Compl Date 5/11/2022

Project Status Notes

Utility Comments

 Construction has been reprogrammed for FY22.  (BM, 2-19-19)

Roosevelt St, Rose Hill St to Emerald St (West Side)

  Construct sidewalks on the west side of Roosevelt St between Rose Hill St & Emerald St in 

accordance with the Central Bench Neighborhood Plan. Project will improve connectivity 

for students attending Jefferson Elementary.  Project also includes full width pavement 

maintenance under project #517018.

Brian McCarthy

Precision Engineering LLC

Joel Grounds

Bill Nelson

12/31/2019 11:12 AM 73 of 91 

Page 77: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS 102970 Contract No

Prj No 820092.0CD ITD Key No

Project Description

Current Project Phase 10 Ready DSN

DesignStatus 27 Prj Mgr

Notice to Proceed 1/2/2020 Consultant

Est Completion Date 4/21/2020 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 6/29/2020 Proj Inspector

Est Compl Date 7/28/2020

Project Status Notes

Utility Comments

  12/13 Finalizing SOW/PSA w WH Pacific   12/13/19 SMJ

Royal Blvd, La Pointe St to Lusk St

  Install 5‐foot wide detached asphalt pathway on Royal Blvd from La Pointe to Lusk St to fill 

pedestrian gaps. Install ADA‐compliant ramps as necessary. Near multiple parks and BSU. 

2020 Commission Directive Projects. 

Seth Jarsky

WH Pacific

No R/W

12/31/2019 11:12 AM 74 of 91 

Page 78: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MI215‐09 Contract No

Prj No 219024 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 97 Prj Mgr

Notice to Proceed 1/17/2019 Consultant

Est Completion Date 7/15/2019 Contact

Right of WayEst Start 7/15/2019 ROW Agent

Completion Date 9/30/2020 Possession % 18

ConstructionStatus 0 Contractor

Notice to Proceed 1/21/2021 Proj Inspector

Est Compl Date 6/4/2021

Project Status Notes

Utility Comments

  The project is in the ROW phase and is on schedule.                     [JT III - 12/13/19]

  N/A

Shamrock Ave Bridge No 1424

  Replace Bridge #1424 over the South Slough on Shamrock Avenue as part of ACHD's Bridge 

Maintenance Program.

Joe Tate

Elite Edge Engineers

Pierson Dewit / Future Selected D

Michele White

12/31/2019 11:12 AM 75 of 91 

Page 79: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS BK213‐04 Contract No

Prj No 818014 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 2/1/2019 Consultant

Est Completion Date 10/14/2019 Contact

Right of WayEst Start 10/14/2019 ROW Agent

Completion Date 2/26/2020 Possession % 4

ConstructionStatus 0 Contractor

Notice to Proceed 6/12/2020 Proj Inspector

Est Compl Date 9/30/2020

Project Status Notes

Utility Comments

 12/13 ROW underway   SMJ 12/13 /19

Shoshone St Bikeway, Canal St to Capital Blvd

Improve Shoshone St as part of the regional low stress bikeway network from Canal St to 

Capital Blvd. Project includes cycle track at Overalnd and Shoshone intersection, RRFB at 

Rose Hill and Shoshone intersection, bulb outs at Nez Perce and Shoshone intersection, 

bikeway wayfinding and markings.

Seth Jarsky

Kittelson & Associates

Bill Nelson

12/31/2019 11:12 AM 76 of 91 

Page 80: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN210‐03 Contract No

Prj No 317044 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 85 Prj Mgr

Notice to Proceed 1/2/2018 Consultant

Est Completion Date 5/24/2019 Contact

Right of WayEst Start ROW Agent

Completion Date 9/1/2020 Possession % 30

ConstructionStatus 0 Contractor

Notice to Proceed 1/12/2021 Proj Inspector

Est Compl Date 10/22/2021

Project Status Notes

Utility Comments

  The project is in the ROW phase and is on schedule. Re-design to add a south leg to the 

intersection is also now underway.  [JT III - 12/13/19]

State St and Pierce Park Ln

  Rebuild the State Street and Pierce Park Ln intersec on in accordance with the State Street 

Transit and Traffic Operations Plan (TTOP).  The State Street TTOP call for expanding State 

Street to three lanes in each direction with bike lanes and a center turn lane.  The two 

outermost vehicular lanes would eventually be reserved for buses and high occupancy 

vehicles.  The Pierce Park leg of the intersection will need to be reconfigured to intersect 

State Street at between 75 and 90 degrees.

Joe Tate

Parametrix Inc

Cody Janson

Bill Nelson

12/31/2019 11:12 AM 77 of 91 

Page 81: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MIS216‐02 Contract No

Prj No 717040 ITD Key No 20275

Project Description

Current Project Phase 19 Construction

DesignStatus 100 Prj Mgr

Notice to Proceed 1/26/2018 Consultant

Est Completion Date 11/5/2018 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 8/8/2019 Proj Inspector

Est Compl Date 1/31/2020

Project Status Notes

Utility Comments

  The project is in the Construc on Phase and is ahead of schedule. [JT III - 12/13/19]

State St, 16th to 23rd Street Lighting Improvements

  This Local Highway Safety Improvement Project (LHSIP) is a federal aid safety project to 

install continuous street lighting to improve visibility and reduce nighttime crashes.

Joe Tate

Precision Engineering LLC

Joel Grounds

No R/W

12/31/2019 11:12 AM 78 of 91 

Page 82: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN205‐03 Contract No

Prj No 308004 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 12/2/2016 Consultant

Est Completion Date 9/11/2018 Contact

Right of WayEst Start 9/11/2018 ROW Agent

Completion Date 10/11/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 12/13/2021 Proj Inspector

Est Compl Date 5/6/2022

Project Status Notes

Utility Comments

 R/W is complete.  Awaiting Bureau of Reclamation and Army Corps permits/agreements  

Construction is currently programmed for FY22.  (BM, 12-18-19)

Ten Mile Rd and Amity Rd

 Construct a multi‐lane roundabout at the intersection of Ten Mile Rd and Amity Rd to 

maintain efficient and safe traffic operations. Project includes Ten Mile Bridge #1182.  

Brian McCarthy

ACHD Design

Jeremy Andree

Bill Nelson

12/31/2019 11:12 AM 79 of 91 

Page 83: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM217‐52 Contract No

Prj No 819039 ITD Key No

Project Description

Current Project Phase 20 Construction In House

DesignStatus 100 Prj Mgr

Notice to Proceed 2/25/2019 Consultant

Est Completion Date 8/30/2019 Contact

Right of WayEst Start 8/30/2019 ROW Agent

Completion Date 11/5/2019 Possession % 100

ConstructionStatus 77 Contractor

Notice to Proceed 11/12/2019 Proj Inspector

Est Compl Date 2/18/2020

Project Status Notes

Utility Comments

 12/13 Construction to be substantially complete week of Dec 16.  SMJ 12/13/19

Ten Mile Rd and Crenshaw St Pedestrian Crossing

  Install an enhanced pedestrian crossing (pedestrian hybrid beacon) on Ten Mile Rd at 

Crenshaw St. In‐house design and build. 

Seth Jarsky

ACHD Design

Jeremy Andree

Dave Serdar

12/31/2019 11:12 AM 80 of 91 

Page 84: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN214‐03 Contract No

Prj No 319038 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 60 Prj Mgr

Notice to Proceed 1/21/2019 Consultant

Est Completion Date 2/26/2020 Contact

Right of WayEst Start 2/26/2020 ROW Agent

Completion Date 9/14/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 12/23/2020 Proj Inspector

Est Compl Date 8/26/2021

Project Status Notes

Utility Comments

 Design of the phased  mul -lane roundabout ongoing.  Online PIM underway with the Ten 

Mile, Victory to Overland project, comment period ends Dec. 20th. (CH 12/09/19)

Ten Mile Rd and Victory Rd

  Widen the intersec on or replace with a roundabout. A traffic analysis will be done to 

determine the ultimate lane configuration based on growth above projections in the area. 

Includes the replacement/widening of the bridge over the irrigation lateral on Ten Mile Rd, 

north of Victory Rd.Design will be coordinated with the Ten Mile Rd, Victory Rd to Overland 

Rd project to widen Ten Mile Rd to 5‐lanes (In‐house design).  These project are planned to 

be bid together.

Cody Homan

Six Mile Engineering PA

Jeff Jones

Dave Serdar

12/31/2019 11:12 AM 81 of 91 

Page 85: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS RD202‐31 Contract No

Prj No 518030 ITD Key No

Project Description

Current Project Phase 19 Construction

DesignStatus 100 Prj Mgr

Notice to Proceed 11/6/2017 Consultant

Est Completion Date 12/7/2018 Contact

Right of WayEst Start 9/5/2017 ROW Agent

Completion Date 7/10/2019 Possession % 100

ConstructionStatus 23 Contractor

Notice to Proceed 9/16/2019 Proj Inspector

Est Compl Date 10/13/2020

Project Status Notes

Utility Comments

 Construction is underway. DJR (12/17/19)

  Pothole 4-15-2018 SCB

Ten Mile Rd, McMillan Rd to Chinden Blvd

Widen Ten Mile Rd to five lanes with curb, gutter, sidewalk and bike lanes in accordance 

with the 2016 CIP. 

Dave Rader

ACHD Design

Kraig Wartman

Bill Nelson

12/31/2019 11:12 AM 82 of 91 

Page 86: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS RCO299 Contract No

Prj No 519041 ITD Key No

Project Description

Current Project Phase 12 Design In House

DesignStatus 60 Prj Mgr

Notice to Proceed 1/4/2019 Consultant

Est Completion Date 2/26/2020 Contact

Right of WayEst Start 2/26/2020 ROW Agent

Completion Date 9/14/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 12/23/2020 Proj Inspector

Est Compl Date 8/26/2021

Project Status Notes

Utility Comments

  Design ongoing, In-house. Online PIM underway with the Ten Mile/Victory project, 

comment period ends Dec. 20th. (CH 12/09/19)

Ten Mile Rd, Victory Rd to Overland Rd

  Widen Ten Mile Rd to 5 lanes with curb, gu er, sidewalk and a Level 3 bike facility in 

accordance with the 2016 CIP and Master Street Map. In‐house design. 

Cody Homan

ACHD Design

Jeremy Andree

Bill Nelson

12/31/2019 11:12 AM 83 of 91 

Page 87: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS RD202‐32 Contract No CT220‐07

Prj No 518001 ITD Key No

Project Description

Current Project Phase 19 Construction

DesignStatus 46 Prj Mgr

Notice to Proceed 10/18/2017 Consultant

Est Completion Date 10/16/2018 Contact

Right of WayEst Start 10/16/2018 ROW Agent

Completion Date 9/16/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 12/30/2019 Proj Inspector

Est Compl Date 9/14/2020

Project Status Notes

Utility Comments

 Bid awarded on 12/4/19 to Central Paving. Utility preconstruction meeting held on 

12/9/19. DJR (12/17/19)

Ten Mile Road, Ustick Road to McMillan Road

  Widen Ten Mile Road from 2 to 5 lanes with curb, gu er and sidewalk and bike lanes in 

accordance with 2016 CIP. Five detached sidewalks will be constructed on each side of the 

street. New pedesterian hybrid beacons will be installed at both the Five Mile Creek 

Pathway and just south of Vecenza way. The project alson includes replacing bridge #2044 

over the Five Mile Creeek and bridge #1103 over the Creason Lateral.

Dave Rader

Civil Survey Consultants

Matt Hart

Renee Jayo

12/31/2019 11:12 AM 84 of 91 

Page 88: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS MDR218‐02 Contract No

Prj No 220003 ITD Key No

Project Description

Current Project Phase 10 Ready DSN

DesignStatus 7 Prj Mgr

Notice to Proceed 1/6/2020 Consultant

Est Completion Date 8/11/2020 Contact

Right of WayEst Start 8/11/2020 ROW Agent

Completion Date 7/27/2021 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 11/1/2021 Proj Inspector

Est Compl Date 1/18/2022

Project Status Notes

Utility Comments

 12/12 Meeting w Legal, resume w FY20 Design and FY21 ROW   SMJ 12/13/19

Thurman Mill Bridge Projects

  Provide water quality and quan ty mi ga on for a series of bridge projects being 

reconstructed in or near the Thurman Mill drainage area. 

Seth Jarsky

J-U-B Engineers Inc

Dave Serdar

12/31/2019 11:12 AM 85 of 91 

Page 89: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM217‐53 Contract No

Prj No 819014 ITD Key No

Project Description

Current Project Phase 15 Right of Way

DesignStatus 100 Prj Mgr

Notice to Proceed 12/6/2018 Consultant

Est Completion Date 5/10/2019 Contact

Right of WayEst Start 6/5/2019 ROW Agent

Completion Date 9/4/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 5/28/2020 Proj Inspector

Est Compl Date 8/7/2020

Project Status Notes

Utility Comments

 Project is in right-of-way. DJR (12/17/19)

Ustick Rd and Milwaukee St School Zone

  Pavement rehabilita on and upgrade pedestrian ramps on specified residen al street 

segments. Segments identified as part of ACHD's Pavement Management Program. Project 

funded or in part through House Bill 312 funding.

Dave Rader

Six Mile Engineering PA

Larry White

Michele White

12/31/2019 11:12 AM 86 of 91 

Page 90: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM214‐61 Contract No CT220‐12

Prj No 819027 ITD Key No

Project Description

Current Project Phase 17 Bid and Award

DesignStatus 90 Prj Mgr

Notice to Proceed 1/14/2019 Consultant

Est Completion Date 8/12/2019 Contact

Right of WayEst Start 8/12/2019 ROW Agent

Completion Date 11/19/2019 Possession % 100

ConstructionStatus 0 Contractor

Notice to Proceed 6/15/2020 Proj Inspector

Est Compl Date 8/11/2020

Project Status Notes

Utility Comments

  Construc on phase has been moved to FY 20. ROW Cert submi ed. 100% plans 

submitted. Scheduled to bid in Jan. (CD 12/16/19)   

  N/A

Valley St, Lake Hazel Rd to La Grange St

  Install approximately 860LF of new curb, gu er, sidewalk, and remove and replace 

approximately 385LF of sidewalk on the west side of Valley Street in front of the school. 

Upgrade and install 7 curb ramps, a seepage bed, driveway approach, crosswalk and 

luminaire.

Chris Dayley

Six Mile Engineering PA

Leah Kelsey

Renee Jayo, Dave Serdar

12/31/2019 11:12 AM 87 of 91 

Page 91: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS IN215‐06 Contract No

Prj No 319043 ITD Key No

Project Description

Current Project Phase 12 Design In House

DesignStatus 58 Prj Mgr

Notice to Proceed 12/5/2018 Consultant

Est Completion Date 4/30/2020 Contact

Right of WayEst Start 4/30/2020 ROW Agent

Completion Date 7/19/2021 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 11/18/2021 Proj Inspector

Est Compl Date 2/3/2022

Project Status Notes

Utility Comments

  Project is in 95% design phase. (RC 11.30.19)

Victory Rd and Locust Grove Rd Roundabout

  Replace intersec on of Victory Rd and Locust Grove Rd with a two lane roundabout in 

accordance with the 2016 Capital Improvements Plan. Shift the roundabout slightly to the 

northeast of the center of the existing intersection to minimize right‐ of‐way impacts.

Ryan Cutler

ACHD Design

Renee Jayo, Dave Serdar

12/31/2019 11:12 AM 88 of 91 

Page 92: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM215‐19 Contract No

Prj No 318032 ITD Key No

Project Description

Current Project Phase 16 Shelved/Bid Ready

DesignStatus 100 Prj Mgr

Notice to Proceed 1/11/2018 Consultant

Est Completion Date 7/20/2018 Contact

Right of WayEst Start 4/23/2018 ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 5/26/2020 Proj Inspector

Est Compl Date 8/26/2020

Project Status Notes

Utility Comments

   The project is shelved / bid ready.  [JT III- 12/13/19]

Victory Rd and Standing Timber Ave Pedestrian Crossing

Installation of a Pedestrian hybrid beacon (PHB) on the west side of Standing Timber Ave. 

across from Victory Rd.  Install directional ramps on both sides of intersection and place 

ramps just west of the existing crossing to avoid impacts to storm drain infrastructure.

Joe Tate

CH2M Hill Engineers Inc

George Van Horn

No R/W

12/31/2019 11:12 AM 89 of 91 

Page 93: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM214‐47 Contract No

Prj No 820017 ITD Key No

Project Description

Current Project Phase 11 Design

DesignStatus 20 Prj Mgr

Notice to Proceed 11/15/2019 Consultant

Est Completion Date 4/30/2020 Contact

Right of WayEst Start 4/30/2020 ROW Agent

Completion Date 9/16/2020 Possession % 0

ConstructionStatus 0 Contractor

Notice to Proceed 4/26/2022 Proj Inspector

Est Compl Date 6/22/2022

Project Status Notes

Utility Comments

  Executed PSA with design consultant. Held kick-off mee ng on Oct 22. Design started. 

30% design due Jan 23, 2020. (CD 12/16/19)

Vista Ave and Nez Perce St Ped Crossing

 Design

and install a marked crosswalk and HAWK, including bike push buttons on Vista

at Nez Perce (South side of the intersection). Remove and install ADA compliant

directional curb ramps. Install bus stops closer to Nez Perce.  

Chris Dayley

Precision Engineering LLC

Joel Grounds

Becca Randall

12/31/2019 11:12 AM 90 of 91 

Page 94: Ada County Highway Districtachdidaho.org/Documents/PlansPrograms/DCR.pdf · 2020. 1. 2. · Ada County Highway District 3775 Adams Street - Garden City ID 83714-6447 Phone (208) 387-6100

Design & Construction Review (DCR)

GIS CM217‐01 Contract No CT220‐03

Prj No 819023 ITD Key No

Project Description

Current Project Phase 17 Bid and Award

DesignStatus 100 Prj Mgr

Notice to Proceed 1/7/2019 Consultant

Est Completion Date 9/30/2019 Contact

Right of WayEst Start ROW Agent

Completion Date Possession %

ConstructionStatus 0 Contractor

Notice to Proceed 5/4/2020 Proj Inspector

Est Compl Date 7/31/2020

Project Status Notes

Utility Comments

  The project is in the bid and award phase and is on schedule. [JT III - 12/13/19]

  N/A

Warm Springs Ave, Glacier Dr to Glacier Dr

  Construct sidewalk on the north side of Warm Springs Avenue from 320' northwest of 

Glacier Drive to the southeast corner of Riverland Terrace Subdivision. Priority request 

from the Boise School District.

Joe Tate

Precision Engineering LLC

Pierson Dewit / Future Selected C

No R/W

12/31/2019 11:12 AM 91 of 91