GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 1
GR-0880 91-9512 British Columbia Ministry of Environment. Power and Special Projects Division Power and Special Projects files 1949-1976 15 m of textual records Correspondence, feasibility studies, consultants reports, engineering studies, application hearings, submissions, progress reports, contract drawings and tender documents regarding hydro-electric projects, water licenses, flood control, petroleum refinery pollution, sewerage treatment plants, fisheries and wildlife, and environmental impact, 1949-1976. The collection largely contains materials relating to Arrow Lakes Dam, 1949, 1954-1969, the Jordan River redevelopment project, 1968-1972, the Babine Lake development (Fulton River dam), 1967-1970, the Columbia River Mica dam project, 1954-1970, the Duncan Lake storage development, 1971-1973, the Kootenay canal development, and the Portage Mountain development (Peace River W.A.C. Bennett dam), 1958-1967. It also includes hearings and submissions regarding the Iona Island sewage treatment plant, 1957-1959, records of Canada - B.C. Consultative Committee on the Okanagan basin agreement, 1970; B.C. Comptroller of Water Rights hearings regarding Nechako River, 1949, various B.C. Research Council reports, 1966-1973, and the International Joint Commission (U.S. and Canada) hearings, 1955. The following maps were removed fro their files by BC Archives staff and accesioend under number M856001.
Box File Registration no. Call no.
9 2 20080 CM/B
9 2 20081 CM/B
9 2 20082 CM/B
9 2 20083 CM/B
9 2 20084 CM/B
9 2 20085 CM/B
9 3 20077 CM/B
9 3 20078 CM/B
9 3 20079 CM/B
9 3 16515 CM/D
9 3 16516 CM/B
9 3 16517 CM/B
9 3 16518 Discarded
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 2
Box list (Boxes 1-88)
Box Contents Date
919512-0001 Hydro-electric projects, miscellaneous reports and correspondence
919512-0002 Tsitikia-Schoen Resource Study Hearings 1975
919512-0003 B.C. Hydro and Power Authority Reports, Mica, Arrow Lake, Duncan Lake Dams, 1965-1973; Recreation in Columbia River basin, 1961; Soil Convention Papers, 1964; Committee on International Hydro decade
1961, 1964-1973
919512-0004 Water License, Dam Applications, Hearings and Submissions 1949-1976
919512-0005 Fraser River 1957-1974
919512-0006 B.C. Research Council Reports 1966-1973
919512-0007 Okanagan Valley. Kettle Valley 1960, 1969-1970, 1975
919512-0008 Sewage Disposal, Iona Island 1957-1959
919512-0009 Wildlife and Fisheries 1965, 1969
919512-0010 Petroleum Refineries Pollution, Solid Waste Disposal
919512-0011 > 00013
Jordan River Redevelopment Project 1968-1972
919512-0014 > 0028
Arrow Lake Dam 1958-1969
919512-0029 > 0030
Babine Lake Development (Fulton River Dam) 1967-1970
919512-0031 > 0039
Columbia -River Hydro-Electric Projects 1954-1966
919512-0040 > 0045
Duncan Lake Storage Development 1961-1973
919512-0046 > 0051
Kootenay Canal Development 1967-1973
919512-0052 > 0072
Portage Mountain development (W.A.C. Bennett Dam, Peace River)
1958-1968
919512-0073 > 0086
Miscellaneous Contract Drawings and Tender Documents
919512-0087 Additional Jordan River Redevelopment reports, 1968-1969
919512-0088 Author and title catalogue cards
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 3
File / Item List
Box File Contents Date
1 B.C. Water Management Branch, Power and Special Projects. Miscellaneous incoming correspondence
1914, 1969, 1971-1974
1 B.C. Energy Board. Reports regarding Columbia and Peace River power projects
1961-1969
1 Crippen Wright Engineering Limited. Electric power requirements in the province of British Columbia
1958
1 Upper Yukon River Power Market Potential, Summary report 1970
1 Upper Yukon River Power Market Potential, Working papers 1970
1 B.C. Power Commission. Homathko River Projects (2 volumes with appendices), prepared by Sandwell International Limited
1959
2 B.C. Environment and Land Use Committee. Transcripts of public meetings regarding Tsitikia-Schoen Resources Study (4 volumes)
1975
3 B.C. Hydro and Power Authority. Columbia Construction Reports - regarding Mica, Arrow and Duncan Lake hydro-electric projects
1965-1970
3 Recreation in the Columbia River Basin. A multiple use proposal by the West Kootenay Association of Rod and Gun Clubs
1961
3 Papers of the 18th Canadian Soil Mechanics Conference 1964
3 Papers related to the Canadian National Committee on the International Hydro-electric Decade - includes correspondence and file indexes
1965-1971
4 B.C. Comptroller of Water Rights. Hearings regarding application by the Aluminium Company of Canada for water licenses on the Nechako and Nanika Rivers
1949
4 B.C. Comptroller of Water Rights. Hearing regarding Campbell River floods
1954
4 B.C. Water Rights Branch. Submission of British Columbia to International Joint Commission hearings regarding Creston Reclamation Company and Duck Lake Dyking District application
1955
4 International Joint Commission. Transcript of hearings regarding Creston Reclamation Company and Duck Lake Dyking District application
1955
4 B.C. Comptroller of Water Rights. Hearing on the application of Brenda Mines Limited for water licenses to authorize storage and diversion of water from Pennask Lake
1969
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 4
4 B.C. Comptroller of Water Rights. Hearing in reference to appeal of Texaco Canada Limited regarding channel of Cache Creek
1975
4 B.C. Hydro and Power Authority. Hearing on B.C. Hydro application to construct a dam on the Columbia at Revelstoke
1976
4 B.C. Hydro and Power Authority. Submissions regarding application of B.C. Hydro to construct a dam on the Columbia River at Revelstoke
1976
5 B.C. Department of Highways. Environmental impact study of proposed Annacis Island crossing and highway linkage
1973-1974
5 Classification system for projects under the Lower Fraser River flood control agreement
5 Fisheries Association of B.C. Submission to Pollution Control Board regarding Fraser River
1957
5 Fraser River Joint Advisory Board. Minutes of meetings 1968-1972
5 B.C. Energy Board. Interim Report, Flood Control Benefit Study for Fraser River below Hope
1971
5 B.C. Energy Board. Final Report, Flood Control Benefit Study for Fraser River below Hope
1972
6 Final report on the affect of log-driving on the Stellako River on salmon
Jun 1966
6 Limnological studies of Williston Lake during summer and fall
1975
6 Environmental pollution studies on air quality in British Columbia
1972
6 Environmental impact of proposed smelter at Clinton, B.C. 1972
6 Report No. 2, Environmental impact of proposed smelter at Clinton, B.C.
1973
7 B.C. Department of Agriculture. Soil survey of the Kettle River valley
1960
7 B.C. Water Resources Service. The Kelowna Pollution Control Plant
1975
7 Canada Research Station (Summerland). Scheduling of irrigations in orchards, a progress report on experimental work done in the Okanagan valley
1969
7 Canada - British Columbia Consultative Board. Okanagan Basin agreement - miscellaneous correspondence, reports, tour itineraries, background papers, and studies
1969-1970
8 Municipality of Richmond. Opposition to establishment of a sewage disposal plant on Iona Island
1957
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 5
8 B.C. Pollution Control Board. Transcript of hearing regarding application of the Greater Vancouver Sewerage and Drainage District for a permit to construct a Sewage treatment plant on Iona Island on the North Arm of the Fraser River
1957
8 Greater Vancouver Sewerage and Drainage District. Sturgeon Bank Sampling
1957
8 Greater Vancouver Sewerage and Drainage District. Preliminary Design, Iona Island Sewage Treatment Plant
1957
8 B.C. Pollution Control Board. Supplementary Information regarding application for Lions Gate Sewage Treatment Plant
1959
8 Greater Vancouver Sewerage and Drainage District. Port Moody - Coquitlam Sewerage Survey
1957-1959
9 Miscellaneous papers and reports regarding wildlife management
1965
9 An aerial wildlife survey of the East Kootenay ARDA study area, with accompanying maps
1965
9 An aerial wildlife survey of the Prince George ARDA study area, with accompanying maps
1965
9 B.C. Department of Recreation and Conservation, Fish and Game Branch. Effects on Fish and Game species by development of Mica Dam for hydro-electric purposes
1965
9 B.C. Department of Recreation and Conservation, Fish and Game Branch. Effects on Fish and Game species by development of Arrow Lakes Dam for hydro-electric purposes
1965
9 Canada, Department of Fisheries and B.C. Fish and Wildlife Branch. Report on the fisheries problems associated with the proposed diversion of water from Shuswap River to Okanagan Lake
1969
9 International Pacific Salmon Fisheries Commission (Bulletin 9). Sockeye and Pink Salmon production in relation to proposed dams in the Fraser River System
1960
10 Petroleum Association for the conservation of the Environment. Comments on proposed national air quality objectives
1971
10 British Columbia Petroleum Association. Submission for the Inquiry into pollution control of petroleum refineries in British Columbia
1972
10 Alscope Consolidated Limited. Solid Waste Management using the Nitrocell Process
1973
10 Modular waste reclamation - the emerging approach to solid waste management, prepared by Nitrocell (U.K.) Limited
1972
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 6
11 J-1 International Power and-Engineering Limited. Jordan River Redevelopment Summary of Information for Advisory Committee Meeting No. 1
May 1968
11 J-2 International Power and Engineering Limited. Jordan River Redevelopment, Preliminary Design Report
Jun 1968
11 J-3 International Power and Engineering Limited. Jordan River Redevelopment - Flood Studies
Nov 1968
12 J-4 B.C. Hydro and Power Authority. Jordan River Redevelopment - Progress Reports No. 2-16
1969
13 J-4 B.C. Hydro and Power Authority. Jordan River Redevelopment - Progress Reports No. 17-28
1969
14 A-1 L.R. Churchill and L.E. Salkeld. Report on Arrow Lakes Damsite Flowage Costs to Elevation 1460
Sep 1958
14 A-2 C.B.A. Engineering Limited. Arrow Lakes Dam Report on Selection of the Damsite
May 1961
14 A-3 P.C. Forward and J.M. Bogyd of B.C. Power Commission. The Present Economic Status of the Arrow Lakes Valley
Jun 1961
14 A-4 Consolidated Services Limited. Appreciation of Land Clearing Operations for High Arrow Reservoir
Jul 1961
14 A-5 Arrow Lakes Dam. Report on the Investigations and Preliminary Design of Arrow Lakes Dam, C.B.A. Engineering Limited
Aug 1961
14 A-6 Arrow Lakes Dam. Report on Selection of the Damsite, C. B.A. Engineering Limited
Aug 1961
15 A-7 Arrow Lakes Dam. Report on the Investigations and Preliminary Design of Arrow Lakes Dam (Volume 1), C.B.A. Engineering Limited
Sep 1961
15 A-8 Arrow Lakes Dam. Report on the Investigations and Preliminary Design of Arrow Lakes Dam (Volume 2, Appendices 1 to 3), C.B.A. Engineering Limited
Sep 1961
15 A-9 Arrow Lakes Dam. Report on the Investigations and Preliminary Design of Arrow Lakes Dam (Volume 3, Appendices 4 to 8), C.B.A. Engineering Limited
Sep 1961
15 A-10 Arrow Lakes Dam. Report on the Investigations and Preliminary Design of Arrow Lakes Dam (Volume 4, Appendix 9), C.B.A. Engineering Limited
Sep 1961
15 A-11 Arrow Lakes Dam. Report on the Investigations and Preliminary Design of Arrow Lakes Dam (Volume 5, Appendix 9 - Data for Section 8 Site), C.B.A. Engineering Limited
Sep 1961
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 7
15 A-12 Arrow Lakes Dam. Report on the Investigations and Preliminary Design of Arrow Lakes Dam (Volume 6, Appendix 9 - Data for Tunnel, Allandale, Syringa East, and Syringa Fansites), C.B.A. Engineering Limited
Sep 1961
16 A-14 Report to C.B.A. Engineering Limited on Laboratory Permeability Tests. Reports No. I and 2, Undisturbed Soil Samples from Section 8, Arrow Lake Dam - R.C. Thurber and Associates Limited
Sep 1961
16 A-15 Hearings Regarding Arrow Lakes Water Licences. Master copies 3-8
26-27 Sep 1961, 29-30 Sep 1961, 3-4 Oct 1961
17 A-16 Permeability Coefficients of the Foundations for the Proposed Arrow Lakes Dam as Determined from Pumping Tests. Robinson, Roberts, and Brown, consultants
Oct 1961
17 A-17 Submission-by Celgar Limited Regarding Arrow Lakes Dam 17 Nov 1961
17 A-18 B.C. Power Commission. Arrow Lakes Dam Hydraulics, Report on a Study of the Arrowhead - Revelstoke Reach - C.B.A. Engineering Limited
23 Jan 1962
17 A-19 C.B.A. Engineering Limited. Laboratory Test Results, Report No. 6 - Thurber and Associates Limited
31 Jan 1962 - 31 May 1962
17 A-20 British Columbia Power Commission. Arrow Lakes Dam Hydraulics, Report on an Economic Study of the Full Surface Level - C.B.A. Engineering Limited
5 Feb 1962
17 A-21 Comparison of Log Handling Methods for Arrow Lakes Dam. Draft Report (Preliminary Only), Appendices 1 to 11, C.B.A. Engineering Limited
12 Feb 1962
17 A-22 Arrow Lakes Project. Agricultural Studies, Economics Division, Canada, Department of Agriculture (Ottawa)
Feb 1962
17 A-23 B.C. Power Commission. Arrow Lakes Dam Report of Cost Estimates for Log Handling Methods, C.B.A. Engineering Limited
1 Mar 1962
17 A-24 B.C. Power Commission, Engineering Branch. Report on the Effect of the Arrow Lakes Dam on the Revelstoke Bridges, A.G. Ballantyne
6 Mar 1962
17 A-25 B.C. Power Commission. The Design Requirements of the Hydraulic Facilities of the Arrow Lakes Project, C.B.A. Engineering Limited
7 Mar 1962
17 A-26 B.C. Power-Commission. Arrow Lakes Dam - Appendum No. I to Report of Cost Estimates for Log Handling Methods, C.B.A. Engineering Limited
21 Mar 1962
17 A-27 Concrete Aggregate Investigations. Eldridge Coast 11 May 1962
17 A-28 Geological Investigation. Arrow Dam Report No. 4, D.D. Campbell
14 May 1962
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 8
18 A-29 Arrow Lakes Dam. Collected Hydraulic Studies, C.B.A. Engineering Limited
9 Jul 1962
18 A-30 C.B.A. Engineering Limited. Laboratory Tests on Soil Samples from Dumping Test 5 (West Blanket), Boreholes T1, T2, T3, T5, Arrow Lakes Dam, R.C. Thurber and Associates Limited
26 Jul 1962
18 A-31 C.B.A. Engineering Limited. Laboratory Test Results on Compacted Borrow Material (Balfour Creek Till), Arrow Lakes Dam, R.C. Thurber and Associates Limited
14 Aug 1962
18 A-32 Arrow Lakes Project. Flood Studies and Design of Discharge Facilities, submission by Licencee with regard to discussions with U.S. Agencies, C.B.A. Engineering Limited
20 Aug 1962
18 A-33 Report No. 1 to C.B.A. Engineering Limited on Laboratory Tests. Undistrubed Silt Samples from Section 8, Drill Hole 172, Samples 12 and 14, R.C. Thurber and Associates Limited
27 Aug 1962
18 A-34 Report to C.B.A. Engineering Limited. Tests on Balfour Till and Causeway Gravel Artificially sedimented in the Laboratory - Thurber and Associates Limited
4 Sep 1962
18 A-35 B.C. Hydro and Power Authority. Arrow Lakes Dam Model Demonstration of Navigation Conditions at Hydraulic Model Laboratory, Ontario, C.B.A. Engineering Limited
27 Sep1962
18 A-36 Report No. 2 to C.B.A. Engineering Limited on Laboratory Tests. Undisturbed Silt Samples from Section 8 Drill Holes 170, 171 and 172, R.C. Thurber and Associates Limited
31 Oct 1961
18 A-37 B.C. Hydro and Power Authority. Arrow Lakes Dam Addendum No. 2 to report of Cost Estimates for Log Handling Methods - C.B.A. Engineering Limited
9 Oct 1962
18 A-38 Preliminary Drawings for Arrow Lakes Dam, C.B.A. Engineering Limited
26 Oct 1962 - 6 Feb 1963
18 A-39 Site Investigations Nov 1962 - Jan 1963, Arrow Lakes Dam, C.B.A. Engineering Limited
Jul 1963
19 A-40 Report to C.B.A. Engineering Limited on Laboratory Permeability Tests on 5 Selected natural till samples, R.C. Thurber and Associates Limited
30 Nov 1962
19 A-41 B.C. Hydro and Power Authority. Arrow Lakes Dam - Report on Large Scale Field Tests, C.B.A. Engineering Limited
1 Dec 1962
19 A-42 Report to C.B.A. Engineering Limited on Laboratory Permeability Tests on 3 manufactured till samples, R.C. Thurber and Associates Limited
11 Dec 1962
19 A-43 B.C. Hydro and Power Authority. Arrow Lakes Dam - Report on Exploration of Borrow Areas for Impervious Material, C.B.A. Engineering Limited
21 Dec 1962
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 9
19 A-44 B.C. Hydro and Power Authority. Arrow Lakes Dam - Summary of Exploration of Borrow Areas for Granular Material (Preliminary), C.B.A. Engineering Limited
Dec 1962
19 A-45 Report to C.B.A. Engineering Limited on Laboratory Permeability Tests on Layered Manufactured Till Samples, R.C. Thurber and Associates Limited
31 Jan 1963
19 A-46 Report to C.B.A. Engineering Limited on Consolidation Tests on Soil Representing the Extreme Limits Allowed in Construction Specifications, R.C. Thurber and Associates Limited
15 Feb 1963
19 A-47 Report to C.B.A. Engineering Limited on Laboratory Settling Tests on Balfour Till, R.C. Thurber and Associates Limited
6 Mar 1963
19 A-48 C.B.A. Engineering Limited, Laboratory. Permeability Tests on Undisturbed Soil Samples of Dry Blankets 2 and 3 and Wet Blanket 5, Arrow Lakes Dam, R.C. Thurber and Associates Limited
19 Apr 1963
19 A-49 B.C. Hydro and Power Authority. Arrow Lakes Dam Report on Disposal of Silt Excavated from River (Preliminary), C.B.A. Engineering Limited
20 Jun 1963
19 A-50 Report on Log Handling During Construction, C.B.A. Engineering Limited
12 Jul 1963
19 A-51 B.C. Hydro and Power Authority. Arrow Lakes Dam - Report on the Use of Temporary Log Handling Facilities During Construction (preliminary only), C.B.A. Engineering Limited
16 Aug 1963
19 A-52 B.C. Hydro and Power Authority. Arrow Lakes Dam - Description of Navigation Lock and Handling of Marine Traffic, C.B.A. Engineering Limited
12 Sep 1963
19 A-53 B.C. Hydro and Power Authority. Arrow Lakes Dam - Temporary Water Supply for Celgar Limited, Economic Studies, C.B.A. Engineering Limited
25 Sep 1963
19 A-54 Second Loading Test on Impervious Blanket Placed under water, Arrow Lakes Dam - C.B.A. Engineering Limited
Sep 1963
19 A-55 Drawings for Arrow Lakes Dam. Big Eddy Subdivision - Property Requirements, Revelstoke Land Protection, General Arrangement, Structures, and Preliminary Design Construction, C.B.A. Engineering Limited
2 Jul 1964, 10 May 1965, 26 Mar 1966
19 A-56 B.C. Hydro and Power Authority. Arrow Dam Design Memorandum, Arrow Dam - Construction Method for Earth Dam, C.B.A. Engineering Limited
Aug 1964
20 A-57 B.C. Hydro and Power Authority. Arrow Project, Construction of Arrow Dam, Specification No. CA-1 and Addenda Volume 1 to 5, C.B.A. Engineering Limited
16 Oct 1964
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 10
20 A-58 B.C. Hydro and Power Authority. Arrow Project, Report on Water Supply to Miscellaneous Small Consumers Living Near the Columbia River in Canada Downstream of the Arrow Project, C.B.A. Engineering Limited
1 Feb 1965
20 A-59 B.C. Hydro and Power Authority. Arrow Project Report on a Survey of Water Consumers Living near the Columbia River Between the Arrow Damsite and the Canada-U.S. Border, C.B.A. Engineering Limited
1 Feb 1965
20 A-60 Arrow Lakes Dam. Navigation Lock Hydraulic Model, Lasalle Hydraulic Laboratory Limited
Feb 1965
21 A-61 B.C. Hydro and Power Authority. Preliminary Report on the Performance of Arrow Reservoir-under 1894 flood conditions, C.B.A. Engineering Limited
3 Mar 1965
21 A-62 Effects on Fish and Game Species of Development of Arrow Lakes for Hydro-Electric Purposes, British Columbia, Fish an Game Branch, Department of Recreation and Conservation
Mar 1965
21 A-63 B.C. Hydro and Power Authority. Columbia Construction Progress Reports - Duncan, Arrow, Mica
1966-1969
21 A-64 B.C. Hydro and Power Authority. Design Memorandum, Arrow Dam, Stability of the Earth Dam, C.B.A. Engineering Limited
26 Apr 1965
21 A-65 B.C. Hydro and Power Authority. Interim Report on the Performance of Arrow Reservoir under 1894 Flood Conditions, C.B.A. Engineering Limited
14 May 1965
21 A-66 Columbia River Treaty - Arrow Project, B.C. Hydro and Power Authority
May 1915
21 A-67 The New Outlook for the Arrow Lakes, B.C. Hydro and Power Authority
Jun 1965
21 A-68 Columbia River Development Report. Arrow Project, Discharge Capacity, C.B.A. Engineering Limited and B.C. Hydro and Power Authority
Aug 1965
21 A-69 Report Regarding Cut-off Wall Arrow Dam Project, Dolmage and Campbell Associates
17 Nov 1965
21 A-70 Special treatment Requirements for Specified Clearing Areas in the Vicinity of Revelstoke, Nakusp and Burton, C. D. Schultz and Company Limited
Dec 1965
21 A-71 Report on Faults in Foundation Bedrock, Arrow Dam Project, Dolmage, Campbell and Associates
13 Jun 1966
21 A-72 Report on Foundation Bedrock Geology, High Arrow Dam, C.B.A. Engineering Limited, D.D. Campbell
8 Aug 1966
21 A-73 B.C. Hydro and Power Authority. Arrow, Project, Arrow Dam - Foundation Bedrock, Report No. 6613, C.B.A. Engineering Limited
Nov 1966
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 11
22 A-74 B.C. Hydro and Power Authority. Arrow Dam - Resident Engineer's Monthly Reports on Construction Progress
May 1966 - Oct 1966
23 A-74 B.C. Hydro and Power Authority. Arrow Dam - Resident Engineer's Monthly Reports on Construction Progress
Nov 1966 - Dec 1966
24 A-74 B.C. Hydro and Power Authority. Arrow Dam - Resident Engineer's Monthly Reports on Construction Progress
Jan 1967 - Jun 1967
25 A-74 B.C. Hydro and Power Authority. Arrow Dam - Resident Engineer's Monthly Reports on Construction Progress
Jul 1967 - Dec 1967
26 A-74 B.C. Hydro and Power Authority. Arrow Dam - Resident Engineer's Monthly Reports on Construction Progress
Dec 1967 - Jan 1968
27 A-74 B.C. Hydro and Power Authority. Arrow Dam - Resident Engineer's monthly reports on construction progress, Jul 1968 - Dec 1968, Jan 1969 - Aug 1969
1968-1969
28 A-75 Arrow Project. Data Tabled at Site Meetings, Oct 25, 26 1966, C.B.A. Engineering Limited
Oct 1966
28 A-77 B.C. Hydro and Power Authority. Arrow Dam Project Information, C.B.A. Engineering Limited
1967
28 A-78 Arrow Project. A Recreational Reconnaissance of Lands that will be Adjusted to the Shoreline of the Arrow Reservoir
28 A-79 Data on Property Affected Arrow Lakes Project for Kaiser Aluminum and Chemical Corporation, Report No. 55-19-R (Job No. 5599-9)
28 Mar 1955
28 A-80 An appreciation of the problems which might result from the Arrow Lakes storage project - Application by the Kaiser Aluminum and Chemical Company
Dec 1954
28 A-81 Report on materials of construction survey for the Arrow Lakes Project
Jan 1961
28 A-82 Geology of the Arrow Lakes Damsite, Geological Survey of Canada
28 A-83 Report on Arrow Lakes Storage possibilities, Water Rights Branch, Department of Lands and Forests
20 Mar 1949
28 A-84 Flowage reports. dam at Arrow Lakes outlet, dam at Murphy Creek
Apr 1957
28 A-85 Preliminary Report on Arrow Lakes Storage to the International Joint Commission, International Columbia River Engineering Board
1949
28 A-86 Engineering Report on Design and estimate of cost of Arrow Lakes Project for Kaiser Aluminum and Chemical Corporation, Henry J. Kaiser Company (Canada) Limited
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 12
28 A-87 Arrow Project. Arrow Dam - studies of uplift pressure beneath the north blanket during reservoir drawdown, Drawings and report (2 separate volumes),C.B.A. Engineering Limited
Apr 1965
28 A-88 Arrow Project. Arrow Dam - Minutes of meeting Oct 8 1968, C.B.A. Engineering Limited
1968
28 A-89 B.C. Hydro and Power Authority. Arrow Project, Arrow Dam - 6 plans describing Balfour borrow area and haulroad remedial work
19 Aug 1969
29 B-1 Department of Fisheries of Canada. Babine Lake Development Project No. 11 (Fulton River Dam) - Copy of advertisement, instructions to tenderers, form of tender, articles of agreement, terms of payment, labour conditions, insurance schedule, general conditions, and specifications, Vancouver, B.C., prepared by G.E. Crippen and Associates
Apr 1968
29 B-2 Department of Fisheries of Canada. Babine Lake Development Project No. 4, Fulton River Regulating Works and Supply Tunnel - Copy of advertisement, instructions to tenderers, form of tender, articles of agreement, terms of payment, labour conditions, insurance schedule, general conditions, and specifications, prepared by G.D. Crippen and Associates Limited
Apr 1968
29 B-3 Department of Fisheries of Canada. Babine Lake Development Project No. 5, Pinkut Creek Spawning Channel Contract No. 4 - Copy of advertisement, instructions to tenderers, form of tender, articles of agreement, terms of payment, labour conditions, insurance schedule, general conditions and specifications, Vancouver
1968
29 B-4 Department of Fisheries of Canada. Babine Lake Development, Fulton Lake reservoir clearing projects - Copy of advertisement, instructions to tenderers, form of tender, articles of agreement, terms of payment, labour conditions, insurance schedule, general conditions, and specifications, prepared by F.F. Slaney and Company Limited, Vancouver
1968
30 B-5 Department of Fisheries of Canada; Babine Lake Development Project No. 9, Fulton River spawning channel No. 2, Contract No. 3, Completion Stage One - Copy of Advertisement, instructions to tenderers, form of tender articles of agreement, terms of payment, labour conditions, insurance schedule, general conditions and specifications, Vancouver
1969
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 13
30 B-6 Department of Fisheries of Canada. Babine Lake Development Project No. 15, Fulton River Pipeline - Copy of Advertisement, instructions to tenderers, form of tender, articles of agreement, terms of payment, labour conditions, insurance schedule, general conditions, and specifications, Vancouver
1968
30 B-7 Department of Fisheries of Canada. Babine Lake Development Project No. 9, Fulton River Spawning Channel No. 2, Contract No. 3, Completion stage one - Copy of advertisement, instructions to tenderers, form of tender, articles of agreement, terms of payment labour conditions, insurance schedule, general conditions and specifications, Vancouver, B.C.
Apr 1969
31 F.J. Bartholemew. Columbia River Treaty and Protocol Brief, 49 pages
31 B.C. Engineering Company. Columbia River Study - Preliminary Report, Proposals for the hydro-electric development of the Columbia River system in Canada
30 Oct 1957
31 Crippen Wright Engineering Limited. Report - Hydro-electric development of the Columbia River Basin in Canada
1959
31 Crippen Wright Engineering Limited. Upper Columbia Hydro-electric Developments, Interim Report No. 2, Diversion of the Kootenay River into Columbia River
1958
31 Crippen Wright Engineering Limited. Upper Columbia Hydro-electric developments, Interim Report No. 2, Kinbasket reservoir versus Mica reservoir operating with Kootenay River diversion for maximum Canadian generation
1958
32 Crippen Wright Engineering Limited. Upper Columbia River hydro-electric Developments, Interim Report No. 4, Low Revelstoke - Kinbasket Scheme operating with Kootenay River diversion for maximum Canadian generation
1958
32 Crippen Wright Engineering Limited. Upper Columbia River Hydro-electric Developments, Interim Report No. 5, Clearwater - Columbia Schemes with and without high calamity curve reservoir operating for maximum Canadian generation
1958
32 Crippen Wright Engineering Limited. Upper Columbia River Hydro-electric Developments, Interim Report No. 6, High Arrow Lakes - Libby and Low Arrow Lakes, Libby Schemes operating for maximum available power to Canada
1958
32 Crippen Wright Engineering Limited. Upper Columbia River Hydro-electric developments, Interim Report No. 7, Comparison of Alternate Schemes
1958
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 14
32 Crippen Wright Engineering Limited Upper Columbia River Hydro-electric Developments, Interim Report No. 8, Power Transmission Systems
33 Report on Columbia River Development (3 volumes, with appendix), Prepared for B.C. Power Commission by Caseco Consultants Limited, Vancouver, B.C.
1961
33 Columbia River Development, Report on Mica Creek Storage Project, Prepared for B.C. Power Commission by Caseco Consultants Limited
1961
34 B.C. Power Commission. Columbia River Development, Hydrologic Studies - Report No. 1, Basic data and outline of proposed studies, Report No. 2, Study of preliminary design floods and flood routing, Prepared by Caseco Consultants Limited
1961
34 B.C. Power Commission. Correspondence regarding Columbia River development hydrologic studies
1961
34 B.C. Power Commission. Plans of Mica dam spillway and associated works
34 B.C. Power Commission. Columbia River Studies, Report on Mica Creek hydro-electric development
1960
35 Reports of the U.S. Pacific Northwest River Basins Commission, Power Planning Committee. Annual reviews of power planning in the Columbia River basin
1967-1972
35 U.S. Columbia Basin Inter-agency Committee, Power Planning Subcommittee. Annual reviews of power planning in the Columbia River basin, 1962-1966, miscellaneous reports on hydro-electric transmission, power potential inventories, and thermal-electric plants in the Columbia River basin, 1949-1966
36 U.S. Columbia Basin inter-agency Committee. Minutes of meetings
1954-1960
37 U.S. Columbia Basin Inter-agency Committee. Minutes of meetings
1960-1964
38 U.S. Columbia Basin Inter-agency Committee. Minutes of meetings
1964-1966
39 U.S. Columbia Basin Inter-agency Committee. Report on determination of historical flows at selected power sites, Columbia River Basin, 1956, miscellaneous reports on water flows, stream depletion, river mile indexes, 1956-1962
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 15
39 Report to the International Joint Commission United States and Canada. Water Resources of the Columbia River Basin, prepared by the International. Columbia River Engineering Board
1959
40 D-1 Duncan Lake Studies, Conducted by B.C. Water Resources Branch
40 D-2 B.C. Power Commission. Laboratory Test Results, Duncan Lake Project, Materials Holes, R.C. Thurber and Associates
17 Apr 1961
40 D-3 Report regarding Triaxial Testing Program Duncan Lakes Project to Montreal Engineering Company Limited, prepared by Soil Mechanics Services Limited
29 Apr 1961
40 D-4 Report on Preliminary Investigations, Duncan Lake Reservoir, Forestral Forestry and Engineering Limited
Jul 1961
40 D-5 B.C. Power Commission. Columbia River Development Feasibility Study, Duncan Storage Project (2 Volumes), Montreal Engineering Company Limited and Crippen Wright Engineering Limited
Jul 1961
40 D-6 B.C. Power Commission, Engineering and Operations Department, Planning Branch. Report on B.C. Hydro Subsurface Investigation Oct - Dec 1960, Duncan Lake Project, Aug 10 1961
1960, 1961
40 D-7 Statement by Consolidated Mining and Smelting Company of Canada Limited to Comptroller of Water Rights Regarding Licence Application for Duncan Lake Storage
15 Sep 1961
40 D-8 Licence Hearings on Duncan and Arrow Lakes, Master Copies 2, 9, 10
2 Sep 1961, 21-22 Nov 1961
40 D-9 Duncan Lake Development, General Report No. 262 and Appendix 2, Lasalle Hydraulic Laboratory Limited and Montreal Engineering Company Limited
Apr 1962
40 D-10 Duncan Lake Storage Development, Specifications for Clearing the site of Duncan Lake Dam and Reservoir Discharge works at Duncan Lake, B.C. and Addenda, Montreal Engineering Company Limited
22 May 1962
41 D-11 Duncan Lake Storage Development, Specifications for the Construction of Duncan Lake Dam and Reservoir Discharge Works at Duncan Lake, B.C., Volume 1-4 and Addenda
May 1962, 30 Nov 1962
41 D-12 Duncan Lake Storage Development, Summary of Field Investigations and Reports, Montreal Engineering Company Limited
May 1964
41 D-13 Duncan Lake Storage Development, Specification No. CD-2, for the construction of Duncan Lake Dam and Reservoir Discharge works at Duncan Lake, B.C., Volume 1-4, Montreal Engineering Company Limited
Jun 1964
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 16
42 D-14 Duncan Lake Project. Preliminary Report on Review of Probable Maximum Inflow Flood to Duncan Reservoir, Caseco Consultants Limited
Aug 1964
42 D-15 Duncan Lake Storage Project. Alternative Spillways and Seepage Control Cut-Offs, Aug 14 1964 and Revised copy of Aug 21 1964, Montreal Engineering Company Limited
1964
42 D-16 Columbia River Studies. Probable Maximum Floods for Mica, Arrow and Duncan Projects, Caseco Consultants Limited
Oct 1964
42 D-17 Columbia River Studies. Report on Review of Probable Maximum Inflow Floods to Mica, Arrow and Duncan Reservoirs, Caseco Consultants Limited
Oct 1964
42 D-18 Duncan Lake Storage Development. Specification No. CD-3 for the supply and Installation Gates for the Reservoir Discharge Works at Duncan Lake. Volumes 1-4 and Addenda, Montreal Engineering Company Limited
Nov 1964
42 D-19 Duncan Lake Dam Storage Development. Right Abutment Drainage - Correspondence and Drawings
1964-1965
42 D-20 Duncan Lake Development. Site Geology, Montreal Engineering Company Limited and Dolmage and Campbell Associates
Jan 1965
42 D-21 Effects on Fish and Game Species of development of Duncan Dam for Hydro-electric Purposes, B.C. Department of Recreation and Conservation, Fish and Game Branch
Feb 1965
42 D-22 The effects on Fisheries of Proposed West Kootenay Water-Storage Project at Trout Lake, P.A. Larkin
1951
42 D-23 Duncan Lake Dam. Spillway Hydraulic Model (Resume of Studies Carried out to the 8th of Feb 1965), Lasalle Hydraulic Laboratory Limited
42 D-24 Duncan Lake Storage Development. Field Investigations Subsequent to May 1964, Montreal Engineering Company
2 Feb 1965
42 D-25 Duncan Lake Development. Hydraulic Model of Spillway, Lasalle Hydraulic Laboratory Limited
May 1965
42 D-27 Duncan Lake Storage Development. Interim Report on Field Investigations, Montreal Engineering Company Limited
Feb - May 1965
42 D-28 Duncan Lake Storage Development. Specification No. CD-4 for the Supply and Installation of Spillway Gates at Duncan Lake, B.C., Volumes 1-4, Montreal Engineering Company Limited
Jun 1976
43 D-29 Duncan Lake Storage Development. Report on Treatment of West Abutment, Montreal Engineering Company Limited
Jul 1965
43 D-30 Duncan Lake Development. Report on Hydraulic Model Studies of Outlet works for Montreal Engineering Company Limited, Western Canada Hydraulic Laboratories Limited
Aug 1965
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 17
43 D-31 Clearing Contract and Specification No. DL 1 for Duncan Project, Clearing Areas A, B, C, and D on Duncan Lake, B.C. Hydro and Power Authority, Land Division
29 Sep 1965
43 D-32 Duncan Lake Development. Tender Drawings, Montreal Engineering Company Limited
Oct 1965
43 D-34 Duncan Lake Storage Development. Interim Report on Field Investigations, Jun - Oct 1965, Montreal Engineering Company Limited
19 Nov 1965
43 D-35 Duncan Lake Storage Development. Interim Report on Field Investigations, Nov 1965 - Jul 1966, Montreal Engineering Company Limited
19 Nov 1965
43 D-36 B.C. Hydro and Power Authority. Special Treatment Requirements for Specified Clearing Areas in the vicinity of Revelstoke, Nakusp, and Burton, C.D. Schultz and Company
Dec 1965
43 D-37 Duncan Lake Development. Spillway Stage Discharge Curves, Lasalle Hydraulic Laboratory Limited
29 Dec 1965
43 D-38 Duncan Lake Dam Storage Development. Report on Dam Cracking and Slurry Trench Failure
1965-1966
43 D-39 Columbia River Development. Supplemental Report, Duncan Project, Discharge Capacity, Montreal Engineering Limited
28 Mar 1966
43 D-40 Progress Report regarding significance of results on Duncan Lake Dam instrumentation, Dr. R.M. Hardy
15 Apr 1966
43 D-41 Duncan Lake Storage Development. Report on Flow Control and instrumentation, Montreal Engineering Company Limited
21 Apr 1966
43 D-42 B.C. Research Council. Sensing of Subterranean Settlement, Phase 1, Part 2, Development of Alternate Systems, prepared for Montreal Engineering Company Limited
24 May 1966
43 D-43 Duncan Lake Storage Development. Report on Events preceding and during two slurry trench failures at Duncan Lake, Montreal Engineering Company Limited
13 Jul 1966
43 D-44 Duncan Lake Storage Development. Report on Dam Construction Progress
9 Aug 1966
43 D-45 Duncan Lake Storage Development. Project Appraisal, Jan 1967, Montreal Engineering Company Limited
10 Jan 1967
43 D-46 Duncan Lake Storage Development. Report on Test Shaft in Duncan Dam, Montreal Engineering Company Limited
3 Feb 1967
44 D-47 Duncan Lake Storage Development. Reports on Dam Foundation, Settlement and Piezometer Readings, Montreal Engineering Company Limited
12 May 1967
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 18
45 D-48 Duncan Lake Storage Development. Boat Launching Ramp Drawings
1967
45 D-49 B.C. Hydro and Power Authority. Duncan Lake Storage Development, Project Appraisal, Montreal Engineering Company Limited
Aug 1967
45 D-50 Duncan Project. Duck Lake, Waterfowl Nesting Habitat, Plan of Development, International Power and Engineering Consultants Limited
Dec 1967
45 D-51 Duncan Project. Inflow Record and Summary 1967-1968
45 D-52 Duncan Storage Project. Design, installation and performances of deep seated settlement gauges, Montreal Engineering Company Limited
14 May 1968
45 D-53 Duncan Project. Dam inspection, Montreal Engineering Company Limited
Apr 1968
45 D-54 Duncan Project. Operating and Maintenance Manual, Volume 2, Montreal Engineering Company Limited
Apr 1968
45 D-55 Report on materials of construction survey for the Duncan River Project
Jan 1961
45 D-56 Geological Survey of Canada. Geology of the Duncan River Damsite
Oct 1958
45 D-57 Report of flowage costs to elevation 1900 for the Duncan River Dam
Oct 1958
45 D-59 Duncan Project. Summary Report, Duncan River Access Road, Reid, Collins, and Associates Limited
Jan 1969
45 D-60 B.C. Hydro and Power Authority. Columbia Construction Progress, Duncan Project - Review of construction
45 D-61 Duncan Project. Letter Report on Evaluation of flowage easement requirements for properties affected by releases from Duncan Dam, I. P. E. C.
Dec 1971
45 D-63 Duncan Dam. Report on Duncan Lake Storage, Columbia River Treaty, P. E. B. Civil Inspection Section
21 Feb 1973
46 K-1 Proposal for Engineering Study - Kootenay Canal Plant, Submitted to Department of Lands, Forests and Water Resources, G.E. Crippen and Associates Limited
24 Feb 1967
46 K-2 Kootenay Canal Project Site Geology, Kootenay River Canal Plant, South Slocan, B.C., G.E. Crippen and Associates Limited
19 Jun 1967
46 K-3 Kootenay Canal Project. 1967 Seismic Investigations, Power House Area, Report to G.E. Crippen and Associates Limited by Geo-Recon Explorations Limited
Jun 1967
46 K-4 Kootenay Canal Plant - Feasibility Report, G.E. Crippen and Associates Limited
Aug 1967
46 K-5 B.C. Hydro and Power Authority, Major Resources Division. Kootenay Canal Plant - preliminary report on design criteria
Mar 1968
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 19
46 K-6 B.C. Hydro and Power Authority. Kootenay Canal Development, Contract No. KC-11, Powerhouse Access Road, Tender Documents, 2 Volumes, (I. P. E. C.)
Nov 1971
46 K-7 B.C. Hydro Power Authority. Kootenay Canal Development - Contract No. KC 4, Turbines and Governors, Tender Documents, 2 volumes (I. P. E. C.)
Aug 1971, Sep 1971
46 K-8 B.C. Hydro and Power Authority. Kootenay Canal Development - Contract KC-5, generators, tender documents, 2 volumes (I. P. E. C.)
Sep 1971
46 K-9 B. C Hydro and Power Authority. Kootenay Canal Development - Contract No. KC-6, Kootenay River Bridge, Tender Documents (I. P. E. C.)
Dec 1971
47 K-11 B.C. Hydro and Power Authority. Monthly Progress Reports for the Kootenay Canal Project, No. 1-19
48 K-11 B.C. Hydro and Power Authority. Monthly progress reports for the Kootenay Canal Project, No. 20-31
49 K-11 B C. Hydro and Power Authority. Monthly progress reports for the Kootenay Canal Project, No. 32-46
50 K-10 B.C. Hydro and Power Authority. Kootenay Canal Development - Contract No. KC 7 Canal, tender documents, 3 volumes, (I. P. E. C.)
Feb 1972
50 K-12 B.C. Hydro and Power Authority. Preliminary drawings showing perspective views and architectural details of the Kootenay Canal powerhouse
50 K-13 B.C. Hydro and Power Authority, Production Division, Power Equipment Maintenance Control Branch. Kootenay Canal Plant, Maintenance standard - Electrical Production - Policy
1 Aug 1970
50 K-14 B.C. Hydro and Power Authority. Kootenay Canal Development - Contract No. KC-8 Powerplant, 4 volumes
Oct 1972
51 K-15 Appraisal of the Kootenay Canal Project - GEPAC Dec 1972
51 K-16 B.C. Hydro and Power Authority. Report to the Regional Districts of Central and East Kootenay on the Kootenay Canal to Cranbrook Transmission Line
Jun 1973
51 K-17 Joint Report - combined loads and resources of the B.C. Hydro and Cominco - W. K. P. and L. Systems
15 Jul 1968
51 K-18 Interim Report on studies of the energy capabilities of the Cominco-West Kootenay Power and Light Canal Plant Systems
6 Nov 1968
51 K-19 Cominco-West Kootenay basic supply work group, Report No. 2 to the Negotiating Committee
22 Mar 1972
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 20
51 K-20 Kootenay Canal Project. Agreement on Basic Supply and Sharing of Benefits between B.C. Hydro and Cominco-West Kootenay
15 Mar 1972
51 K-21 Kootenay Canal Plant. Notes of meeting and correspondence
1971-1972
51 K-22 Status Report on Acquisition of City of Nelson Property for construction of Kootenay Canal Project
Dec 1973
51 K-24 Kootenay Canal Plant. Review of peaking capability and installed capacity, G.E. Crippen and Associates Limited
18 Dec 1969
51 K-25 Kootenay Canal Development. Summary of Information for Advisory Board Meeting No. 2, I. P. E. C.
Oct 1975
51 K-26 City of Nelson. Kootenay Canal Land Acquisition, Documents regarding "The Taking"
27 Apr 1976
52 P-23 B.C. Hydro and Power Authority. Peace River Hydro-Electric Project, Portage Mountain Development - Construction Progress Reports
Apr 1965 - Dec 1967
53 P-23 B.C. Hydro and Power Authority. Peace River Hydro-Electric Project, Portage Mountain Development - Construction Progress Reports
Jan 1968 - May 1968
54 P-23 B.C. Hydro and Power Authority. Peace River Hydro-Electric Project, Portage Mountain Development - Construction Progress Reports
Jun 1968 - Dec 1968
55 P-23 B.C. Hydro and Power Authority. Peace River Hydro-Electric Project, Portage Mountain Development - Construction Progress Reports
Jan 1969 - Jan 1971
56 P-24 Peace River Project. Progress Reports, B.C. Hydro and Power Authority and International Power and Engineering Consultants Limited
1964 - 1968
57 Papers regarding Portage Mountain Dam, presented at the 19th Canadian Soil Mechanics Conference
1966
57 B.C. Water Rights Branch. Exhibits regarding Portage Mountain Dam applications
1962
57 Wenner-Gren British Columbia Development Company Limited, Volume 1, Report on the Feasibility of transmitting Power from Peace River to Vancouver, British Thomson-Houston Export Company, Limited
57 Wenner-Gren British Columbia Development Company Limited, Volume 1, Appendix 1, Report on the Feasibility of Transmitting Power from Peace River to Vancouver, British Thomson-Houston Export Company, Limited
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 21
57 Wenner-Gren British Columbia Development Company Limited, Report on the Feasibility of Building Dams on the Peace River, Appendix 1 - Memorandum on available Supplies for Peace River Project by Sir Thomas Foy, Appendix 2 - Memorandum on Run Off of Peace River at Hudson Hope, The British Thomson-Houston Export Company Limited
57 Wenner-Gren British Columbia Development Company Limited, Volume 1 - Report on the Feasibility of Building Dams on the Peace River, British Thomson-Houston Export Company, Limited
57 Wenner-Gren British Columbia Development Company Limited, Report on the Feasibility of Building Dams on the Peace River, Appendix 6, Report on Visit to Peace River Canyon, Peace River Project Interim Report by the Cementation Company Limited, British Thomson Houston Export Company, Limited
57 Wenner-Gren British Columbia Development Company Limited, Report on the Feasibility of Building Dams on the Peace River, Appendix 7, Memorandum on Peace River Hydro Electric Project Stage 2 by Sir Thomas Foy, British Thomson-Houston Export Company, Limited
58 P-131 Peace River Hydro-Electric Project. Contract No. 111, Portage Mountain Development, Reservoir Debris Booms, Volumes 1 and 2, and Addenda, Tender documents and contract documents, International Power and Engineering Consultants Limited
6 Jan 1967, 13 Mar 1967
58 P-132 Peace River Hydro-Electric Project. Portage Mountain Dam, Report on river closure and coffer dam construction model studies, LaSalle Hydraulic Laboratory Limited
Sep 1962
58 P-133 Peace River Hydro-Electric Project. Portage Mountain Dam, Report on availability of construction materials, International Power and Engineering Consultants Limited
21 Dec 1962
58 P-134 Portage Mountain Project - Summary of information for panel meeting No. 12, International Power and Engineering Consultants Limited
3-7 Jul 1967
58 P-135 Report to International Power and Engineering Consultants Limited on Portage Mountain Development, Zone 6A, material drained triaxial compression tests, R.C. Thurber and Associates Limited
31 Jul 1967
58 P-136 Peace River Hydro-Electric Project. Portage Mountain Development, low level outlet works, manual of interim operation, International Power and Engineering Consultants Limited
Nov 1967
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 22
58 P-137 Portage Mountain Development. Report on Mylonite Shear Tests, Appendix - determination of Roller Friction, International Power and Engineering Consultants Limited
Oct 1967
58 P-138 Portage Mountain Development. Dam Drawings of Foundation Drainage, International Power and Engineering Consultants Limited
Oct 1965
59 P-1 Peace River Hydro-Electric Project, Report, B.C. and B.B. Power Consultants Limited
Dec 1959
59 P-2 Peace River Hydro-Electric Project. Geology, Volume 1, B.C. and B.B. Power Consultants Limited
Dec 1959
59 P-3 Peace River Hydro-Electric Project. Geology, Volume 2, B.C. and B.B. Power Consultants Limited
Dec 1959
59 P-4 Peace River Hydro-Electric Project. Soils Engineering, B.C. and B.B. Power Consultants Limited
Dec 1959
59 P-5 Peace River Hydro-Electric Project. Hydrology, B.C. and B.B. Power Consultants Limited
Dec 1959
59 P-6 Peace River Hydro-Electric Project. Portage Mountain Dam, B.C. and B.B. Power Consultants Limited
Dec 1959
59 P-7 Peace River Hydro-Electric Project. Site 1 Dam, B.C. and B.B. Power Consultants Limited
Dec 1959
59 P-8 Peace River Hydro-Electric Project. Transmission System, B.C. and B.B. Power Consultants Limited
Dec 1959
59 P-9 Power Capabilities and Operating Aspects of a British Columbia Power Pool, R. L. Chantrill and J. D. Stevens
May 1961
59 P-11 Portage Mountain Dam. Fill Placement Quality Control Analysis of Field Tests for Period Aug 11 to Aug 25 1964, International Power and Engineering Consultants Limited
Sep 1964
59 P-12 Portage Mountain Dam. Fill Placement Quality Control Analysis of Field Tests for Period Aug 26 to Sep 17 1964, International Power and Engineering Consultants Limited
28 Sep 1964
59 P-13 Portage Mountain Dam. Fill Placement Quality Control Analysis of Field Tests for Period Sep 29 to Oct 15 1964, International Power and Engineering Consultants Limited
31 Oct 1964
59 P-14 Portage Mountain Dam. Fill Placement Quality Control Analysis of Field Test for Sep 29 to Nov 3 1964, International Power and Engineering Consultants Limited
30 Dec 1964
59 P-15 B.C. Hydro and Power Authority. Peace River Project - Portage Mountain Development Field Progress Reports No. 127 to 122 for week ending 25 Mar 1964 to week ending 29 Apr 1964
59 P-16 Ripley's Reports for Portage Mountain Damsite, Nov 5-6 1963 to Oct 4 1963, Ripley, Klohn, and Keonoff Limited, Consulting Engineers
19 Nov 1963 - 4 Oct 1963
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 23
60 P-17 Map of Peace River Canyon, Area of Soil Investigations, The British Thomson-Houston Company (Canada) Limited
60 P-18 B.C. Hydro and Power Authority. Electric Service Agreements of 3 Jul 1963 and of 25 Oct 1963 between Kiewit-Dawson-Johnson, and B.C. Hydro and Power Authority
60 P-19 Hearings on Peace River Water Licences 2 Aug 1962
60 P-20 Continuation of Hearing on Application of B.C. Hydro and Power Authority for Water Licence on Peace River, Court House, Victoria, B.C.
15 Oct 1962
60 P-21 Peace River Project. Record of Correspondence with Comptroller of Water Rights, B.C., 1960, International Power and Engineering Consultants Limited
Nov 1960
60 P-22 B.C. Hydro and Power Authority. Peace River Hydro-Electric Project - Embankment Control Reports
8 Apr 1965
61 P-26 Preliminary Report on the Earthquake Resistance of Portage Mountain Dam
4 Jul 1960
61 P-27 Supplementary Study of the feasibility and Estimated cost of the Peace River Power Development Company Limited, Transmission System, Shawinigan Engineering Company Limited
2 Nov 1960
61 P-28 Report of Soil Tests on Pervious Gravels, Portage Mountain Dam, Peace River Project, U.S. Corps of Engineers
Jan 1961
61 P-30 The Effect of Regulation of the Peace River, Interim Report No. 1
Jun 1962
61 P-31 Report on Laboratory Direct Shear Tests on Solid Undisturbed Coal Samples - Portage Mountain Dam, R.C. Thurber and Associates Limited
22 Apr 1963
61 P-32 Report on Laboratory Direct Shear Tests and Examination of Particle Structure- Undisturbed Shale/Mylonite Samples - Portage Mountain Dam, R.C. Thurber and Associates Limited
31 Jul 1963
61 P-33 Peace River Development Report on Stage Fluctuation Warning Gauges, International Power and Engineering Consultants Limited
Jun 1962
61 P-34 Fisheries Problems Associated with the Development of the Peace River and its upper Tributaries for Hydro-Electric Purposes, B.C. Department of Recreation and Conservation
Jan 1960
61 P-35 Review of Reports on Peace River Hydro-Electric Project, H.Q. Golder
Feb 1960
61 P-36 Review of Reports on the Geology and Damsites on the Peace River, B.C. Department of Mines
Mar 1960
61 P-37 Peace River Development Company Limited. Site I Dam - Preliminary Report, International Power and Engineering Consultants Limited
Aug 1960
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 24
61 P-38 Peace River Project. Notes for Panel Meeting, G.B. Morris Sep 1963
61 P-39 Notes on Design Panel Meeting - Portage Mountain Development, International Power and Engineering Consultants Limited
Sep 1963
61 P-40 Peace River Hydro-Electric Project. Portage Mountain Development - Interim Report on Reservoir Drawdown and Energy Production, International Power and Engineering Consultants Limited
Jul 1963
61 P-41 Correspondence regarding Peace River Hydro Electric Project
61 P-42 Peace River Hydro-Electric Project. Portage Mountain Dam - Report on Availability of Construction Materials, International Power and Engineering Consultants Limited
21 Dec 1962
61 P-43 Portage Mountain Development. Comments on Plans and Specifications, D.J. Bleifuss
6 May 1963
61 P-44 Preliminary report on Comparison of costs and sequencing of development of Peace and Columbia Rivers, J.B. Hedley and A.W. Lash
13 Jul 1962
61 P-45 Peace River Project Organization Manual, B.C. Hydro and Power Authority
1964
61 P-46 Plans submitted for approval foundation drainage tunnel grouting culvert, International Power and Engineering Consultants Limited
24 Jan 1964
61 P-47 Plans submitted for approval core contact blanket grouting plans, International Power and Engineering Consultants Limited
3 Dec 1964
61 P-48 Portage Mountain Development Dam. Grout Curtain Design Report, International Power and Engineering Consultants Limited
Jan 1964
61 P-49 Peace River Hydro-Electric Project. Portage Mountain Dam - Report on River closure and coffer dam construction model studies, International Power and Engineering Consultants Limited
Sep 1962
62 P-50 Direct Shear Tests on Coal and Mylonite, Ripley, Klohn, and Leonnoff Limited
22 Nov 1963
62 P-51 Peace River Hydro Electric Project. Portage Mountain Development - Study on the necessity of using turbine inlet valves, International Power and Engineering Consultants Limited
Apr 1964
62 P-52 Modification of Upstream Slope in the vicinity of Penstock intakes, International Power and Engineering Consultants Limited
May 1964
62 P-53 Progress Report on Seepage Measurement, International Power and Engineering Consultants Limited
Jun 1964
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 25
62 P-54 Peace River Development Outlet works and Penstocks, Proposals, includes 10 drawings, International Power and Engineering Consultants Limited
19 May 1965
62 P-55 Report on the Main Aspects of Foundation Rock Excavation and Treatment up to May 1964, International Power and Engineering Consultants Limited
May 1964
62 P-56 Panel Report No. 6, Peace River Project, International Power and Engineering Consultants Limited
13 Jun 1964
62 P-57 Progress Report on Hydrometeorology and Underground Hydraulic Works, International Power and Engineering Consultants Limited
Jun 1964
62 P-58 Portage Mountain Dam. Fill placement quality control memorandum on general principles and methods, International Power and Engineering Consultants Limited
Jun 1964
62 P-59 Canada, Department of Transport. Critical Meteorological conditions for maximum inflow, wind set-up, and waves, Portage Mountain Reservoir, Peace River, B.C., J.P. Bruce, T.L. Richards, U. Sporns
6 Nov 1964
62 P-60 Peace River Hydro-Electric Project. Portage Mountain Development - Interim Report on Design Flood and Spillway Capacity, International Power and Engineering Consultants Limited
Dec 1963
62 P-61 Peace River Project. Portage Mountain Dam - Report on Zone 1 and Zone 6 test fill, International Power and Engineering Consultants Limited
Aug 1964
62 P-62 Report on the heating, ventilation, and air conditioning systems for the Portage Dam Power House, Hudson Hope, B.C., Crowther, MacKay, and Associates Limited
Aug 1964
62 P-63 Report on hydraulic Model studies of approach channel and intakes to powerplant, interim report No.1, International Power and Engineering Consultants Limited
Sep 1964
62 P-64 Material to accompany panel report, International Power and Engineering Consultants Limited
Sep 1964
62 P-65 Portage Mountain Dam. Embankment and Foundation Instrumentation Interim Design, International Power and Engineering Consultants Limited
Sep 1964
63 P-66 Third Report on rheostatic problem of the underground penstocks of the Portage Mountain Development, Peace River Project, International Power and Engineering Consultants Limited
1 Sep 1964
63 P-67 Report on Investigation of stability of right abutment, Portage Mountain Dam, International Power and Engineering Consultants Limited
28 Apr 1964
63 P-68 Portage Mountain Dam. Tailrace model, Progress Report No. 1, Lasalle Hydraulic laboratory
24 Sep 1964
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 26
63 P-69 Design Report on Power House and Associated Structures (Panel Session, Sep - Oct 1964), International Power and Engineering Consultants Limited
Dec 1962
63 P-70 Tentative design data, basic construction timing alternative - Portage Mountain Development, International Power and Engineering Consultants Limited
Dec 1962
63 P-71 Report on high pressure laboratory direct shear tests on undisturbed mylonite shale samples form the Portage Mountain Development, R.C. Thurber and Associates Limited
31 Aug 1964
63 P-72 Comments regarding Dr. Golder's mylonite report, V. Dolmage and D.D. Campbell
19 Nov 1964
63 P-73 Portage Mountain Dam. Tailrace Model - Progress Report No. 2, Lasalle Hydraulic Laboratory Limited
Nov 1964
63 P-74 Portage Mountain Dam. Tailrace Model - Progress Report no.3, Lasalle Hydraulic Laboratory Limited
Nov 1964
63 P-75 Portage Mountain Development computed settlement of bedrock, International Power and Engineering Consultants Limited
Jan 1965
63 P-76 Peace River Project. Portage Mountain Dam - Exploratory Drilling at the Portage Mountain Damsite, International Power and Engineering Consultants Limited
8 Feb 1965
63 P-77 Peace River Project. Portage Mountain Dam - Memorandum on effect of frost action of embankment fill, International Power and Engineering Consultants Limited
26 Feb 1965
63 P-78 Portage Mountain Dam. Tailrace Model, Progress Report No. 4, Lasalle Hydraulic Laboratory
Mar 1965
63 P-79 Portage Mountain Dam. Interim Design Report, International Power and Engineering Consultants Limited
Nov 1962
63 P-80 Portage Mountain Development. Discharge capacity of the Portage Mountain Dam Low Level Outlet, International Power and Engineering Consultants Limited
May 1963
63 P-81 Portage Mountain Dam. Progress Report No. 1 on Zone 1 High Pressure Triaxial Tests, R.C. Thurber and Associates
25 Mar 1965
63 P-82 Portage Mountain Dam. Report on Zone 1 High Pressure Triaxial Tests - Laboratory Methods, R.C. Thurber, and Associates
25 Mar 1965
63 P-83 Progress Report No. 2, Zone 1 consolidated drained high pressure triaxial tests, R.C. Thurber and Associates
20 Apr 1965
63 P-84 Portage Mountain Dam. Progress Report No. 3, Zone 1 Consolidated undrained High Pressure Triaxial Tests, R.C. Thurber and Associates
26 May 1965
63 P-85 Portage Mountain Dam. Progress Report No. 4, Zone 1 Consolidated Undrained High Pressure Triaxial Tests, R.C. Thurber and Associates
11 Aug 1965
63 P-86 Panel Report No. 9, Peace River Project 8 Oct 1965
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 27
63 P-87 Portage Mountain Dam. Correspondence and Plans regarding intake structures, embankment designs, and seepage, International Power and Engineering Consultants Limited
1965
63 P-88 Portage Mountain Project. Summary of Information for panel discussion, International Power and Engineering Consultants Limited
14-19 Jun 1965
64 P-89 Portage Mountain Project. Summary of information for panel discussion, International Power and Engineering Consultants Limited
4-8 Oct 1965
64 P-90 Portage Mountain Development. Memorandum on triaxial testing of zones 1 and 6 materials, International Power and Engineering Consultants Limited
6 Dec 1965
64 P-91 Portage Mountain Dam. Report of Triaxial Compression, Test 4-2-5b, Zone 1, Materials, Geo-Testing Incorporated
Oct 1965
64 P-92 Portage Mountain Dam. Report of Triaxial Compression Testing, Zone 6, Materials, Geo-Testing Incorporated
Oct 1965
64 P-93 Portage Mountain Dam. Report of Triaxial compression test 4-1, Zone 4 materials, Geo-Testing Incorporated
Nov 1965
64 P-94 Portage Mountain Dam. Memorandum on Analysis of Fill placement quality control for 1965, International Power and Engineering Consultants Limited
10 Feb 1966
64 P-95 Portage Mountain Project. Review of Water Rights Preliminary Flood Routing Study, International Power and Engineering Consultants Limited
6 Jan 1966
64 P-96 Portage Mountain Project. Memorandum on Seepage Measurements in Portage Pass and Gaylord Saddle, International Power and Engineering Consultants Limited
27 Jul 1965
64 P-97 Portage Mountain Plans Received, International Power and Engineering Consultants Limited
2 Feb 1966
64 P-98 Portage Mountain Project. Summary of information for panel meeting No. 10
28 Feb 1966 - 4 Mar 1966
64 P-114 Derivation of maximum probable flood : Portage Mountain project, Peace River, British Columbia / David M. Rockwood
Jun 1965
64 P-115 Report on review of spillway design flood derivations for Portage Mountain Dam, F.F. Snyder
11 Jun 1965
65 P-116 Peace River Hydro-Electric Project. Contract No. 10 with Kiewit-Johnson-Dawson for Portage Mountain Dam (Contract Documents. Volumes 1 and 2, Supplemental Contract A and B), International Power and Engineering Consultants Limited
3 May 1963
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 28
66 P-117 Peace River Hydro-Electric Project. Contract with Kiewit-Dawson-Johnson, a joint venture for Portage Mountain Dam, Grout Curtain - Sub-contract Tender documents, Volumes 1 and 2, addendum No. 1, International Power and Engineering Consultants Limited
27 Feb 1964, 31 Mar 1964
66 P-118 Peace River Hydro-Electric Project. Contract No. 22, Portage Mountain Development, Turbines and Governors - Tender Documents, Volumes 1 and 2 and Addenda, International Power and Engineering Consultants Limited
7 Jul 1964
67 P-119 Peace River Hydro-Electric Project. Contract No. 23, Portage Mountain Development, Generators and Excitors - Tender Documents. Volumes 1 and 2, and Addenda, International Power and Engineering Consultants Limited
1 Sep 1964
68 P-120 Peace River Hydro-Electric Project. Contract No. 25, Portage Mountain Development, Power Plant - Tender Documents, Volumes 1 to 4 and Addenda, International Power and Engineering Consultants Limited
Jan 1965
68 P-121 Peace River Hydro-Electric Project. Portage Mountain Development. Construction Stage Ventilation Specification No. PR-2, International Power and Engineering Consultants Limited and Dolmage Mason and Steward Limited
12 Feb 1965
68 P-122 Peace River Hydro-Electric Project. Contract No. 26, Portage Mountain Development, Powerhouse Access. Tunnel - Tender Document, Volumes 1 and 2, and Addenda, International Power and Engineering Consultants Limited
27 Jul 1964
68 P-123 Peace River Hydro-Electric Project. Peace Transmission Line No. 1, Contract No. 33 Construction, Sections 3 and 4 Tender Documents, Volumes 1 and 2, International Power and Engineering Consultants Limited
4 Jan 1965
69 P-124 Peace River Hydro-Electric Project. Contract No. 39 with Kiewit-Dawson-Johnson for Portage Mountain Development - Spillway and Low Level outlets, Volumes 1 to 3 and Addenda, International Power and Engineering Consultants Limited
28 Jun 1966
70 P-126 Peace River Hydro-Electric Project. Portage Mountain Development, Contract No. 82 - Spillway Radial Gates and Hoists, Tender Documents, International Power and Engineering Consultants Limited
25 Jul 1966
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 29
70 P-127 Peace River Hydro-Electric Project. Portage Mountain Development, Contract No. 83 - Spillway Slide Gates, Tender Documents, International Power and Engineering Consultants Limited
1 Jun 1966 (Revision No. 1, 10 Jun 1966)
70 P-128 Peace River Hydro-Electric Project. Contract No. 87 with Mitsui and Company Limited for Portage Mountain Development - Ring-Follower Gates, Tender Documents, International Power and Engineering Consultants Limited
14 Apr 1966
70 P-129 Peace River Hydro-Electric Project. Portage Mountain Development, Contract No. 88, Hollow Cone Valves, Tender Documents, International Power and Engineering Consultants Limited
14 Apr 1966
70 P-130 Peace River Hydro-Electric Project. Contract No. 71 with the Foundation Company of Canada Limited and Canadian Comstock Company Limited for Portage Mountain Development - Central Control Building, Switchyard and Power plant completion, Volumes 1 to 5, International Power and Engineering Consultants Limited
23 Dec 1966
71 P-109 Memorandum on Supplementary Stability Analyses for Upstream Slope, Portage Mountain Development, International Power and Engineering Consultants Limited
26 Jan 1967
71 P-110 Memorandum on Zone 6 Material, Low Pressure Triaxial Tests, International Power and Engineering Consultants Limited
23 Mar 1967
71 P-111 Report on Portage Mountain Development, Zone 6 Material Conventional and Cyclic Loading Triaxial Tests, R.C. Thurber and Associates Limited
28 Feb 1967
71 P-112 Peace River Hydro-Electric Project. Portage Mountain Dam - Report on Hydraulic Model Studies of Spillway and Approach Channel, Western Canada Hydraulic Laboratories Limited
Dec 1966
71 P-113 Memorandum on Proposed Modification to Dam Crest, International Power and Engineering Consultants Limited
22 Apr 1965
72 P-99 Portage Mountain Project. Summary of Information for Panel Meeting No 10, Supplement, International Power and Engineering Consultants Limited
25 Feb 1966 - 4 Mar 1966
72 P-100 Portage Mountain Dam. Report of Committees on Influence of Mylonite Seams in Right Abutment, International Power and Engineering Consultants Limited
21 Feb 1966
72 P-101 Portage Mountain Conveyor System, Conference Pre-print 376, American Society of Civil Engineers
16-20 May 1966
72 P-102 Report on Portage Mountain Dam Zone 6 - Sand Consolidated Drained Triaxial Tests 6-D-1 and 6-D-2, R.C. Thurber and Associates Limited
4 Jul 1966
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 30
72 P-103 Portage Mountain Project. Summary of Information for Panel Meeting No. 11, International Power and Engineering Consultants Limited
12-16 Sep 1966
72 P-104 Hydraulic Model Studies of Portage Mountain Development Low-Level Outlet Works, B.C., Canada, U.S. Department of the Interior, Bureau of Reclamation
30 Jun 1966
72 P-105 Portage Mountain Dam. Influence of Mylonite Seams, Supplementary Notes, N3 Mylonite, International Power and Engineering Consultants Limited
3 Nov 1966
72 P-106 Portage Mountain Dam. Notes on Supplementary Stability Analysis of Right Abutment N3 Mylonite, International Power and Engineering Consultants Limited
14 Nov 1966
72 P-107 Memorandum concerning Review by H.W. Colder of Report of Mylonite Committee
16 Oct 1966
72 P-108 Portage Mountain Development. Survey - Plans of Embankments, Stability Analysis, International Power and Engineering Consultants Limited
1966
73 A-90 B.C. Hydro and Power Authority. Arrow Lakes Dam, 121 Drawings describing the performance of the dam since completion
29 Sep 1969
73 A-91 B.C. Hydro and Power Authority. Arrow Lakes Dam - Piezometer readings, drainage readings, settlement and alignment points for the year 1969
Feb 1970
74 A-57 B.C. Hydro and Power Authority. Arrow Project - Construction of Arrow Dam, specification No. CA-1 and Addenda, Volumes 1-5, B.C. A. Engineering Limited
16 Oct 1964
75 A-76 Arrow Lakes Dam. Earthworks Information Presented at the Board of Review Meeting
12 May 1966
76 D-58 B.C. Hydro and Power Authority. Duncan Lake Project - "As Constructed" Drawings
Apr 1968
77 K-10 B.C. Hydro and Power Authority. Kootenay Canal Development - Contract No. KC7 Canal, Tender Documents, 3 volumes (Volume 3 only)
Feb 1972
78 Various Portage Mountain plans and tender documents 1966
79 Various Portage Mountain plans and tender documents 1966
80 Various Portage Mountain plans and tender documents 1966
81 Various Portage Mountain plans and tender documents 1966
GR-0880 Power and Special Projects files 1949-1976 G:\RSD\@ORCS09\13050.20\GR-0880.DOC:2013/05/22 page 31
82 Various Portage Mountain plans and tender documents 1966
83 Various Portage Mountain plans and tender documents 1966
84 Various Portage Mountain plans and tender documents 1966
85 Various Portage Mountain plans and tender documents 1966
86 J-7 B.C. Hydro and Power Authority. Jordan River Redevelopment. Contract JR-4 Power Plant and Elliott Dam Contract Documents (Part B only, for part A, see volume 87)
29 Jul 1969
Additional reports on Jordan River redevelopment project
87 J-6 B.C. Hydro and Power Authority. Jordan River Redevelopment - Contract No. JR-3 with Nissho-Iwai Company Limited for Turbine and Governor
18 Dec 1968
87 J-7 B.C. Hydro and Power Authority. Jordan River Redevelopment - Contract JR-4 Powerplant and Elliott Dam Contract Documents, 2 volumes (Part A only, for part B, see volume 86)
29 Jul 1969
87 J-8 B.C. Hydro and Power Authority. Jordan River Redevelopment - Contract No. JR-5 with Mitsubishi Canada Limited - Generator
10 Mar 1969
88 Catalogue cards, author and title index. List of reports that were submitted to or collected by Water Management Branch, but that were not included in GR-0880