OFFICE OF CHIEF ENGINEER (CENTRE) COMMUNICATION & WORKS DEPARTMENT KHYBER PAKHTUNKHWA PESHAWAR 1-Police Road Peshawar 091-9211225 FAX 091-9210852 85 Dated:TOi / 2018 No.CEC/GSP/8-6/ The Executive Engineer, C&W Division Charsadda. Subject: TECHNICAL QUALIFICATION OF CONTRACTORS/FIRMS (ON SINGLE STAGE-TWO ENVELOP PROCEDURE). Reference: SE C&W Circle Peshawar letter No. 773/7-SE dated 18-01-2018. As recommended by the Procurement Committee and forwarded vide Superintending Engineer C&W Circle Peshawar letter quoted under reference, the following firms/contractors for the following works are hereby technically approved: SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 856/170357 SUB ADP NO. 428 (PK-20). SH: B/T OF ROAD FROM MAIN TANGI MARDAN TO TOR KHAT U/C BEHRAM DHERI AND ROAD IN U/C GHANDERI DISTRICT CHARSADDA (02-KM). SI No. Name of Contractor SI No. Name of Contractor 1. Abdul Kabir Construction Co. 4. Syed Fazle Hakeem Bacha Shah Jehan Ahmad 2. lmza Construction 5. 3. Horizon 6. Bakhtaj Ud Din & Co. SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 856/170357 SUB ADP NO. 429 (PK-20). SH: RECONSTRUCTION OF ROAD FROM HARICHAND TO SUR KAMAR DISTRICT CHARSADDA (03-KM). SI No. Name of Contractor SI No. Name of Contractor 1. Imza Construction 3. Dawood Construction Pvt. Ltd. 2. Shah Jehan Ahmad 4. Bakhtaj Ud Din & Co. SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 857/170358 SUB ADP NO. 318 (PK-20). SH: IMPROVEMENT & BLACK TOPPING OF ROAD FROM CHAIL TO SULTAN MASTER KILLI AND ROAD IN U/C HISARA NEHARI DISTRICT CHARSADDA. SI No. Name of Contractor SI No. Name of Contractor 1. Hasht Nagar Construction Co. 3. Shah Jehan Ahmad 2. lmza Construction 4. Bakhtaj Ud Din & Co. SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 857/170358 SUB ADP NO. 319 (PK-20). SH: RECONSTRUCTION AND BLACK TOPPING OF ROAD FROM HISARA TO SHAH AFZAL KILLI AND ROAD IN U/C MANDANI DISTRICT CHARSADDA. SI No. Name of Contractor SI No. Name of Contractor 1. Farhad Ali & Sons 4. Dawood Construction Pvt. Ltd. 2. Muhammad Tariq 5. Bakhtaj Ud Din & Co. 3. Shah Jehan Ahmad SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 857/170358 SUB ADP NO. 320 (PK-20). SH: CONSTRUCTION OF ROAD FROM DHAKI BAZAR TO SAHIB GUL MAHAL ROAD TO ARIZI FROM REDWAN TO KHORABAD GUL FARAZ TO SURGHAN U/C DHAKKI DISTRICT CHARSADDA. SI No. Name of Contractor SI No. Name of Contractor 1. Habibullah Khan & Brothers 3. Shah Jehan Ahmad 2. lmza Construction Co. 4. Bakhtaj Ud Din & Co. SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 856/170357 SUB ADP NO. 426 (PK-17). SH: CONSTRUCTION/REHABILITATION OF ROAD FROM KALYAS TO BOOBAK (2.5-KM) DISTRICT CHARSADDA. SI No. Name of Contractor SI No. Name of Contractor 1. Nasrullah Khan & Co. 4. Shah Jehan Ahmad 2. Zakir Ullah Construction Co. 5. Wajid All 3. Farukh Engineering Co. 6. Bakhtaj Ud Din & Co. SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 857/170358 SUB ADP NO. 315 (PK-17 ) SH: CONSTRUCTION/REHABILITATION OF ROAD FROM NOWSHERA TO TALAOW KOROONA VIA SHAHID ABAD U/C DHERI ZARDAD DISTRICT CHARSADDA. SI No. Name of Contractor SI No. Name of Contractor 1. Nasrullah Khan & Co. 4. Horizon 2. Shah Jehan Ahmad 5. Bakhtaj Ud Din & Co. 3. Friends Engineering Services 6. Anwar Ali Khan Continue on Page-2

Upload: others

Post on 05-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 85 - cwd.gkp.pk · TO KHORABAD GUL FARAZ TO SURGHAN U/C DHAKKI DISTRICT CHARSADDA. SI No. Name of Contractor SI No. Name of Contractor 1. Habibullah Khan & Brothers 3. Shah Jehan

OFFICE OF CHIEF ENGINEER (CENTRE) COMMUNICATION & WORKS DEPARTMENT

KHYBER PAKHTUNKHWA PESHAWAR 1-Police Road Peshawar

091-9211225 FAX 091-9210852

85

Dated:TOi / 2018 No.CEC/GSP/8-6/

The Executive Engineer, C&W Division Charsadda.

Subject: TECHNICAL QUALIFICATION OF CONTRACTORS/FIRMS (ON SINGLE STAGE-TWO ENVELOP PROCEDURE).

Reference: SE C&W Circle Peshawar letter No. 773/7-SE dated 18-01-2018.

As recommended by the Procurement Committee and forwarded vide Superintending Engineer C&W Circle Peshawar letter quoted under reference, the following firms/contractors for the following works are hereby technically approved:

SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 856/170357 SUB ADP NO. 428 (PK-20). SH: B/T OF ROAD FROM MAIN TANGI MARDAN TO TOR KHAT U/C BEHRAM DHERI AND ROAD IN U/C GHANDERI DISTRICT CHARSADDA (02-KM).

SI No. Name of Contractor SI No. Name of Contractor 1. Abdul Kabir Construction Co. 4. Syed Fazle Hakeem Bacha

Shah Jehan Ahmad 2. lmza Construction 5. 3. Horizon 6. Bakhtaj Ud Din & Co.

SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 856/170357 SUB ADP NO. 429 (PK-20). SH: RECONSTRUCTION OF ROAD FROM HARICHAND TO SUR KAMAR DISTRICT CHARSADDA (03-KM).

SI No. Name of Contractor SI No. Name of Contractor 1. Imza Construction 3. Dawood Construction Pvt. Ltd. 2. Shah Jehan Ahmad 4. Bakhtaj Ud Din & Co.

SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 857/170358 SUB ADP NO. 318 (PK-20). SH: IMPROVEMENT & BLACK TOPPING OF ROAD FROM CHAIL TO SULTAN MASTER KILLI AND ROAD IN U/C HISARA NEHARI DISTRICT CHARSADDA.

SI No. Name of Contractor SI No. Name of Contractor 1. Hasht Nagar Construction Co. 3. Shah Jehan Ahmad 2. lmza Construction 4. Bakhtaj Ud Din & Co.

SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 857/170358 SUB ADP NO. 319 (PK-20). SH: RECONSTRUCTION AND BLACK TOPPING OF ROAD FROM HISARA TO SHAH AFZAL KILLI AND ROAD IN U/C MANDANI DISTRICT CHARSADDA.

SI No. Name of Contractor SI No. Name of Contractor 1. Farhad Ali & Sons 4. Dawood Construction Pvt. Ltd. 2. Muhammad Tariq 5. Bakhtaj Ud Din & Co. 3. Shah Jehan Ahmad

SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 857/170358 SUB ADP NO. 320 (PK-20). SH: CONSTRUCTION OF ROAD FROM DHAKI BAZAR TO SAHIB GUL MAHAL ROAD TO ARIZI FROM REDWAN TO KHORABAD GUL FARAZ TO SURGHAN U/C DHAKKI DISTRICT CHARSADDA.

SI No. Name of Contractor SI No. Name of Contractor 1. Habibullah Khan & Brothers 3. Shah Jehan Ahmad 2. lmza Construction Co. 4. Bakhtaj Ud Din & Co.

SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 856/170357 SUB ADP NO. 426 (PK-17). SH: CONSTRUCTION/REHABILITATION OF ROAD FROM KALYAS TO BOOBAK (2.5-KM) DISTRICT CHARSADDA.

SI No. Name of Contractor SI No. Name of Contractor 1. Nasrullah Khan & Co. 4. Shah Jehan Ahmad

2. Zakir Ullah Construction Co. 5. Wajid All

3. Farukh Engineering Co. 6. Bakhtaj Ud Din & Co.

SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 857/170358 SUB ADP NO. 315 (PK-17) SH: CONSTRUCTION/REHABILITATION OF ROAD FROM NOWSHERA TO TALAOW KOROONA VIA SHAHID ABAD U/C DHERI ZARDAD DISTRICT CHARSADDA.

SI No. Name of Contractor SI No. Name of Contractor 1. Nasrullah Khan & Co. 4. Horizon 2. Shah Jehan Ahmad 5. Bakhtaj Ud Din & Co.

3. Friends Engineering Services

6. Anwar Ali Khan

Continue on Page-2

Page 2: 85 - cwd.gkp.pk · TO KHORABAD GUL FARAZ TO SURGHAN U/C DHAKKI DISTRICT CHARSADDA. SI No. Name of Contractor SI No. Name of Contractor 1. Habibullah Khan & Brothers 3. Shah Jehan

SPECIAL PACKAGE FOR DEVELOPMENT INITIATIVE ADP NO. 857/170358 SUB ADP NO. 316 (PK-17). SH: CONSTRUCTION/REHABILITATION OF SHAMAI ROAD FROM DEGAI KOROONA TO KABALI KOROONA DISTRICT CHARSADDA.

SI No. Name of Contractor SI No. Name of Contractor 1. Abid Construction Co. 4. Shah Jehan Ahmad 2. Horizon 5. Wajid All

3. Habib Ullah Khan & Brothers 6. Bakhtaj Ud Din & Co.

DISTRICT DEVELOPMENT INITIATIVE ADP NO. 858/170359 SUB ADP NO. 407 (PK-17). SH: CONSTRUCTION/REHABILITATION OF ROAD GHANI KHAN ROAD TO DHAB BANDA DISTRICT CHARSADDA (1.8-KM).

SI No. Name of Contractor SI No. Name of Contractor 1. Nasrullah Khan & Co. 4. Shah Jehan Ahmad

2. Friends Engineering Services 5. Bakhtaj Ud Din & Co.

3. Farukh Engineering Co.

DISTRICT DEVELOPMENT INITIATIVE ADP NO. 858/170359 SUB ADP NO. 576 (PK-17). SH: CONSTRUCTION/REHABILITATION OF RURAL ROAD IN UCs DOSEHRA, NISATTA, DHERI ZARDAD & MAIRA PRANG DISTRICT CHARSADDA.

SI No. Name of Contractor SI No. Name of Contractor 1. Shah Jehan Ahmad 2. Bakhtaj Ud Din & Co.

It must be ensured that the recommended Contractors/Firms do possess the required codes/specialties in their PECs.

The Procurement Committee shall be responsible for correctness, authenticity and validity of the documents.

An affidavit shall be obtained from the above bidders before opening of financial bid that their financial bids are accompanied by the bid security.

CHIEF ENGINEER (CENTRE) c.c

1. Superintending Engineer, C&W Circle Peshawar. 2. Deputy Director (IT) C&W Department Khyber Pakhtunkhwa Peshawar with the request to