Estimate For House -Type 01- Twin House Description Unit Qty Rate Rs. Ct A - Column & Plinth Beam 12 MM Tore Iron for Column & Plinth Beam 44 620.00 10 MM tore Iron for Basses 15 420.00 6 MM Iron Rods for Stirrups Kg 35 145.00 Binding wire Kg 3 185.00 Cement Bags 30 950.00 Sand Cubes 1.25 9,000.00 3/4" Mattel Cubes 2 7,000.00 Labour Chrges for Columns 6 6,750.00 Labour Chrges for Plinth Beam L Ft 70 250.00 Total Carreid to Summary B- Wall Bricks 1,060 8.50 Sand Cubes 0.5 9,000.00 Cement Bags 4 950.00 Labour Charges For Cement Blocks Works 1,060 7.50 Total Carreid to Summary C- Slab 12 MM Tore Iron for Beams 18 620.00 10 MM Tore Iron for Slab 105 420.00 6 MM Iron Rods for Stirrups Kg 15 145.00 Binding wire Kg 5 185.00 Cement Bags 32 950.00 Sand Cubes 1.25 9,000.00 3/4" Mattel Cubes 2 7,000.00 Labour Charges for Slab Sq Ft 336 95.00 Labour Charges for Tie Beams L Ft 70 125.00 Labour Charges for Stair Case 1 20,000.00 condute Work Total Carreid to Summary D-Plastering Cement Bags 8 950.00 Sand Cubes 0.5 11,000.00 Potty Bags 10 550.00 Labour Charges for plastering Sq Ft 326 25.00 Labour Charges for Pooty Works Sq Ft 662 15.00

Upload: ihsanbinhamza

Post on 11-Dec-2015

245 views

Category:

Documents


0 download

DESCRIPTION

Ablution Tank

TRANSCRIPT

Page 1: Ablution Tank

Estimate For House -Type 01- Twin House

Description Unit Qty Rate AmountRs. Cts Rs. Cts

A - Column & Plinth Beam12 MM Tore Iron for Column & Plinth Beam 44 620.00 27,280.00 10 MM tore Iron for Basses 15 420.00 6,300.00 6 MM Iron Rods for Stirrups Kg 35 145.00 5,075.00 Binding wire Kg 3 185.00 555.00 Cement Bags 30 950.00 28,500.00 Sand Cubes 1.25 9,000.00 11,250.00 3/4" Mattel Cubes 2 7,000.00 12,250.00 Labour Chrges for Columns 6 6,750.00 40,500.00 Labour Chrges for Plinth Beam L Ft 70 250.00 17,500.00 Total Carreid to Summary 149,210.00

B- WallBricks 1,060 8.50 9,010.00 Sand Cubes 0.5 9,000.00 4,500.00 Cement Bags 4 950.00 3,800.00 Labour Charges For Cement Blocks Works 1,060 7.50 7,950.00

Total Carreid to Summary 25,260.00

C- Slab12 MM Tore Iron for Beams 18 620.00 11,160.00 10 MM Tore Iron for Slab 105 420.00 44,100.00 6 MM Iron Rods for Stirrups Kg 15 145.00 2,175.00 Binding wire Kg 5 185.00 925.00 Cement Bags 32 950.00 30,400.00 Sand Cubes 1.25 9,000.00 11,250.00 3/4" Mattel Cubes 2 7,000.00 14,000.00 Labour Charges for Slab Sq Ft 336 95.00 31,920.00 Labour Charges for Tie Beams L Ft 70 125.00 8,750.00 Labour Charges for Stair Case 1 20,000.00 20,000.00 condute Work 6,000.00

Total Carreid to Summary 180,680.00

D-PlasteringCement Bags 8 950.00 7,600.00 Sand Cubes 0.5 11,000.00 5,500.00 Potty Bags 10 550.00 5,500.00 Labour Charges for plastering Sq Ft 326 25.00 8,150.00 Labour Charges for Pooty Works Sq Ft 662 15.00 9,930.00

Page 2: Ablution Tank

Total Carreid to Summary 36,680.00

E - Ablution Tank10 MM Tor Iron 46 420.00 19,320.00 Binding wire Kg 3 185.00 555.00 Cement Bages 7 950.00 6,650.00 Sand Cubes 0.25 9,000.00 2,250.00 3/4" Mattel Cubes 0.5 7,000.00 3,500.00 Labour Charges Sq Ft 108 275.00 29,700.00

Total Carreid to Summary 61,975.00

F- Floor Concrete & Tile WorksCement Sand3/4" Mattel12"x8" wall Tiles for Walls 198 80.00 15,840.00 12"x8" wall Tiles for both side of 333 80.00 26,640.00 Ablution TankFloor Tile 350 125.00 43,750.00 Labour Charges for Floor Concreting Sq Ft 350 40.00 14,000.00 Labour Charges for Floor Plastering Sq Ft 350 20.00 7,000.00 Labour Charges for wall Tiles Sq Ft 132 45.00 5,940.00 Labour Charges for Tiling for Tank Sq Ft 222 45.00 9,990.00 Labour Charges for Floor Tiles Sq Ft 350 45.00 15,750.00

Total Carreid to Summary 138,910.00

Estimate For Columns & Rubble Massionary Works

With D.P.C Concrete Finnishing

Description Unit Qty Rate Amount

Rs. Cts Rs. Cts

Page 3: Ablution Tank

A - Column & Plinth Beam

12 MM Tore Iron for Column 13 Columns 42 620.00 26,040.00

10 MM tore Iron for Basses 33 420.00 13,860.00

6 MM Iron Rods for Stirrups Kg 40 145.00 5,800.00

Binding wire Kg 5 185.00 925.00

Cement Bags 28 950.00 26,600.00

Sand Cubes 1 9,000.00 9,000.00

3/4" Mattel Cubes 2 7,000.00 12,250.00

Labour Chrges for Columns 13 5,000.00 65,000.00

Total Carreid to Summary 159,475.00

B- Rubble Massionary works

Rubble )6"x9" & 6"x4") 7 4,200.00 29,400.00

Sand Cubes 3 9,000.00 27,000.00

Cement Bags 49 950.00 46,550.00

Bricks 600 9.00 5,400.00

3/4" Mattel 0.75 7,000.00 5,250.00

12 MM Tore Iron 24 420.00 10,080.00

Labour charges for Rubble work 7 5,000.00 35,000.00

Labour charges for Brick works &

R.C.C. Works L Ft 200 75.00 15,000.00

Total Carreid to Summary 173,680.00

333,155.00

Estimate For Columns & Plinth Beams With 10 MM Tore Iron

Description Unit QtyRate Amount

Rs. Cts Rs. CtsA - Column & Plinth Beam10 MM Tore Iron for Column 13 Columns 42 420.00 17,640.00 10 MM Tore Iron for Plinth Beam 200 L Ft 48 420.00 20,160.00 10 MM tore Iron for Basses 33 420.00 13,860.00 6 MM Iron Rods for Stirrups Kg 85 145.00 12,325.00 Binding wire Kg 8 185.00 1,480.00 Cement Bags 50 950.00 47,500.00 Sand Cubes 2 9,000.00 18,000.00 3/4" Mattel Cubes 3 7,000.00 21,000.00 Labour Chrges for Columns 13 5,000.00 65,000.00 Labour Chrges for Plinth Beams L Ft 200 250.00 50,000.00

Total Carreid to Summary 266,965.00

Estimate For Columns & Plinth Beams With 12 MM Tore Iron

Description Unit QtyRate Amount

Rs. Cts Rs. CtsA - Column & Plinth Beam12 MM Tore Iron for Column 13 Columns 42 620.00 26,040.00 12 MM Tore Iron for Plinth Beam 200 L Ft 48 620.00 29,760.00 10 MM tore Iron for Basses 33 420.00 13,860.00 6 MM Iron Rods for Stirrups Kg 85 145.00 12,325.00 Binding wire Kg 8 185.00 1,480.00 Cement Bags 50 950.00 47,500.00

Page 4: Ablution Tank

Sand Cubes 2 9,000.00 18,000.00 3/4" Mattel Cubes 3 7,000.00 21,000.00 Labour Chrges for Columns 13 5,000.00 65,000.00 Labour Chrges for Plinth Beams L Ft 200 250.00 50,000.00

Total Carreid to Summary 284,965.00

Page 5: Ablution Tank

SUMMARYDescription Amount

A Column & Plinth Beam 148,210.00 B Wall 25,260.00 C Slab 180,680.00 D Plastering 36,680.00 E Ablution Tank 61,975.00 F Floor Concrete & Tiles 139,910.00

Total 592,715.00