A Case study from Denmark
Danish Signalling Programme
Bent Ahlgren, Banedanmark and Anders Møller, Rambøll
![Page 2: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/2.jpg)
Agenda
1. The basis for the Danish Signalling Programme
2. Procurement Phase
3. Way ahead
4. Benefits
o Punctuality
o Safety
o Improved operational procedures
o Capacity
![Page 3: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/3.jpg)
Background of the Signalling Programme
![Page 4: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/4.jpg)
Danish signalling needsto be renewed now
Banedanmark is the owner of DK railway infrastructure:• Replacement• Maintenance• Operation
60% of all signalling will exceed absolute final service-life within 15 years
Life of DK- ATC expires in 2020
It takes 10-12 years to renew all signalling assets.
More systems have risk of serious breakdowns even today.
50% of today's train delays are due to signalling failures.
4
![Page 5: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/5.jpg)
A total renewal of the signalling system minimize total cost and provide better performance
A total renewal is the best solution:
• Cheapest and fastest implementation• Provides higher punctuality and capacity• Most benefits for the passengers• Benefits are achieved faster
2006: Strategic political decision of a total renewal strategy
2007-08: Detailed plans & budget for a total renewal programme
Jan 2009:Final political decision for a fully financed total renewal programme was decided by the Danish Parliament
Feb 2009-12: Signalling Programme procurement phase
5
![Page 6: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/6.jpg)
Two different systems
Conventional network (Fjernbanen):
ERTMS 2 and modern centralized signalling infrastructure and onboard
S-banen:
Modern metro/urban system. CBTC
More interfacing projects: Fixed transmission network, STM, GSM-R etc
New operational rules
No Fall Back System
6
![Page 7: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/7.jpg)
The logic in total renewal
7
Better prices
• Economies of scale
• International competition
• Learning curve effect
Quantum leap in technology
• EC standard component, redundancy of central components, higher availability
• Few safety approvals
• Few interfaces
Savings on operations and uniform safety
• Reduction in maintenance costs
• Simpler and safer operational rules
• Fewer Traffic Management sites and reduction in staff
![Page 8: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/8.jpg)
Procurement Phase
![Page 9: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/9.jpg)
Contract strategy
Design Build Maintain contracts
• 2 Contracts on main & regional lines (East and West)
• 1 Supplier 2 contracts on the S-bane including all rolling stock
• 1 Contract for on-board main & regional rolling stock
• GSM-R data included in GSM-R tender starting now
Framework type contracts that allow fitting of new lines
Possible option for ERTMS regional
9
East contract
West contract
TMS Coordination by suppliers
Rolling stock contract
All supply & implementation from track to TMS
![Page 10: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/10.jpg)
Status
• S-bane - 5 bids received
• Contract awarded to Siemens
• Within target budget, time frame 2020 > 2018
• Main Line (Fjernbanen) – 6 bids received
• 2 Contracts awarded to Alstom (East) & Thales-Balfour Beatty Rail (West)
• Within target budget
• On-Board – 5 bids received
• Contract awarded to Alstom
• Within target budget
10
![Page 11: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/11.jpg)
Approach
• Early dialog with suppliers
• Marked research, purchase what the market is able to supply
• Minimum development risk approach. Only calculated and limited
development risks
• Functional requirements: let the Supplier supply existing systems
• New operational rules: remove national monopoly barriers
• Dedicated organisation and international team
• Negotiated procedure
• Close involvement of our owners
• Start collaboration approach
11
What we did to achieve this
![Page 12: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/12.jpg)
Strategy: Benefit perspective
But total replacement gives more benefits than traditional replacement
• Enhanced punctuality
• Enhanced Capacity on selected lines
• Uniform safety level in whole country
• Optimizing maintenance
• Optimizing the train control organisation
• Optimising advanced train control
• Enhanced passenger information
• Driver for a transformation of Banedanmark
12
Re-signalling naturally gives limited benefits compared to cost amount
![Page 13: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/13.jpg)
Roll out strategies: cost perspective
Focus on cost drivers:
• TRUE COMPETITION. Buy what the industry has on the shelves. New Ops.
Rules, etc
• High numbers of units = cheaper unit price,
• Same supplier: same solution, same interfaces, very few approvals
• ”Factory production” installation (installation 25% of the cost)
• Less track mounted equipment = installation outside possession hours.
• Achieving learning curve effect
• Optimizing possessions.
• Collaboration Programme management: cost of disputes
• Discuss safety level from a ”total perspective”
• Choose cost consentive solutions: GPRS rather than ERTMS 1 on stations,
no back-up, no shunting, development of a ”suitcase solution”
13
As there is no real standard, SP opted for Economy of scale
![Page 14: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/14.jpg)
Way ahead
![Page 15: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/15.jpg)
Roll-out until 2021
15
Starting 2009, it will take 10-12 years to carry out the total renewal
Two contracts for the conventional network
One framework contract for on-board equipment
Contract interface at Lillebælt
Roll-out phases:
•Early deployment
•Main lines
•Regional lines
•Low density lines
![Page 16: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/16.jpg)
The S-bane
One contract
Technology: Suppliers well proven “metro” type system e.g. CBTC
Early deployment line:Jægersborg - Hillerød
Roll-out starting from end branches towards centre of Copenhagen
Last, the central lines: Risk-minimising approach
![Page 17: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/17.jpg)
What does it mean for Banedanmark and the employees ?
17
Reorganisation during the next 12 years with impact on:
–All traffic management staff in Banedanmark
–All signalling technicians
–Train drivers with the train operation companies
Changes include:
–New operational rules
–New workplace systems
–New places of work geographically
–and more…
![Page 18: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/18.jpg)
The expected benefits
o Punctuality
o Safety
The Signalling Programme
o Improved operational procedures
o Capacity
![Page 19: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/19.jpg)
Punctuality
80 % reduction in delays caused by signalling
Reduction in delays caused by signalling
![Page 20: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/20.jpg)
Safety
Uniform level of safety country wide
![Page 21: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/21.jpg)
Improved operational procedures
Railway Undertakings, Privat Lines, Infrastructure Managers: 4.700
Banedanmark (excl. BDK Produktion): 450
Contractors (incl. BDK Produktion): 1.000
TOTAL 6.150
Time needed to meet training requirements
![Page 22: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/22.jpg)
Capacity
Double up in 2020
![Page 23: A Case study from Denmark - irse.org 30032012... · A Case study from Denmark Danish Signalling Programme Bent Ahlgren, Banedanmark and Anders Møller, Rambøll. ... • GSM-R data](https://reader035.vdocuments.mx/reader035/viewer/2022081515/5af2d6f47f8b9a154c8c0a2e/html5/thumbnails/23.jpg)