acrow northside bridge

Upload: franklin-garcia

Post on 04-Jun-2018

243 views

Category:

Documents


2 download

TRANSCRIPT

  • 8/13/2019 Acrow Northside Bridge

    1/12

    A-PLANT ACROWFORMWORK SOLUTION FOR NORTHSIDE BRIDGE

  • 8/13/2019 Acrow Northside Bridge

    2/12

  • 8/13/2019 Acrow Northside Bridge

    3/12

    Name: A-Plant Acrow Cantilever Formwork Solution for Northside Bridge

    Location Where Used: Northside Bridge, Workington

    Address: Ashtead Plant Hire Company Limited, 102 Dalton Avenue, Birchwood Park, Warrington WA3 6YE

    Web: www.aplant.com/acrow

    Telephone No: 01925 281000

    E-mail: [email protected]

    To watch a film about the project visit www.youtube.com/aplanthire

    3A-PLANT ACROWFORMWORK SOLUTION FOR NORTHSIDE BRIDGE

    www.aplant.com/acrow

  • 8/13/2019 Acrow Northside Bridge

    4/12

    4A-PLANT ACROWFORMWORK SOLUTION FOR NORTHSIDE BRIDGE

    www.aplant.com/acrow

  • 8/13/2019 Acrow Northside Bridge

    5/12

    5A-PLANT ACROWFORMWORK SOLUTION FOR NORTHSIDE BRIDGE

    www.aplant.com/acrow

  • 8/13/2019 Acrow Northside Bridge

    6/12

    6A-PLANT ACROWFORMWORK SOLUTION FOR NORTHSIDE BRIDGE

    www.aplant.com/acrow

  • 8/13/2019 Acrow Northside Bridge

    7/12

    An Introduction to the Project

    In November 2009, Workingtons Northside Bridge was swept away during devastating floods in Cumbria,

    tragically killing PC Bill Barker who was on the bridge diverting traffic. The collapse of the landmark bridge

    effectively split the town in two, resulting in an 18-mile round trip to get from one end of Workington to

    the other. Following the collapse, the Army erected a temporary footbridge named Barkers Crossing

    in memory of Bill Barker and this was dismantled to allow for a multi-million pound construction of

    Northside Bridge.

    The works involved the fabrication and construction of a 152m three-span composite steel/concrete

    highway bridge, being erected in the same position as the former structure over the River Derwent. The

    bridge reinstated pedestrian, vehicular and cycle access along the A597, which provides the main highway

    link to Workington from outlying areas. The structure is supported on concrete piers with bored pile

    foundations. The completed bridge was clad in sandstone, similar to that used on the original structure

    with reclaimed stone. Sandstone blocks were actually recovered from the collapsed structure of the bridge

    and stored for re-use in the replacement.

    The construction project was funded by the Department of Transport at an approximate cost of 11 million.

    Carried out over a 50+ week contract, A-Plant Acrow worked alongside the contractors Birse Civils and

    Mabey Bridge, the supplier of the steel beams, to provide a unique solution to help Workington become

    connected once again.

    7A-PLANT ACROWFORMWORK SOLUTION FOR NORTHSIDE BRIDGE

    www.aplant.com/acrow

  • 8/13/2019 Acrow Northside Bridge

    8/12

    Cantilever String Course Formwork Solution

    A-Plant Acrow was heavily involved in the consultation and design process for the new Northside Bridge.

    Through this we were awarded the work for the supply of the formwork for the pier bases, along with

    producing detailed schemes for the North and South abutments, which included design for a specially

    fabricated formwork end bull nose using Slimlite Soldiers and Mammoth Panels so the abutment could be

    cast as one.

    Following several visits to site, the experienced A-Plant Acrow Sales and Engineering Team devised a

    bespoke solution using a range of Acrow formwork products. Primarily based on the ESS21 Parapet

    Support System developed in-house, A-Plant were able to utilise our expertise in the market to ensure that

    Birse Civils and Mabey Bridge had a cost-effective, flexible and practical solution to enable construction of

    the bridge that had a curve on plan and elevation with inclined soffit on the cantilever.

    The ESS21 parapet formwork is a system of components that allows the user to construct cantilever

    formwork off the edges of steel beams. For this project it was clear from the start that due to the complex

    curve and slope on the new bridge we would need to provide tables of various lengths to fit its geometry.

    As part of the agreement the contractor built all the tables in the yard at the A-Plant Acrow depot in Glasgow

    and tagged the tables with a code number. With the aid of two yard staff and a forklift for their use they

    completed the tables in just one week, which enabled a significant cost saving for the table assembly. The

    system was of further benefit to the construction of the bridge deck cantilevers and as there was no lay downarea on the site where the tables could be built.

    A-Plant then delivered all the items to site, and by creating a temporary jig onsite the contractor was able to

    basically clip and pin all the parts together quickly and efficiently, before they were lifted into place. Once

    lifted the tables were connected to bridge beams via a simple triangular frame that was tied back using a tie

    rod. This then provided the base to set the forms and cast the concrete.

    The bridge cantilever formwork was erected to provide access along each edge and allow the sequential

    pours to be carried out. The design called for loads to be applied from the new deck in a precise process to

    ensure stability while the structure was being constructed. Due to the complex nature of this project, withsome of the bridge being over a road and some over water, the formwork was attached to the beams at

    various stages before eventually the main 66m and 88t centre beams were spectacularly and with expertise

    precision lifted by crane into place.

    Opened by Princess Anne in October 2012

    A-Plant Acrow is proud to have played such a

    key role in facilitating construction of this new

    structure.

    8A-PLANT ACROWFORMWORK SOLUTION FOR NORTHSIDE BRIDGE

    www.aplant.com/acrow

  • 8/13/2019 Acrow Northside Bridge

    9/12

    Drawings or Plans Demonstrating the

    Innovation

    9A-PLANT ACROWFORMWORK SOLUTION FOR NORTHSIDE BRIDGE

    www.aplant.com/acrow

  • 8/13/2019 Acrow Northside Bridge

    10/12

    10A-PLANT ACROWFORMWORK SOLUTION FOR NORTHSIDE BRIDGE

    www.aplant.com/acrow

  • 8/13/2019 Acrow Northside Bridge

    11/12

    11A-PLANT ACROWFORMWORK SOLUTION FOR NORTHSIDE BRIDGE

    www.aplant.com/acrow

  • 8/13/2019 Acrow Northside Bridge

    12/12