a short baseline neutrino facility (sblnf) in the cern north area: design overview

33
A SHORT BASELINE NEUTRINO FACILITY (SBLNF) IN THE CERN NORTH AREA: DESIGN OVERVIEW M. Calviani , I. Efthymiopoulos, A. Ferrari, B. Goddard, R. Losito, J. Osborne, P. Sala, L. Scibile, R. Steerenberg, H. Vincke 8 th INTERNATIONAL WORKSHOP ON NEUTRINO BEAMS & INSTRUMENTATION NBI2012 – 6 th /10 th November 2012

Upload: magnar

Post on 15-Feb-2016

21 views

Category:

Documents


0 download

DESCRIPTION

8 th INTERNATIONAL WORKSHOP ON NEUTRINO BEAMS & INSTRUMENTATION NBI2012 – 6 th /10 th November 2012. A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

A SHORT BASELINE NEUTRINO FACILITY (SBLNF) IN THE CERN NORTH AREA: DESIGN OVERVIEWM. Calviani, I. Efthymiopoulos, A. Ferrari, B. Goddard, R. Losito, J. Osborne, P. Sala, L. Scibile, R. Steerenberg, H. Vincke

8th INTERNATIONAL WORKSHOP ON NEUTRINO BEAMS &

INSTRUMENTATIONNBI2012 – 6th/10th November 2012

Page 2: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

2

Outline

7th November 2012 (NBI2012)

Introduction to the Short Baseline Neutrino Facility Study Group

Experimental requirements Preliminary parameters of the

installation Proto-layout of the installation Neutrino production area configuration Open points and challenges Conclusions

Page 3: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

3

7th November 2012 (NBI2012)

Introduction to the Short Baseline Neutrino Facility Study Group

Experimental requirements Preliminary parameters of the

installation Proto-layout of the installation Neutrino production area configuration Open points and challenges Conclusions

Page 4: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

4

SBLNF study group

7th November 2012 (NBI2012)

A SBLNF study group has been convened to address the feasibility of a short baseline neutrino facility in the CERN North Area

This should serve primarily the ICARUS/NESSiE experiment (C. Rubbia et al., SPSC-P-347) as well as a neutrino test area for detector R&D and neutrino cross-section measurement

Why not use CNGS? Target area very deep (~60m), too costly to install new

detectors underground DP configuration not adapted for a low energy neutrino

beam

Page 5: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

5

7th November 2012 (NBI2012)

Introduction to the Short Baseline Neutrino Facility Study Group

Experimental requirements Preliminary parameters of the

installation Proto-layout of the installation Neutrino production area configuration Open points and challenges Conclusions

Page 6: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

6

Experimental requirements

Sterile neutrino physics (C. Rubbia et al., SPSC-P-347): Exploring the possible existence of one or more sterile

neutrino Search for spectral differences of electron-like specific

signatures in two identical detectors at two different neutrino decay distances

7th November 2012 (NBI2012)

nm+anti-nm

ne+anti-ne

An exact proportionality between two ne spectra implies absence of neutrino oscillations

1600 m: ICARUS T600 detector + magnetic spectrometer (NESSiE)

350 m: new 150 LAr-TPC detector + magnetic spectrometer (NESSiE)

Page 7: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

7

7th November 2012 (NBI2012)

Introduction to the Short Baseline Neutrino Facility Study Group

Experimental requirements Preliminary parameters of the

installation Proto-layout of the installation Neutrino production area configuration Open points and challenges Conclusions

Page 8: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

8

Preliminary parameters of the installation

7th November 2012 (NBI2012)

100 GeV/c beam momentum Neutrino spectrum peaked at ~2 GeV ND at 350 meters, FD at 1600 meters, middle

position detector at ~700 meters from target DP: length ~80-120 m, radius 100/200 cm

DV of 100 meters is the experiment minimum requirement

Hadron absorber: Graphite core, 2-3 meters long, 1x1 m2 surface Segmented Fe blocks (10/18 meters in total)

Beam line at around 10/15 meters from “ground”

Page 9: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

9

CERN accelerator complex

7th November 2012 (NBI2012)

SBLN

F

Page 10: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

10

Primary beam configuration

7th November 2012 (NBI2012)

100 GeV/c baseline primary beam momentum 3.5*1013 p/pulse (4.5*1013 p/pulse ultimate

running) 6s (3.6s min) repetition rate ~100 kW (200 kW) beam power Time sharing between fixed-target physics

Yearly POTs between ~3-4.5*1019 p+/yr New extraction lines from existing tunnels Beam 1s on target: 1-2.5 mm, divergence ≤1

mrad

Page 11: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

11

Beam extraction from SPS

7th November 2012 (NBI2012)

Magnetic septa

(MST+MSE)

Short baseline neutrino beam

Beam excitation via injection kicker in LSS1 + extraction via existing septa

Solution tested for low intensities during recent beam tests

B. Goddard

Fast extraction not available in the SPS North Area branch (complex to install a new kicker in a short time)

Injection kicker (MKP)

slow

Page 12: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

12

7th November 2012 (NBI2012)

Introduction to the Short Baseline Neutrino Facility Study Group

Experimental requirements Preliminary parameters of the

installation Proto-layout of the installation Neutrino production area configuration Open points and challenges Conclusions

Page 13: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

13

7th November 2012 (NBI2012)

Beam line ~parallel to the existing North Area lines

New production infrastructure

Experiments and neutrino beam test areas

Target area

Near detector~350 meters

Testing area for new generation detectors

Far detector~1.6 km

Page 14: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

14

Muon fluence and constraints

7th November 2012 (NBI2012)

Decay pipe

Hadr

on st

oppe

r

Moraine soil

Proton momentum

Muon range (from target)

100 GeV/c ~320 meters

110 GeV/c ~340 meters

120 GeV/c ~360 meters

Assumptions: 4.5*1013 p/pulse 1.9 g/cm3 moraine density DP 100 m long HS: 3 m core + 7 m Fe

ND should be at least at 350 meter from target!

Page 15: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

15

7th November 2012 (NBI2012)

Introduction to the Short Baseline Neutrino Facility Study Group

Experimental requirements Preliminary parameters of the

installation Proto-layout of the installation Neutrino production area configuration Open points and challenges Conclusions

Page 16: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

16

Neutrino beam production area configuration

7th November 2012 (NBI2012)

The baseline configuration of the target area inspired by both AP0/NuMI “chase” and T2K: No direct personnel access close to production

elements Reduced number of equipment in hot zones Remote maintenance on all equipment Reduced air volume around the production elements Allow for target volume and decay pipe under He

environment (TS and DP separated in case of access) Shallow depth calls for heavy shielding around target

trench and decay pipe

Page 17: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

17

(Proto) layout of the installation (FLUKA)

7th November 2012 (NBI2012)

Ground (moraine)

Decay pipeDecay pipe shielding

Hadron stopperTarget station building and

vault

Primary beam area

Target chase

Target shielding

FLUKA preliminary implementation:Shielding thickness not optimized!

Page 18: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

18

(Proto) layout of the installation (FLUKA)

7th November 2012 (NBI2012)

Ground (moraine)

Target chase

He vessel (medium blue)

Concrete shielding (red)

Iron shielding (dark blue)

Target station building and vault

Target & horn/reflector

300

cm20

0 cm

300 cm

Page 19: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

19

Absorber/m stations

7th November 2012 (NBI2012)

Hadron absorber: Effective iron length of 10/18

meters Water cooling system (surface)

Muon pits (i.e., diamond-detectors): Pit 1 inside the dump to be sensitive

to low energy m (~5 GeV) Pit 2 downstream the absorber Access via a dedicated surface building

Page 20: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

20

Potential target configuration

7th November 2012 (NBI2012)

CNGS target design Cooling by radiative

emission and partly by convective exchange

Graphite at high temperature (~1000 °C)

Revolver structure would have allowed to exchange remotely target without interventions

Page 21: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

21

Potential target configuration

7th November 2012 (NBI2012)

SBLNF: CNGS-like “evolutionary” design graphite/beryllium options under investigation Simpler construction and more diagnostics Complete remote manipulation Possibility to have a closed He-loop cooling

(enhanced convection) – external air blow could be avoided Pressurized circuit with an external heat exchanger

No segmentation required by physics Larger rod and beam radius (~4-10 mm radius)

Reduced off-axis vibration issues Enhanced production of low energy p/K PRELIMINARY

DESIGN ON-

GOING

Page 22: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

22

Potential target configuration

7th November 2012 (NBI2012)

Advantages DisadvantagesTarget inside horn

Higher pion collection from target

More difficult maintenance and construction

Less degree of freedom for target design

Electrical coupling between target/horn

Target outside horn

Easier maintenance and installation

More degree of freedom for a more robust design

Less efficient in pion collection

For both solution the baseline is to have a passive or actively He-cooled target

PROS & CONS

TO BE STUDIED

IN DETAIL

Page 23: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

23

7th November 2012 (NBI2012)

Introduction to the Short Baseline Neutrino Facility Study Group

Experimental requirements Preliminary parameters of the

installation Proto-layout of the installation Neutrino production area configuration Open points and challenges Conclusions

Page 24: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

24

Preliminary radioprotection aspects

7th November 2012 (NBI2012)

Optimisation: annual dose <100 mSv for exposed personnel (<10 mSv for general public)

CERN dose limits: 6 mSv/y or 20 mSv/y (for radiation workers), 1 mSv for other

personnel working at CERN and 0.3 mSv/y for general public

Detailed studies to follow: Required shielding (thickness, material choice) Induced radioactivity (structure, surroundings, soil, groundwater) Optimization of design to minimize intervention doses for

maintenance personnel Waste & decommissioning

Page 25: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

25

Preliminary radioprotection aspects

7th November 2012 (NBI2012)

H*(10) with the current shielding: In the target vault <10 mSv/h Above DP, At 15 m from beam axis

< 1 mSv/h Values manageable with a proper

shielding design

PRELIMINARY

Page 26: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

26

Challenges in the design

7th November 2012 (NBI2012)

He vessel for TS/DP: Material/thickness? He at atmospheric pressure? Closed loop with recirculation? Purge system? Constraints in He purity for a C/Be target? Which shielding elements should be included in the

vessel? Separate volume via appropriate shutter (closed

during access) to avoid purging the DP volume

Several technical questions concerning the engineering of the installation are still open

Page 27: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

27

Challenges in the design

7th November 2012 (NBI2012)

Target: In case of a He-cooled target, shall we keep the target

and He-vessel circuits separated? How critical is the purity in the He-loop?

Shielding: Inner iron layer water/air cooled (~50 kW deposited)? Decay pipe inner layer shall be water cooled (T2K-like?)

Soil/water activation minimization: Groundwater mobility for surface layers? Careful design of the interface between activation zone

and surrounding earth Radioactive gas emission in the TS

Page 28: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

28

7th November 2012 (NBI2012)

Introduction to the Short Baseline Neutrino Facility Study Group

Experimental requirements Preliminary parameters of the

installation Proto-layout of the installation Neutrino production area configuration Open points and challenges Conclusions

Page 29: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

29

Conclusions

7th November 2012 (NBI2012)

A study group has started addressing the technical feasibility of a short baseline neutrino facility in the CERN North Area

It would be a 100 GeV/c p+ beam, ~200 kW installation, at shallow depth (10/15 m)

Neutrino production area to be a “chase”-based design

Significant design efforts to be dedicated in 2013 to have it operational in the next few years

Design experience from NBI colleagues will be precious, considering feedback from running

installations (T2K/NuMI/NoVA)

Page 30: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

30

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

Backup

7th November 2012 (NBI2012)

Page 31: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

31

(Proto) layout of the installation

7th November 2012 (NBI2012)

Main target vault, housing: Target/horn/reflector

trench Radioactive storage

area A temporary shielded

area - fast inspection and “easy” repair

Annex service building: general services and

assembly

Page 32: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

32

Open points: TS energy deposition

Target: ~1.5 kW “Chase” iron shielding:

~50 kW deposited power

Air/He cooling necessary?

DP shielding: ~68 kW on the first 50

cm layer thermal cracking?

Mitigation strategy to be further investigated

Region kJ/pulse kW (average)Target 5.62 1.56Top Fe shielding (layer 1) 48.32 13.42Lateral Fe shielding 57.50 15.97Bottom Fe shielding 55.42 15.39Decay pipe shielding (total) 258.56 71.82Hadron stopper (graphite) 159.54 44.32Hadron stopper (iron) 123.70 34.36Horn (total) 7.01 1.95Reflector (total) 5.05 1.40

7th November 2012 (NBI2012)

Page 33: A Short Baseline Neutrino facility (SBLNF) in the CERN NORTH AREA: Design overview

M. Calviani et al., Short Baseline neutrino facility (SBLNF) design overview

33

Layout considerations

7th November 2012 (NBI2012)

The position of the target is constrained by: Existing buildings Bending radius of

the extraction line The near detector

distance from target and existing buildings