BIM Camp, Zürich_27.10.2017 A BIM STORY Philipp Seer Head of BIM / Burckhardt+Partner AG José Alves BIM Coordinator / Burckhardt+Partner AG Lauren Eller Associate Project Manager / Burckhardt+Partner AG Andreas Wecker BIM Management / Losinger Marazzi Thibaut Lecoutere BIM Site Coordinator / Losinger Marazzi

Upload: others

Post on 30-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

A BIM STORY

Philipp SeerHead of BIM / Burckhardt+Partner AG

José AlvesBIM Coordinator / Burckhardt+Partner AG

Lauren EllerAssociate – Project Manager / Burckhardt+Partner AG

Andreas WeckerBIM Management / Losinger Marazzi

Thibaut LecoutereBIM Site Coordinator / Losinger Marazzi

Page 2: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

1st February 2017Start of BIM coordination with the execution team

ten 3D models

33 laboratories

33 offices

375 m2 technical equipment

355 windows

8,722 m of pipe

820 m2 per floor

1,322 electrical outlets

186 rooms

and more …

6th November 2016End of design phase with closure folder

Summer 2018Delivery of the building

7th November 2017Crane dismantling

February 2015LM & B+P won the tender and is awarded the work

3.7 m clear room height

1st March 2017First coordination meeting with Solibri

6th April 2017First 3D model on Site with Dalux

25th October 2015First signature of BIM Execution Plan

9th January 2017Mobilization of the work team

Beginning of 2014client CHUV launched a call for tender in total enterprise

October 2015Contract signature

December 2015First architectural coordination model

… based on the project CNP CERY

Page 3: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

Software and data formats used in the project

IFC format BCF format

Revit native format

and SMC format

Page 4: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Software and data formats used in the project

Consultants General contractor Providers

Structure

Mechanical

Plumbing

Electrical

Furniture

Precast Facade

CoordinationProject database

BIM2Field

Lite DMS

API

API

Architecture

Page 5: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Case study laboratory building

BIM Camp, Zürich_27.10.2017

Model usage and information flow during the different project phases

P

S

D

L

T

C

FProgram

Strategy

Development

Legal

Tendering

Construction

Future…

Page 6: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Building Information Model

BIM Camp, Zürich_27.10.2017

Requests of the client

P

S

D

L

T

C

FProgram

Strategy

Development

Legal

Tendering

Construction

Future…

Page 7: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

From the database into the 3D model

The client’s specifications for rooms

PBIM Camp, Zürich_27.10.2017

Page 8: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Digital room book

From the database into the 3D model

P

Room

Core

information

Room data

sheet

Items per

room

Item library

BIM Camp, Zürich_27.10.2017

Page 9: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

P

From the database into the 3D model

Centralization of the client’s specifications – database

BIM Camp, Zürich_27.10.2017

Page 10: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

Import of client’s data from dRofus into the 3D model

P

From the database into the 3D model

Page 11: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

Import of client data from dRofus into the 3D model

P

From the database into the 3D model

Page 12: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

Visualization of the clients requests on architectural changes

P

From the database into the 3D model

Page 13: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

The planning of the project evolves …

P… and needs the client’s approval

From the database into the 3D model

Page 14: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

Approved information gets synchronized back from the 3D model to the dRofus database

P

From the database into the 3D model

Page 15: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Building Information Model

BIM Camp, Zürich_27.10.2017

P

S

D

L

T

C

FProgram

Strategy

Development

Legal

Tendering

Construction

Future…

Page 16: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

S

BIM Process – Expectations & Goals

Page 17: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

ARCHITECT CIVIL ENG. MEP ENG. OTHER

GENERAL

CONTRACTOR

CLIENT

BIM Camp, Zürich_27.10.2017

Project Manager

BIM Manager

Project Manager

BIM

Referent

BIM

Referent

BIM

Referent

BIM

Referent

BIM Manager

BIM Coordinator

on site

S

BIM Process - Project Organisation & Roles

Page 18: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

S

BIM Goals

Building services equipment

Page 19: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

S

Guidelines

Contract Client Architect Engineer Contractor Subcontractor (…)

Shared Vision BIM Execution Plan – Shared objectives -

Details

Coordination

ScheduleModelised Item

Item

Configuration

3D Model

Organisation

Responsibility /

Management

3D Models

transfer

2D/3D

CoordinationModelling rulesBIM Glossary

Output

documents

Collaborative

Database

Detailed

validation

process

Quality Control

Rules

Request for

information

Page 20: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

BIM Camp, Zürich_27.10.2017

We model like we construct…

Walls

Floors

Partitions

New floors

Screeds and finishings

Rooms

S

Modeling rules

LODLOD

LOI

Page 21: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Building Information Model

BIM Camp, Zürich_27.10.2017

P

S

D

L

T

C

FProgram

Strategy

Development

Legal

Tendering

Construction

Future…

Page 22: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

D

Project development

Site / topography Site / topography

Existing buildingsNew building

Page 23: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

D

Project development

Page 24: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

D

Project development

Page 25: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

D

Project development

Page 26: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical
Page 27: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

D

Communication

Page 28: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Building Information Model

BIM Camp, Zürich_27.10.2017

P

S

D

L

T

C

FProgram

Strategy

Development

Legal

Tendering

Construction

Future…

Page 29: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

L

Permit documentation

Page 30: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Building Information Model

BIM Camp, Zürich_27.10.2017

P

S

D

L

T

C

FProgram

Strategy

Development

Legal

Tendering

Construction

Future…

Page 31: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Tendering

Page 32: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Tendering

Page 33: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Tendering

Page 34: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Tendering - Coordination

2 - Assignments

Who? What?

3 - Report

Coordination Meeting

4 - Clash processing

5 - Upload of new models

formats:IFC + NATIVE

1 - 3D models

Clash Detection

Coordination

Cycle

different 3D models

3D Coordination

Quantitytake-off

3D Coordination allows high-quality design

Page 35: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Coordination

Page 36: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Issue Management

old method:

- assignment in Revit

- using native models

T

Coordination

Page 37: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Coordination

current method:

- assignment in Solibri

- using IFC models

Issue Management

Page 38: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Coordination

Page 39: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Coordination

Clash resolving

Page 40: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Coordination

Clash resolving

Page 41: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Coordination

… with updated IFC and NATIVE models - a new coordination cycle can begin

End of the coordination cycle

Page 42: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

T

Coordination

Coordination increases accuracy of quantity extractions

Page 43: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Building Information Model

BIM Camp, Zürich_27.10.2017

P

S

D

L

T

C

FProgram

Strategy

Development

Legal

Tendering

Construction

Future…

Page 44: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

C

Construction

Page 45: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

C

Construction

Page 46: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

C

Construction

Page 47: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

C

Construction

Page 48: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

C

Construction

Page 49: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

Conclusion

BIM Camp, Zürich_27.10.2017

P

S

D

L

T

C

FProgram

Strategy

Development

Legal

Tendering

Construction

Future…

Input FM

Feedback

Use cases

TODAY

A BIM project from the beginning in all trades

Easy, quick & early handling of complex topics

New processes & software

Team spirit : Sharing skills & knowledge

Planning team & Construction crew make use of BIM

Page 50: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

F

Facility management

COO

REV

DATA BASE REVISED MODELS

Items Products

Technical Data Sheets

USERS

… INPUT …

Page 51: A BIM STORY · 2017-10-30 · BIM Camp, Zürich_27.10.2017 1st February 2017 Start of BIM coordination with the execution team ten 3D models 33 laboratories 33 offices 375 m2 technical

A STORY TO BE CONTINUED …