abb power market experience
DESCRIPTION
Experience Delivering Similar Systems. ABB Power Market Experience. Power Markets. North America. Europe. Asia. Australasia. South America. Africa. Pool Scheduling Systems Major ISO Systems. ABB Power Markets: North America. (EMS). ABB Power Markets: North America. California ISO: - PowerPoint PPT PresentationTRANSCRIPT
Copyright © ABB 2006
ABB Power Market Experience
Experience
Delivering Similar Systems
Copyright © ABB 2006
North America
AfricaSouth America
Pool Scheduling Systems
Major ISO Systems
AsiaEurope
Power Markets
Australasia
Copyright © ABB 2006
ABB Power Markets: North America
(EMS)
Copyright © ABB 2006
California ISO:
Eight Years Operation
Ontario IESO:
Five Years
Operation
New York ISO:
Five years
Operation
ABB Power Markets: North America
Copyright © ABB 2006
Contract SignedMarch 1997
Systems ShippedSeptember 1997
Systems OnlineMarch 1998
Combined ABB Market System and EMS System
New real-time market went online October 1st 2004
Copyright © ABB 2006
Copyright © ABB 2006
Jan Apr Jul Oct Jan
19981997
Feb Mar May Jun Aug Sep Nov Dec
6+ Month Development
Extended Testing & VerificationExtended Testing & Verification
SA/SI/BBS Dry Runs BeginSA/SI/BBS Dry Runs Begin
PMS Dry Runs BeginPMS Dry Runs Begin
PMS Factory Acceptance TestPMS Factory Acceptance Test
SA/SI/BBS Contract SignedSA/SI/BBS Contract Signed
PMS Contract SignedPMS Contract Signed
7+ Month Development
1998
Feb Mar
ISO OperationalISO Operational
Apr
Copyright © ABB 2006
IESO Ontario (Canada) Power Market Design
• New EMS
• Look-ahead in R/T market
• PASA (
• Direct message exchange with generators
• New State Estimator
• Multi-Interval Optimization (2004)
• Enhanced real-time market online June 23rd 2004
Copyright © ABB 2006
Ontario (Canada) Power Market System
First operational in May 2001
Significant changes implemented:
• New EMS Replacement for old DAX system
• Look-ahead in R/T market
• PASA (predicted adequacy assessment)
• Direct message exchange with generators
• New State Estimator
• Multi-Interval Optimization (2004)
• Enhanced real-time market online June 23rd 2004
Copyright © ABB 2006
Partnership Master Agreement Signed August 1995
Systems Deliveries commenced in 1996
NYPP Converted to NY ISO in November 1999
Significant changes implemented: SCUC, look-ahead AGC, 5-min Real Time Market
Major market redesign project started in 2003
New SMD Market in live operation since January 2005
Copyright © ABB 2006
NYSIO Market Design
Very close to FERC SMD:
• Signed August 1995• Systems Deliveries • commenced in 1996• NYPP Converted to NY ISO in November 1999• Significant changes implemented: SCUC, look-ahead AGC, • 5-min Real Time Market• Major market redesign project started in 2003
• New SMD Market in live operation since January 2005
Copyright © ABB 2006
Transmissionconstraint
Market regionin which pricescorrelate
Nordic/Baltic
Mittel
Iberia
FRANCE
NorthwestEurope
RUSSIA
FINLAND
AUSTRIA
ITALYSPAIN
SWEDEN
NORWAY
GERMANY
HUNGARY
ROMANIA
BULGARIA
TURKEY
DENMARK
POLAND
BELARUS
UKRAINE
UK
CZECH REP.
SLOVAKIA
GREECE
BELGIUM
IRELAND
SERBIA
ALBANIA
MOLDOVA
LITHUANIA
LATVIA
ESTONIA
LUX.
MONTENEGRO
BOSNIA
CROATIA
SLOVENIASwitz
MACEDONIA
Britannica
Stattnet:
NordPool Market
Endesa:
OMEL (Spanish) Market
RWEnet:
RWEnet (German) Market
TERNA:
Italian Market
National Grid:
Original UK Market
ABB in European Power Markets
Copyright © ABB 2006
UK GM Pool
ABB Scheduling Scheduling
Software
Scheduling
SETTLEMENT UNCONSTRAINED
RUNS
CONSTRAINED RUNS
Generator Data
Load Data
Regional Electricity
Company Data
Constraint Data
Energy Settlements Info. Services
POWER SYSTEM PRODUCTION
NGC System Scheduling
Pool Commercial Operation
Generators & RECS
Plant Availability
Assessment
Transmission Network Studies
Scheduling & Dispatch
System Development
Asset Management
Inp
ut
Pro
c.
Ou
tpu
t P
roc.
Settlement
Ou
tpu
t P
roc.
Inp
ut
Pro
c
ABB Scheduling
Software
First site in world to use “SCUC”, developed by ABB in 1998
Copyright © ABB 2006
ABB and Asian Power Markets
Copyright © ABB 2006
시스템구성 : 계층구조
The KPX MOS Project Contract signed
January 2002
Systems delivered August 2002
Site testing finished October 2003
Market Dry Run complete 2003
Acceptance Certificate Issued 2003
Live Market will commence this year
Copyright © ABB 2006
시스템구성 : 계층구조
The KPX Market Design
Korean Market Design:
Contract signed
January 2002
Systems delivered August 2002
Site testing finished October 2003
Market Dry Run complete 2003
Acceptance Certificate Issued 2003
Live Market will commence this year
Copyright © ABB 2006
KPX MOS Deliverables
Primary MOS Backup MOS Interface to 3rd Party EMS PSSA /market training system Development system
“Technology Transfer” to local partner KDN
Acceptance Certificate issued by KPX 2003 Now under maintenance contract
Copyright © ABB 2006
North America
AfricaSouth America
Pool Scheduling Systems
Major ISO Systems
AsiaEurope
Power Markets
Australia
East China
Copyright © ABB 2006
East China Grid Company
Contract Signing March 2003
Copyright © ABB 2006
East China Grid Company
Contract Signed: March 2003
Integrated ABB EMS/MOS
Phase 1 Market Opening Ceremony May 2004
Simulated Day-Ahead Market in Operation
System Take Over Certificate March 2006
Total System Size 2006: 100,000 MW peak load
Copyright © ABB 2006
North America
AfricaSouth America
Pool Scheduling Systems
Major ISO Systems
AsiaEurope
Power Markets
Australia
Philippines
Copyright © ABB 2006
PHILIPPINES Wholesale Electricity Spot Market
Contract Signing February 2004
Copyright © ABB 2006
PHILIPPINES
Contract signed February 2004
Dev system delivered April 2004
FAT completed November 2004
SAT completed Manila 02/05
1-yr Market Readiness Trials
Market in Live Operation since
June 2006
First full-scale multi-commodity
power market in Asia
Copyright © ABB 2006
PHILIPPINESMarket Design:
Hourly market with nodal pricing for generation and zonal pricing for consumption
Week-Ahead, Day-Ahead, and Real-Time markets for energy and ancillary services
Financial transmission rights Web-based infrastructure for bid/offer
submission by market participants Prudential risk analysis Direct interface with EMS for exchange of
market and grid data Advanced applications to perform
dispatch and compute resulting MCPs Meter data aggregation, settlements and
invoice generation Direct EFT interfaces with local banks, full
accounting functionality for WESM
Copyright © ABB 2006
PHILIPPINES
Systems Characteristics:
Primary System
Market Interface, Market Applications, Settlements, FTs, FTRs, Metering system (all ABB)
Backup Site Interface to existing GE EMS
Market simulation system Development system
Copyright © ABB 2006
PHILIPPINES Wholesale Electricity Spot Market
Market Go-Live June 23rd 2006
Copyright © ABB 2006
North America
AfricaSouth America
Pool Scheduling Systems
Major ISO Systems
AsiaEurope
Power Markets
Australia
Western Australia
Copyright © ABB 2006
Western Australia Wholesale Electricity Market
Copyright © ABB 2006
Western Australia: Market Design
Web-based infrastructure for bid/offer submission by market participants
Prudential risk analysis Direct interface with the
System Manager (EMS) for exchange of market and electric network data
Advanced applications to perform the dispatch and compute the resulting MCPs
Meter data aggregation and settlements and invoices creation
Direct interfaces with local banks for EFT through AUSTRACLEAR
Copyright © ABB 2006
Western Australia Wholesale Electricity Market
Contract Signing August 2005
Copyright © ABB 2006
Western Australia Wholesale Electricity Market
Contract signed August 2005
Market Interface, Market Applications, Settlements
FAT December 2005 Shipped in 5 months SATJan-March 2006 Market Trials
Complete August 2006 Market Live Operation
September 2006 Live 13 months AOC
Copyright © ABB 2006
North America
AfricaSouth America
Pool Scheduling Systems
Major ISO Systems
AsiaEurope
Power Markets
Australia
Ireland
2007
Copyright © ABB 2006Contract Signing April 2006
Ireland Single Electricity Market
Copyright © ABB 2006
Ireland SEM Market Design
Single Electricity Market for whole Island – two countries, two currencies
Dual, interconnected computer systems in Dublin and Belfast to support internet power trading, financial settlements, energy dispatch and grid security
Will be Etc
Copyright © ABB 2006
Ireland Single Electricity Market
Contract award to ABB April 2006 Prime Contract for all hardware and
software infrastructure Systems development in Santa Clara
May – November 2006 FAT in Santa Clara December 2006 Systems will ship to Dublin and
Belfast in February 2006 Five month site testing and market
trials Market will open July 2007 Will be the most advanced electricity
market system in Europe
Copyright © ABB 2006
Texas Nodal Market Operations
Next Project:
ABB has been selected by ERCOT to replace the Areva Market Systems in the new $200m Texas Nodal (LMP) Market
Project is just starting
Copyright © ABB 2006
Texas Nodal Market Operations
Market Design:
Congestion Revenue Rights (PTP Options, Obligations, Flowgates) Day-Ahead Energy and Ancillary Services Co-optimized Market Daily Reliability Unit Commitment (DRUC) Hourly Reliability Unit Commitment (HRUC) Security Constrained Economic Dispatch every 5 minutes 15 minute settlement Resource-Specific Offers, Congestion management resource-
specific Actual Shift Factors for Resources Nodal Locational Marginal Prices (LMP) for Generation Zonal weighted LMPs for Loads
Copyright © ABB 2006
Robb PikeSupervisor, SMD2
New York ISO3890 Carman Road
Schenectady, NY 12303
518-356-6156
Cao Mao ShengProject Manager
State Power East China
201 Nanjing Road East
Shanghai, China
021-6329-0000-2473
Greg FordVP, Market
OperationsCalifornia ISO
151 Blue Ravine Rd
Folsom California
916-351-2344
Bill LimbrickCIO
Ontario IESOStation A, Box
4474Toronto
ON M5W 4E5Canada
905-403-6923
Kim Ib-KyungGeneral Manager
IT DepartmentKorea Power
Exchange167 Samsung-
DongSeoul Korea
82-2-3456-6590
Lasse HolopainenVice President
Market OperationsPhilippines WESM9th Flr Robinsons
TowerADB Ave, Ortigas
Center Pasig City
Philippines
632-631-8734
ABB Market Operations References
Jonathan O’SullivanProject Director
ESB National GridAll Ireland Electricity
Market27 Lower Fitzwilliam
StreetDublin 2, Ireland
353-676-5831
Ms. Dora GuzelevaManager, MarketAdministration
Western Australia IMO
Level 22, 221, St George’s
TerracePerth, WA – 6000
61-8-9420-5617