access on 11 october 2011 visit of muon pit area technical stop 7 – 11 november 2011
DESCRIPTION
3. 4. 1. 2. Access on 11 October 2011 Visit of muon pit area Technical Stop 7 – 11 November 2011 Access only from Tue 8 Nov – Friday 11 Nov (15:00) Transport of cables ~0.5 days Cable installation ~2 days Cable connection & testing ~1 day Installation of detectors Testing detectors! - PowerPoint PPT PresentationTRANSCRIPT
E. Gschwendtner, CERN
Access on 11 October 2011Visit of muon pit area
Technical Stop 7 – 11 November 2011Access only from Tue 8 Nov – Friday 11 Nov (15:00)Transport of cables ~0.5 daysCable installation ~2 daysCable connection & testing ~1 dayInstallation of detectorsTesting detectors!
In parallel:Power supplyFibre optics cablesEthernet installationInstallation of Racks
2nd SBWG, 14 Oct 2011
Only diamond detector installation feasible!
E. Gschwendtner, CERN
Fibre optics cables
2nd SBWG, 14 Oct 2011
US85 TE80
TZ80
Max 24 fibres ?
4 fibres ?
How many fibres do we need?
12 fibres8 fibres
E. Gschwendtner, CERN
Area 3: Crossing TNM41 – TZ81 and TNM42 – TZ82
To Area 2 (TNM42)
To Area 1 (TNM
41)
To A
rea
4
Electronics Rack
EthernetRack
2nd SBWG, 14 Oct 2011