A World Bank Group solution to rapidly expand private investment

in utility-scale solar PV

Rome – Italy October 28, 2016

Stratos Tavoulareas Senior Energy Advisor

Page 2: A World Bank Group solution to rapidly expand private investment in

2 2

Solar power generation has reached a tipping point

The economics of utility-scale solar PV power have reached a tipping point…

…and many IFC markets benefit from some of the best irradiation levels on

the planet Price of crystalline silicon PV cells, $/W

84

60

36

30

24

6

3

120

84

60

60

30

9

6

0 50 100 150

Geothermal

Large hydropower

Small hydropower

Large thermal

Thermal <100MW

Wind

Solar High

Solar power can be built in 3-6 months vs. 3-10 years for thermal, hydro &

geothermal…

….and many countries need to diversify away from a dependency on HFO and

fossil fuels Typical construction periods (months) Evolution of oil, gas and coal prices since 2004

Page 3: A World Bank Group solution to rapidly expand private investment in

3 3

But investment in solar PV is slow…

Lack of market scale

Lack of competition

High transaction costs

High perceived risk and cost of capital

Limited institutional capacity

Page 4: A World Bank Group solution to rapidly expand private investment in

4 4

Renewables Auctions Becoming Widespread Select Renewable Energy Policies Globally

Source: REN21, BMI

Page 5: A World Bank Group solution to rapidly expand private investment in

5 5

Scale, standardization & competition are needed

Case Study: Dramatic tariff reductions have been achieved in South Africa

Capacity allocated per round (MW) Number of received bids and success rate (includes wind)

Tariffs per round (ZAR/kWh)

Large, repeat allocation

Capacity build-up

Strong competition

Tariff decrease

Inclusive Framework

Proven bankable

Program expansion

High investor interest

+1,900 MW of solar PV power

Tariff drop of -76% for PV projects over the 4 rounds

Surge in investor interest and increasing selectivity in bidders afforded

0

500

1000

1500

2000

PV

Round 4

Round 3

Round 2

Round 1

0

0,5

1

1,5

2

2,5

3

3,5

Round 1 Round 2 Round 3 Round 4

53%

24% 18% 17%

0%

10%

20%

30%

40%

50%

60%

0

20

40

60

80

100

Round 1 Round 2 Round 3 Round 4

# of bids received Success rate

Page 6: A World Bank Group solution to rapidly expand private investment in

6 6

The WBG solution: A “One-Stop-Shop” offering

Scaling Solar is a “one-stop-shop” for Governments to rapidly mobilize competitive privately funded grid

connected solar projects within 2 years of engaging our team.

Scaling Solar brings together several World Bank Group services under a single engagement:

Advice to assess the right size and location for power plants in grid.

Simple and rapid tendering to ensure strong competition from committed industry players.

Standardized, balanced project documents to eliminate drafting and negotiation delays.

Competitive financing and insurance attached to tender and available to all bidders.

Risk management and credit enhancement products to lower financing costs and deliver lower tariffs.

Scaling Solar’s comprehensive package delivers speed and certainty and addresses barriers at every stage of the development

life cycle to deliver solar power at record speed and at the lowest possible prices.

As it is implemented across multiple countries, Scaling Solar will also deliver market scale, allowing smaller countries to enjoy

the purchasing power of bigger and more developed economies.

Page 7: A World Bank Group solution to rapidly expand private investment in

7 7

How will it work? Scaling Solar’s 5 steps

• Several WBG instruments brought together under a single product offering

• Client governments would engage in a single mandate to access the “one-stop-shop”

Project Preparation

Tender Process &

Award

Construction

& Operation

Bid Preparation

1 2 3

Financial Close

4 5

• Technical and economic analysis for optimal size and location of PV plants

• Site investigation

• Legal & regulatory analysis

• Template tender documents

• Template project documents

• Attachment of stapled financing, insurance and credit enhancement

• Request for qualification

• Bidder consultation

• Request for proposals

• Proposal review and award

• Signing of project documents

• Finalization of equipment, construction and operation contracts

• Final project approvals

• Finalization of loan agreements, insurance and risk management

• Construction

• Commissioning

• Operation

8 months 6 months 10

months

Page 8: A World Bank Group solution to rapidly expand private investment in

8 8

What’s new about this?

Delivery Speed & Efficiency

Optimization & Risk Mgmt

Economies of Scale

Templates (RFQ, RFP, PPA, GSA) support rapid & low cost tender preparation

Balanced docs and stapled financing avoid negotiation

Site selection & development minimize uncertainty and optimize for grid

Stapled PRI and off-taker credit enhancement lower risks & so tariffs

Standardization across multiple countries creates large regional market

Delivers benefits of economies of scale

1 2 3

Page 9: A World Bank Group solution to rapidly expand private investment in

Government Support Agreement (GSA)

• Scaling Solar designed for countries without IPP track records, so Government support is critical to

attract investment

• Many Governments dislike overarching sovereign guarantees … so Scaling Solar does not require one

• Primary credit enhancement is an escrow account / LC maintained by the utility – Government’s

financial obligation is limited to a buy-out obligation in the event of repeated non-payment and

exhaustion of escrow / LC

• Other areas of Government support:

o General commitment to the project

o Permits

o Direct Agreement and Legal Opinion

o Non-discrimination and protection from harassment

o Bank accounts and transferability, convertibility, and availability of currency

•9

Page 10: A World Bank Group solution to rapidly expand private investment in

Not all countries are suitable for Scaling Solar

Key characteristics of suitable countries:

Solar should be justifiable considering competing options

Government interested to scale up solar quickly

Alternatives (negotiated deals or FiT) have not worked

Power market: regulated with limited/no IPPs and single buyer

Weak off-taker

Grid able to absorb at least 30 MW; multiple sites OK

Page 11: A World Bank Group solution to rapidly expand private investment in

Looking forward

Zambia: winning bidders selected for Round 1 (100 MW); Round 2

(200 MW) starting

Next:

Senegal, Madagascar and Ethiopia;

West Bank scoping study;

Afghanistan early discussions

South East Asia

Exploring opportunities in Eastern Europe & Central Asia

Page 12: A World Bank Group solution to rapidly expand private investment in

12 12

Scaling Solar tender results in Zambia

6.0c/kWh non-indexed is equivalent to an average in

current dollars over contract life of 4.7c/kWh

Projects were developed and tender was prepared and executed to conclusion in 9 months

West lunga Site

Mosi-oa Tunya

Site

Neoen / First Solar 6.0150 6.1350

ENEL Green Power 7.7989 7.8390

Access / EREN Zambia 1 8.2879 8.9509

MULILO Zambia PV1

Consortium 8.4000 8.4000

EDF Energies Nouvelles 10.0400 9.9850

SEP / AVIC Intl 10.6000 10.6000

Page 13: A World Bank Group solution to rapidly expand private investment in

13 13

Scaling Solar in Zambia relative to regional benchmarks

Page 14: A World Bank Group solution to rapidly expand private investment in

14 14

Developers that have participated in Scaling Solar tenders

[1] A politically exposed person is defined as an individual who is or has in the past been entrusted with prominent public or political functions, including heads of state or government, senior government, judicial, military, or political party officials, and senior executives of state or sub-national owned enterprises.

Page 15: A World Bank Group solution to rapidly expand private investment in

15 15

What are the benefits?

1. For Governments:

2. For Project Developers:

3. For Donors*:

Reach Leverage Transparency Impact

Market creation Reduced development

time Level playing field Regional scale

Speed Reduced cost Certainty Competitive fixed-rate

tariffs

* Opportunities for donors include: funding transaction advisory (steps 1-3) or provision of capital grants to all bidders to lower tariffs and improve affordability