90% Design K115 UNIT PRICE DESCRIPTIONS
Page 1 of 18
ITEM NUMBER: MWH – 001
DESCRIPTION: Bid Item 4 - Rock Excavation with Blasting – Channel 1
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER
SPECIFIC REQUIREMENTS: Rock excavation requiring blasting as defined in Section 31 23 16 (K082-C2-CS-10-064) to construct channel 1.
Includes:
Excavation Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
ITEM NUMBER: MWH – 002
DESCRIPTION: Bid Item 5 – Rippable Rock Excavation – Channel 1
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER Rock stabilization measures (rockbolts, shotcrete, etc.)
necessary as a result of CONTRACTOR excavation methods/processes
SPECIFIC REQUIREMENTS: Rippable rock excavations as defined in Section 31 23 16 (K082-C2-CS-10-064) to construct channel 1.
Includes:
Excavation/Ripping Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
![Page 2: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/2.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 2 of 18
ITEM NUMBER: MWH – 003
DESCRIPTION: Bid Item 6 - Unclassified Excavation – Channel 1
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER
SPECIFIC REQUIREMENTS: Unclassified (materials not classified as rock) excavations to construct channel 1.
Includes:
Excavation Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
ITEM NUMBER: MWH – 004
DESCRIPTION: Bid Item 7 – Type I Rockfill – Channel 1
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: Dewatering Borrow Areas (incidental to this item)
SPECIFIC REQUIREMENTS: This Item includes all work required to install Type I Rockfill Material to construct Channel 1. Work in accordance with specification 240K-C2-CS-10-001.
Includes:
Excavation Processing Placing Spreading Grading Handling/Rehandling Loading/Hauling to Disposal Areas Restoring Borrow Areas Construction Water Compacting
Measurement for payment will be made in cubic meters in-place of Type I Rockfill – Channel 1 Material which has been placed and compacted to the neat lines and grades shown on the Drawings.
![Page 3: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/3.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 3 of 18
ITEM NUMBER: MWH – 005
DESCRIPTION: Bid Item 8 – Type II Common Fill – Channel 1
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: Dewatering Borrow Areas (incidental to this item)
SPECIFIC REQUIREMENTS: This Item includes all work required to install Type II Common Fill Material to construct Channel 1. Work in accordance with specification 240K-C2-CS-10-001.
Includes:
Excavation Processing Placing Spreading Grading Handling/Rehandling Loading/Hauling to Disposal Areas Restoring Borrow Areas Construction Water Compacting
Measurement for payment will be made in cubic meters in-place of Type II Common Fill Material which has been placed and compacted to the neat lines and grades shown on the Drawings.
ITEM NUMBER: MWH – 006
DESCRIPTION: Bid Item 9 – Type III Select Fill – Channel 1
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: Dewatering Borrow Areas (incidental to this item)
SPECIFIC REQUIREMENTS: This Item includes all work required to install Type III Select Fill Material to construct Channel 1. Work in accordance with specification 240K-C2-CS-10-001.
Includes:
Excavation Processing Placing Spreading Grading Handling/Rehandling Loading/Hauling to Disposal Areas Restoring Borrow Areas Construction Water Compacting
Measurement for payment will be made in cubic meters in-place of Type III Select Fill Material which has been placed and compacted to the neat lines and grades shown on the Drawings.
![Page 4: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/4.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 4 of 18
ITEM NUMBER: MWH – 007
DESCRIPTION: Bid Item 10 - Rock Excavation with Blasting – Channel 2
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER
SPECIFIC REQUIREMENTS: Rock excavation requiring blasting as defined in Section 31 23 16 (K082-C2-CS-10-064) to construct channel 2.
Includes:
Excavation Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
ITEM NUMBER: MWH – 008
DESCRIPTION: Bid Item 11 – Rippable Rock Excavation – Channel 2
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER Rock stabilization measures (rockbolts, shotcrete, etc.)
necessary as a result of CONTRACTOR excavation methods/processes
SPECIFIC REQUIREMENTS: Rippable rock excavations as defined in Section 31 23 16 (K082-C2-CS-10-064) to construct channel 2.
Includes:
Excavation/Ripping Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
![Page 5: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/5.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 5 of 18
ITEM NUMBER: MWH – 009
DESCRIPTION: Bid Item 12 - Unclassified Excavation – Channel 2
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER
SPECIFIC REQUIREMENTS: Unclassified (materials not classified as rock) excavations to construct channel 2.
Includes:
Excavation Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
ITEM NUMBER: MWH – 010
DESCRIPTION: Bid Item 13 - Rock Excavation with Blasting – Channel 3
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER
SPECIFIC REQUIREMENTS: Rock excavation requiring blasting as defined in Section 31 23 16 (K082-C2-CS-10-064) to construct channel 3.
Includes:
Excavation Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
![Page 6: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/6.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 6 of 18
ITEM NUMBER: MWH – 011
DESCRIPTION: Bid Item 14 – Rippable Rock Excavation – Channel 3
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER Rock stabilization measures (rockbolts, shotcrete, etc.)
necessary as a result of CONTRACTOR excavation methods/processes
SPECIFIC REQUIREMENTS: Rippable rock excavations as defined in Section 31 23 16 (K082-C2-CS-10-064) to construct channel 3.
Includes:
Excavation/Ripping Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
ITEM NUMBER: MWH – 012
DESCRIPTION: Bid Item 15 - Unclassified Excavation – Channel 3
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER
SPECIFIC REQUIREMENTS: Unclassified (materials not classified as rock) excavations to construct channel 3.
Includes:
Excavation Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
![Page 7: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/7.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 7 of 18
ITEM NUMBER: MWH – 013
DESCRIPTION: Bid Item 16 – Riprap – Channel 3
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: N/A
SPECIFIC REQUIREMENTS: This Item includes all work required to install Riprap through areas of colluvium foundation materials in Channel 3.
Includes:
Processing of on-site excavated rock Hauling form stockpiles Placing Spreading Compacting Grading
Measurement for payment will be made in cubic meters in-place of riprap which has been placed and compacted to the neat lines and grades shown on the Drawings.
ITEM NUMBER: MWH – 014
DESCRIPTION: Bid Item 17 – Filter A – Channel 3
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: Dewatering Borrow Areas (incidental to this item)
SPECIFIC REQUIREMENTS: This Item includes all work required to install Filter A Material to construct riprap bedding through areas of colluvium foundation materials in Channel 3.
Includes:
Excavation Processing Washing Loading/Hauling Placing Spreading Grading Stockpiling Handling/Rehandling Disposal of Waste materials Restoration of Borrow Areas Construction Water Compaction
Measurement for payment will be made in cubic meters in-place of Filter A Material which has been placed and compacted to the neat lines and grades shown on the Drawings.
![Page 8: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/8.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 8 of 18
ITEM NUMBER: MWH – 015
DESCRIPTION: Bid Item 18 - Geotextile – Channel 3
UNIT OF MEASUREMENT: Square Meters (M2) (of Placed Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: Overlap of adjacent geotextile sheets On-Site Storage
SPECIFIC REQUIREMENTS: Geotextile includes: Furnishing Geotextile Handling Installation
The measurement for payment will be made in square meter of geotextile in-place according to the lines and grades shown on the Drawings and meeting the requirements of the specifications.
ITEM NUMBER: MWH – 016
DESCRIPTION: Bid Item 19 - Rock Excavation with Blasting – Embankment
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER
SPECIFIC REQUIREMENTS: Rock excavation requiring blasting as defined in Section 31 23 16 (K082-C2-CS-10-064) to construct the Seepage Corridor Embankment.
Includes:
Excavation Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
![Page 9: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/9.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 9 of 18
ITEM NUMBER: MWH – 017
DESCRIPTION: Bid Item 20 – Rippable Rock Excavation – Embankment
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER Rock stabilization measures (rockbolts, shotcrete, etc.)
necessary as a result of CONTRACTOR excavation methods/processes
SPECIFIC REQUIREMENTS: Rippable rock excavations as defined in Section 31 23 16 (K082-C2-CS-10-064) to construct the Seepage Corridor Embankment.
Includes:
Excavation/Ripping Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
ITEM NUMBER: MWH – 018
DESCRIPTION: Bid Item 21 - Unclassified Excavation – Embankment
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER
SPECIFIC REQUIREMENTS: Unclassified (materials not classified as rock) excavations to construct the Seepage Corridor Embankment.
Includes:
Excavation Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
![Page 10: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/10.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 10 of 18
ITEM NUMBER: MWH – 019
DESCRIPTION: Bid Item 22 - Foundation Preparation – Embankment
UNIT OF MEASUREMENT: Square Meters (M2)
BASIS OF MEASUREMENT: Surveys performed after excavation
UNMEASURED ITEMS: N/A
SPECIFIC REQUIREMENTS: Foundation preparation of the embankment includes:
Cleaning foundation area Grading surfaces Removal of spoil materials Proof Rolling Foundation Treatment (Dental Concrete, Slush Grouting
and/or Stitch Grouting)
Measurement for payment will be in square meters of foundation area acceptably prepared and graded as shown on the drawings and described in the technical specifications.
ITEM NUMBER: MWH – 020
DESCRIPTION: Bid Item 23 - Zone 1 Rockfill – Embankment
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: N/A
SPECIFIC REQUIREMENTS: This Item includes work required to install Zone 1 Rockfill to produce and construct the Seepage Corridor Embankment.
Includes:
Processing of excavated material Washing as necessary Loading/Hauling Placing Spreading Grading Stockpiling Handling/Rehandling Construction Water Compacting
Measurement for payment will be made in cubic meters in-place of Zone 1 Rockfill which has been placed and compacted to the neat lines and grades shown on the Drawings.
![Page 11: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/11.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 11 of 18
ITEM NUMBER: MWH – 021
DESCRIPTION: Bid Item 24 - Zone 5 Fine Transition - Embankment
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: N/A
SPECIFIC REQUIREMENTS: This Item includes all work required to install Zone 5 Fine Transition Material to construct the Seepage Corridor Embankment.
Includes:
Loading/Hauling Placing Spreading Grading Stockpiling Handling/Rehandling Construction Water Compacting
Measurement for payment will be made in cubic meters in-place of Zone 5 Fine Transition which has been placed and compacted to the neat lines and grades shown on the Drawings.
ITEM NUMBER: MWH – 022
DESCRIPTION: Bid Item 25 - Zone 6 Coarse Transition - Embankment
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: N/A
SPECIFIC REQUIREMENTS: This Item includes all work required to install Zone 6 Coarse Transition Material to construct the Seepage Corridor Embankment.
Includes:
Loading/Hauling Placing Spreading Grading Stockpiling Handling/Rehandling Construction Water Compacting
Measurement for payment will be made in cubic meters in-place of Zone 6 Coarse Transition which has been placed and compacted to the neat lines and grades shown on the Drawings.
![Page 12: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/12.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 12 of 18
ITEM NUMBER: MWH – 023
DESCRIPTION: Bid Item 26 – Zone 7 Select Core - Embankment
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: N/A
SPECIFIC REQUIREMENTS: This Item includes all work required to install Zone 7 Select Core Material to construct the Seepage Corridor Embankment.
Includes:
Moisture Conditioning Loading/Hauling Placing Spreading Construction Water Compacting/Special Compaction
Measurement for payment will be made in cubic meters of the Zone 7 material acceptably placed to the lines and grades shown on the Drawings.
ITEM NUMBER: MWH – 024
DESCRIPTION: Bid Item 27 – Type II Common Fill – Embankment
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: Dewatering Borrow Areas (incidental to this item)
SPECIFIC REQUIREMENTS: This Item includes all work required to install Type II Common Fill Material to construct the Seepage Corridor Embankment. Work in accordance with specification 240K-C2-CS-10-001.
Includes:
Excavation Processing Placing Spreading Grading Handling/Rehandling Loading/Hauling to Disposal Areas Restoring Borrow Areas Construction Water Compacting
Measurement for payment will be made in cubic meters in-place of Type II Common Fill Material which has been placed and compacted to the neat lines and grades shown on the Drawings.
![Page 13: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/13.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 13 of 18
ITEM NUMBER: MWH – 025
DESCRIPTION: Bid Item 28 – Type III Select Fill – Embankment
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed, Compacted Material)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: Dewatering Borrow Areas (incidental to this item)
SPECIFIC REQUIREMENTS: This Item includes all work required to install Type III Select Fill Material to construct the Seepage Corridor Embankment. Work in accordance with specification 240K-C2-CS-10-001.
Includes:
Excavation Processing Placing Spreading Grading Handling/Rehandling Loading/Hauling to Disposal Areas Restoring Borrow Areas Construction Water Compacting
Measurement for payment will be made in cubic meters in-place of Type III Select Fill Material which has been placed and compacted to the neat lines and grades shown on the Drawings.
![Page 14: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/14.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 14 of 18
ITEM NUMBER: MWH – 026
DESCRIPTION: Bid Item 29 - Structural Concrete – Low Level Inlet Structure
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed Concrete)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: Dewatering Borrow Areas (incidental to this item)
SPECIFIC REQUIREMENTS: Structural Concrete – Low Level Inlet Structure includes: Form work Placing Concrete Vibrating Concrete Finishing/Curing Concrete Procuring Reinforcing Steel Transporting Reinforcing Steel Installing Reinforcing Steel Procuring Foundation Anchors Transporting Foundation Anchors Installing Foundation Anchors Procuring Waterstop Transporting Waterstop Installing Waterstop Joint Preparation Work Placing Leveling Concrete as Directed by the ENGINEER
Measurement for payment will be made in cubic meters in-place of concrete which has been placed to the neat lines and grades shown on the Drawings.
![Page 15: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/15.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 15 of 18
ITEM NUMBER: MWH – 026.1
DESCRIPTION: Bid Item 29.1 - Structural Concrete – Inlet Riser Section (Optional)
UNIT OF MEASUREMENT: Each (EA) (constructed Inlet Riser Section)
BASIS OF MEASUREMENT: Construction Drawings
UNMEASURED ITEMS: N/A
SPECIFIC REQUIREMENTS: Structural Concrete – Inlet Riser Section includes: Form work Placing Concrete Vibrating Concrete Finishing/Curing Concrete Procuring Reinforcing Steel Transporting Reinforcing Steel Installing Reinforcing Steel Procuring Foundation Anchors Transporting Foundation Anchors Installing Foundation Anchors Procuring Waterstop Transporting Waterstop Installing Waterstop Joint Preparation Work Placing Leveling Concrete as Directed by the ENGINEER
Measurement for payment will be made for each inlet riser section, which has been constructed as shown on the drawings and as approved by the ENGINEER.
ITEM NUMBER: MWH – 027
DESCRIPTION: Bid Item 30 – Outlet Conduit
UNIT OF MEASUREMENT: Linear Meter (LM) (of installed Pipe)
BASIS OF MEASUREMENT: Construction Drawings
UNMEASURED ITEMS: The Cleanout Assembly as shown in the Drawings
SPECIFIC REQUIREMENTS: Outlet Conduit includes: Installing 24-Inch Steel Pipe
Measurement for payment will be made per linear meter of Steel pipe installed to the lines and grades shown on the drawings.
![Page 16: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/16.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 16 of 18
ITEM NUMBER: MWH – 028
DESCRIPTION: Bid Item 31 - Structural Concrete – Conduit Encasement
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed Concrete)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: Concrete Anchor block for Cleanout Assembly
SPECIFIC REQUIREMENTS: Structure Concrete – Conduit Encasement includes: Form work Placing Concrete Vibrating Concrete Finishing/Curing Concrete Procuring Reinforcing Steel Transporting Reinforcing Steel Installing Reinforcing Steel Procuring Foundation Anchors Transporting Foundation Anchors Installing Foundation Anchors Procuring Waterstop Transporting Waterstop Installing Waterstop Joint Preparation Work Placing Leveling Concrete as Directed by the ENGINEER Includes Anchor Block for Cleanout Assembly
Measurement for payment will be made in cubic meters in-place of concrete which has been placed to the neat lines and grades shown on the Drawings.
ITEM NUMBER: MWH – 029
DESCRIPTION: Bid Item 32 – Vent Pipe
UNIT OF MEASUREMENT: Linear Meter (LM) (of installed Pipe)
BASIS OF MEASUREMENT: Construction Drawings
UNMEASURED ITEMS: Concrete Encasement for the upstream vent pipe All Pipe Supports necessary for the downstream vent pipe
installation Anchors
SPECIFIC REQUIREMENTS: Vent Pipe includes: Installing 6-Inch Steel Pipe
Measurement for payment will be made per linear meter of Steel pipe installed to the lines and grades shown on the drawings.
![Page 17: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/17.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 17 of 18
ITEM NUMBER: MWH – 030
DESCRIPTION: Bid Item 33 – Embankment Outlet Pipe - HDPE SDR 9
UNIT OF MEASUREMENT: Linear Meter (LM) (of installed Pipe)
BASIS OF MEASUREMENT: Construction Drawings
UNMEASURED ITEMS: N/A
SPECIFIC REQUIREMENTS: Embankment Outlet Pipe – HDPE SDR 9 includes: Installing HDPE SDR 9 Pipe
Measurement for payment will be made per linear meter of HDPE SDR 9 pipe installed to the lines and grades shown on the drawings.
ITEM NUMBER: MWH – 031
DESCRIPTION: Bid Item 34 – Embankment Outlet Pipe - HDPE SDR 17
UNIT OF MEASUREMENT: Linear Meter (LM) (of installed Pipe)
BASIS OF MEASUREMENT: Construction Drawings
UNMEASURED ITEMS: N/A
SPECIFIC REQUIREMENTS: Embankment Outlet Pipe – HDPE SDR 17 includes: Installing HDPE SDR 17 Pipe
Measurement for payment will be made per linear meter of HDPE SDR 17 pipe installed to the lines and grades shown on the drawings.
ITEM NUMBER: MWH – 032
DESCRIPTION: Bid Item 35 - Unclassified Excavation – Embankment Outlet Pipe
UNIT OF MEASUREMENT: Cubic Meters (M3) (in-situ)
BASIS OF MEASUREMENT: Surveys performed before and after excavation
UNMEASURED ITEMS: Clearing and Grubbing (considered incidental to this item) Excavation below the excavation contours shown in the
Drawings or beyond limits prescribed by the ENGINEER
SPECIFIC REQUIREMENTS: Unclassified (materials not classified as rock) excavations to construct the Embankment Outlet Pipe.
Includes:
Excavation Loading/Hauling Handling/Rehandling Stockpiling Loading/Hauling to Disposal Areas
Measurement for payment will be made in-place to the lines and grades shown on the Drawings, or when lines and grades are not shown on the Drawings or described in the Specifications, will be as prescribed by the ENGINEER and shall include only material that is actually removed within the prescribed pay lines.
ITEM NUMBER: MWH – 033
![Page 18: 90% k115_unit Price Descriptions_mwh](https://reader038.vdocuments.mx/reader038/viewer/2022100501/55cf9484550346f57ba28543/html5/thumbnails/18.jpg)
90% Design K115 UNIT PRICE DESCRIPTIONS
Page 18 of 18
DESCRIPTION: Bid Item 36 - Structural Concrete – Spillway
UNIT OF MEASUREMENT: Cubic Meters (M3) (of Placed Concrete)
BASIS OF MEASUREMENT: Surveys performed before and after placement
UNMEASURED ITEMS: N/A
SPECIFIC REQUIREMENTS: Structural Concrete - Spillway includes: Form work Placing Concrete Vibrating Concrete Finishing/Curing Concrete Procuring Reinforcing Steel Transporting Reinforcing Steel Installing Reinforcing Steel Procuring Foundation Anchors Transporting Foundation Anchors Installing Foundation Anchors Procuring Waterstop Transporting Waterstop Installing Waterstop Joint Preparation Work Placing Leveling Concrete as Directed by the ENGINEER Foundation Preparation
Measurement for payment will be made in cubic meters in-place of concrete which has been placed to the neat lines and grades shown on the Drawings.