Planning a Software ProjectFrom

Pankaj Jalote’s book

Page 2: 8 project planning

2

Agenda

• Background• Process planning• Effort estimation • Schedule and resource estimation• Quality Planning• Risk management• Configuration Management• Project monitoring plans

Page 3: 8 project planning

3

Software Project

• Goal: Build a software system to meet commitments on cost, schedule, quality

• Worldwide - many projects fail– one-third are runaways with cost or schedule

overrun of more than 125%

Page 4: 8 project planning

4

Project Failures

• Major reasons for project runaways– unclear objectives– bad planning– no project management methodology– new technology– insufficient staff

• All of these relate to project management• Effective project management is key to

successfully executing a project

Page 5: 8 project planning

5

Why improve PM?

• Better predictability leading to commitments that can be met

• Lower cost through reduced rework, better resource mgmt, better planning,..

• Improved quality through proper quality planning and control

• Better control through change control, CM, monitoring etc.

Page 6: 8 project planning

6

Why improve PM ….

• Better visibility into project health and state leading to timely intervention

• Better handling of risks reducing the chances of failure

• All this leads to higher customer satisfaction• And self and organization improvement

Page 7: 8 project planning

7

Two Dimensions in project execution

Page 8: 8 project planning

8

Process-based Project Execution

• Small project both engg and PM can be done informally

• Large projects require formality• Formality: well defined processes used for each

task; measurements used to control• Here we focus on processes for PM only

Page 9: 8 project planning

9

The Project Mgmt Process

• Has three phases - planning, monitoring and control, and closure

• Planning is done before the main engineering LC (Life Cycle) and closure after the LC

• Monitoring phase is in parallel with LC

Page 10: 8 project planning

10

Project Planning

• Basic objective: To create a plan to meet the commitments of the project, I.e. create a path that, if followed, will lead to a successful project

• Planning involves defining the LC process to be followed, estimates, detailed schedule, plan for quality, etc.

• Main output - a project management plan and the project schedule

Page 11: 8 project planning

11

Key Planning Tasks

• Define suitable processes for executing the project

• Estimate effort• Define project milestones and create a schedule• Define quality objectives and a quality plan• Identify risks and make plans to mitigate them• Define measurement plan, project-tracking

procedures, training plan, team organization, etc.

Page 12: 8 project planning

12

Process Planning

• Plan how the project will be executed, I.e. the process to be followed

• Process will decide the tasks, their ordering, milestones

• Hence process planning is an important project planning task

• Should plan for LC and PM processes as well as supporting processes

Page 13: 8 project planning

13

Life Cycle Process

• Various LC models - waterfall, iterative, prototyping; diff models suit different projects

• During planning can select the model that is best for the project

• This gives the overall process which has to be fine-tuned to garb the project needs

• Usually done by process tailoring - changing the process to suit the project

• Tailoring finally results in adding, deleting, modifying some process steps

Page 14: 8 project planning

14

Effort Estimation

Page 15: 8 project planning

15

Effort Estimation

• For a project total cost and duration has to be committed in start

• Requires effort estimation, often in terms of person-months

• Effort estimate is key to planning - schedule, cost, resources depend on it

• Many problems in project execution stem from improper estimation

Page 16: 8 project planning

16

Estimation..

• No easy way, no silver bullet• Estimation accuracy can improve with more

information about the project• Early estimates are more likely to be inaccurate

than later – More uncertainties in the start– With more info, estimation becomes easier

Page 17: 8 project planning

17

Estimation accuracy

Page 18: 8 project planning

18

Effort Estimation Models..

• A model tries to determine the effort estimate from some parameter values

• A model also requires input about the project, and cannot work in vacuum

• So to apply a model, we should be able to extract properties about the system

• Two types of models - top-down and bottom-up

Page 19: 8 project planning

19

Effort Estimation Models

Extract Estimation Model

Values of somecharacteristics

Effort Estimate

Knowledge aboutSW project

Page 20: 8 project planning

20

Top-down Estimation

• First determines the total effort, then effort for components

• Usually works with overall size• One method is to see estimate as a

function of effort; the common function used is

E = a * size b

• E (Effort) is in person-months, size in KLOC

• Constants a and b determined through regression analysis of past project data

Page 21: 8 project planning

21

Top down estimation

• Can also estimate from size and productivity– Get the estimate of the total size of the software– Estimate project productivity using past data

and project characteristics – Obtain the overall effort estimate from

productivity and size estimates

• Effort distribution data from similar project are used to estimate effort for different phases

Page 22: 8 project planning

22

Bottom-up Estimation

• Effort for components and phases first estimated, then the total

• Can use activity based costing - all activities enumerated and then each activity estimated separately

• Can group activities into classes - their effort estimate from past data

Page 23: 8 project planning

23

An Estimation Procedure

• Identify programs in the system and classify them as simple, medium, or complex (S/M/C)

• Define the average coding effort for S/M/C • Get the total coding effort.• Use the effort distribution in similar projects to

estimate effort for other tasks and total• Refine the estimates based on project specific

factors

Page 24: 8 project planning

24

COCOMO Model for Estimation

• Is a top-down approach• Uses size, but adjusts using some factors• Basic procedure

– Obtain initial estimate using size– Determine a set of 15 multiplying factors from different

project attributes– Adjust the effort estimate by scaling it with the final

multiplying factor

Page 25: 8 project planning

25

COCOMO..

• Initial estimate: a * size b ; some standard values for a, b given for diff project types

• There are 15 cost driver attributes like reliability, complexity, application experience, capability, …

• Each factor is rated, and for the rating a multiplication factor is given

• Final effort adjustment factor is the product of the factors for all 15 attributes

Page 26: 8 project planning

26

COCOMO – Some cost drivers

Cost Driver Very low

Low Nominal

High Very High

Required reliabilityDatabase sizeProduct complexityExecution time constraintMemory constraintAnalyst capabilityApplication experienceProgrammer capabilityUse of software toolsDevelopment schedule

.75

.7

1.461.291.421.241.23

.88

.94

.85

1.191.131.171.101.08

1.01.01.01.01.01.01.01.01.01.0

1.151.081.151.111.06.86.91.86.911.04

1.41.161.31.31.21.71.82.70.831.1

Page 27: 8 project planning

27

COCOMO – effort distribution

• Effort distribution among different phases is given as a percent of effort

• Eg. For medium size product it is– Product design – 16%– Detailed design – 24%– Coding and UT – 38%– Integration and test – 22%

Page 28: 8 project planning

28

Sizing With Function Points

Page 29: 8 project planning

29

Sizing

• Effort for project depends on many factors• Size is the main factor – many experiments and

data analysis have validated this• Size in the start is only an estimate; getting size

estimates from requirement is hard• Need a size unit that can be “computed” from

requirements• Function points attempt to do this

Page 30: 8 project planning

30

Function Points

• Is a size measure like LOC• Determined from SRS• Defines size in terms of “ functionality “• Why “measure” size early ?

– Needed for estimation and planning

• Five different parameters– external input type– external output type– logical internal file type– external interface file type– external inquiry type

Page 31: 8 project planning

31

Function Points…

• These five parameters capture the functionality of a system

• within a type , an element may be simple , average or complex

• A weighted sum is taken External input type : • each unique input type• A input type is unique if the format is

different from others or if the specifications require different processing.

Page 32: 8 project planning

32

Function Points…

• Simple : a few data elements• Complex : many data elements and many internal

files needed for processing• Only files needed by the application are counted.

( HW/OS config. Files are are not counted ) External output type :• each unique output that leave system boundary• E.g.

– Reports , messages to user , data to other applications

• Simple : few columns

Page 33: 8 project planning

33

Function Points…

• Average : many columns• Complex : references many files for

production Logical internal file type : • An application maintains information

internally for its own processes• Each logical group of data generated , used

and maintained• Same for simple , average and complex

Page 34: 8 project planning

34

Function Points…

• External interface file type– logical files passed between application

• External inquiry type– input , output combination

• Weights– External Input 3 4 6– External Output 4 5 7– Logical int. file 7 10 15– External int. file 5 7 10– External inquiry 3 4 6

Page 35: 8 project planning

35

Function Points…

Unadjusted function point :• Basic function points• Adjusted for other factors• 14 such factors

– performance objectives , transaction rate etc.

• Final FP is adjusted– differs at most 35%

Page 36: 8 project planning

36

Function Points…

• Interest in FP – since obtained at requirements => major

advantage

• Well correlated with size– in some what interchangeable and tables exist

• 1 FP = 70 LOC of C• Works well for MIS , but not for system type• Major draw back - subjectivity

– not repeatable– not precisely known ever for a built system – not addictive

Page 37: 8 project planning

37

Scheduling and Staffing

Page 38: 8 project planning

38

Project Schedule

• A project Schedule is at two levels - overall schedule and detailed schedule

• Overall schedule comprises of major milestones and final date

• Detailed schedule is the assignment of lowest level tasks to resources

Page 39: 8 project planning

39

Overall Schedule

• Depends heavily on the effort estimate• For an effort estimate, some flexibility exists

depending on resources assigned• Eg a 56 PM project can be done in 8 months (7

people) or 7 months (8 people)• Stretching a schedule is easy; compressing is

hard and expensive

Page 40: 8 project planning

40

Overall Scheduling...

• One method is to estimate schedule S (in months) as a function of effort in PMs

• Can determine the fn through analysis of past data; the function is non linear

• COCOMO: S = 2.5 E 3.8 • Often this schedule is checked and corrected

for the specific project• One checking method – square root check

Page 41: 8 project planning

41

Determining Overall Schedule from past data

Effort in person-days

0

50

100

150

200

250

300

350

400

0 200 400 600 800 1000 1200 1400 1600 1800

Sch

ed

ule

(D

ays

)

Page 42: 8 project planning

42

Determining Milestones

• With effort and overall schedule decided, avg project resources are fixed

• Manpower ramp-up in a project decides the milestones

• Manpower ramp-up in a project follows a Rayleigh curve - like a normal curve

• In reality manpower build-up is a step function

Page 43: 8 project planning

43

Manpower Ramp-up

Design Build Test

PTS

Page 44: 8 project planning

44

Milestones ...

• With manpower ramp-up and effort distribution, milestones can be decided

• Effort distribution and schedule distribution in phases are different

• Generally, the build has larger effort but not correspondingly large schedule

• COCOMO specifies distr of overall sched. Design – 19%, programming – 62%, integration – 18%

Page 45: 8 project planning

45

An Example Schedule

# Task Dur. (days)

Work (p-days)

Start Date

End Date

2 Project Init tasks 33 24 5/4 6/23

74 Training 95 49 5/8 9/29

104

Knowledge sharing

78 20 6/2 9/30

114

Elaboration iteration I

55 55 5/15

6/23

198

Construction iteration I

9 35 7/10

7/21

Page 46: 8 project planning

46

Detailed Scheduling

• To reach a milestone, many tasks have to be performed

• Lowest level tasks - those that can be done by a person (in less than 2-3 days)

• Scheduling - decide the tasks, assign them while preserving high-level schedule

• Is an iterative task - if cannot “fit” all tasks, must revisit high level schedule

Page 47: 8 project planning

47

Detailed Scheduling

• Detailed schedule not done completely in the start - it evolves

• Can use MS Project for keeping it• Detailed Schedule is the most live document for

managing the project• Any activity to be done must get reflected in the

detailed schedule

Page 48: 8 project planning

48

An example task in detail schedule

Module Act Code

Task Duration Effort

History PUT Unit test # 17

1 day 7 hrs

St. date End date

%comp Depend. Resource

7/18 7/18 0% Nil SB

Page 49: 8 project planning

49

.Project Scheduling…..

• The scheduling process

Estimate resourcesfor activities

Identify activitydependencies

Identifyactivities

Allocate peopleto activities

Create projectcharts

Softwarerequirements

Activity chartsand bar charts

Page 50: 8 project planning

50

..Project Scheduling….

• Graphical notations used in software project scheduling:– Tables: summary description of tasks – Bar charts: show schedule against the time– Activity charts: graphs that depict dependencies

between tasks and indicate the critical path (the longest path in the activity graph)

Page 51: 8 project planning

51

…Project Scheduling…

• Example of tabular description [Fig. 5.5, SE-7]:

Page 52: 8 project planning

52

….Project Scheduling..

• Example of activity chart

start

T2

M3T6

Finish

T10

M7T5

T7

M2T4

M5

T8

4/7/03

8 days

14/7/03 15 days

4/8/03

15 days

25/8/03

7 days

5/9/03

10 days

19/9/03

15 days

11/8/03

25 days

10 days

20 days

5 days25/7/03

15 days

25/7/03

18/7/03

10 days

T1

M1 T3T9

M6

T11

M8

T12

M4

Page 53: 8 project planning

53

…..Project Scheduling.

• Example of bar chart

4/7 11/7 18/7 25/7 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9

T4

T1T2

M1

T7T3

M5T8

M3

M2T6

T5M4

T9

M7T10

M6

T11M8

T12

Start

Finish

Page 54: 8 project planning

54

……Project Scheduling

• Staff allocation chart

4/7 11/7 18/7 25/ 1/8 8/8 15/8 22/8 29/8 5/9 12/9 19/9

T4

T8 T11

T12

T1

T3

T9

T2

T6 T10

T7

T5

Fred

Jane

Anne

Mary

Jim

Page 55: 8 project planning

55

Detail schedule

• Each task has name, date, duration, resource etc assigned

• % done is for tracking (tools use it)• The detailed schedule has to be consistent with

milestones– Tasks are sub-activities of milestone level activities,

so effort should add up, total schedule should be preserved

Page 56: 8 project planning

56

Team Structure

• To assign tasks in detailed schedule, need to have a clear team structure

• Hierarchic team org is most common– Project manager has overall responsibility; also does

design etc.– Has programmers and testers for executing detailed

tasks– May have config controller, db manager, etc

Page 57: 8 project planning

57

Team structure..

• An alternative – democratic teams– Can work for small teams; leadership rotates

• Another one used for products– A dev team led by a dev mgr, a test team led by test

mgr, and a prog. Mgmt team– All three report to a product mgr– Allows specialization of tasks and separate career

ladders for devs, tests, PMs

Page 58: 8 project planning

58

SCM process and planning

• Have discussed SCM process earlier• During planning, the SCM activities are planned

along with who will perform them• Have discussed planning also earlier

– Includes defining CM items, naming scheme, directory structure, access restrictions, change control, versioning, release procedure etc

Page 59: 8 project planning

59

Quality Planning

Page 60: 8 project planning

60

Quality Planning

• Delivering high quality is a basic goal• Quality can be defined in many ways• Current industry standard - delivered defect

density (e.g. #defects/KLOC)• Defect - something that causes software to

behave in an inconsistent manner• Aim of a project - deliver software with low

delivered defect density

Page 61: 8 project planning

61

Defect Injection and Removal

• Software development is labor intensive• Defects are injected at any stage• As quality goal is low delivered defect density,

these defects have to be removed• Done primarily by quality control (QC) activities

of reviews and testing

Page 62: 8 project planning

62

Defect Injection and Removal

Req.Analysis

Design R Coding R UT IT/ST AT

DevelopmentProcess

Defect Injection

R

Defect Removal

Page 63: 8 project planning

63

Approaches to Quality Management

• Ad hoc - some testing, some reviews done as and when needed

• Procedural - defined procedures are followed in a project

• Quantitative - defect data analysis done to manage the quality process

Page 64: 8 project planning

64

Procedural Approach

• A quality plan defines what QC tasks will be undertaken and when

• Main QC tasks - reviews and testing• Guidelines and procedures for reviews and

testing are provided• During project execution, adherence to the plan

and procedures ensured

Page 65: 8 project planning

65

Quantitative Approach

• Goes beyond asking “has the procedure been executed”• Analyzes defect data to make judgements about quality• Past data is very important• Key parameters - defect injection and removal rates,

defect removal efficiency (DRE)

Page 66: 8 project planning

66

Quality Plan

• The quality plan drives the quality activities in the project

• Level of plan depends on models available• Must define QC tasks that have to be

performed in the project• Can specify defect levels for each QC tasks (if

models and data available)

Page 67: 8 project planning

67

Risk Management

Page 68: 8 project planning

68

Risk Management

• Any project can fail - reasons can be technical, managerial, etc.

• Project management aims to tackle the project management aspect

• Engineering life cycles aim to tackle the engineering issues• A project may fail due to unforeseen events - risk

management aims to tackle this

Page 69: 8 project planning

69

Risk Management

• Risk: any condition or event whose occurrence is not certain but which can cause the project to fail

• Aim of risk management: minimize the effect of risks on a project

Page 70: 8 project planning

70

Risk Management Tasks

RISKMANAGEMENT

RISK ASSESSMENT

RISK IDENTIFICATION

RISK ANALYSIS

RISK PRIORITIZATION

RISK MANAGEMENTPLANNING

RISK RESOLUTION

RISK MONITORING

RISK CONTROL

Page 71: 8 project planning

71

Risk Identification

• To identify possible risks to a project, i.e. to those events that might occur and which might cause the project to fail

• No “algorithm” possible, done by “what ifs”, checklists, past experience

• Can have a list of “top 10” risks that projects have seen in past

Page 72: 8 project planning

72

Top Risk Examples

• Shortage of technically trained manpower• Too many requirement changes• Unclear requirements• Not meeting performance requirements• Unrealistic schedules• Insufficient business knowledge• Working on new technology

Page 73: 8 project planning

73

Risk Prioritization

• The number of risks might be large• Must prioritize them to focus attention on the

“high risk” areas• For prioritization, impact of each risk must be

understood• In addition, probability of the risk occurring

should also be understood

Page 74: 8 project planning

74

Risk Prioritization ...

• Risk exposure (RE) = probability of risk occurring * risk impact

• RE is the expected value of loss for a risk• Prioritization can be done based on risk

exposure value• Plans can be made to handle high RE risks

Page 75: 8 project planning

75

A Simple approach to Risk Prioritization

• Classify risk occurrence probabilities as: Low, Medium, High

• Classify risk impact as: Low, Medium, High• Identify those that are HH, or HM/MH• Focus on these for risk mitigation• Will work for most small and medium sized projects

Page 76: 8 project planning

76

Risk Control

• Can the risk be avoided?– E.g. if new hardware is a risk, it can be avoided by

working with proven hardware

• For others, risk mitigation steps need to be planned and executed– Actions taken in the project such that if the risk

materializes, its impact is minimal– Involves extra cost

Page 77: 8 project planning

77

Risk Mitigation Examples

• Too many requirement changes– Convince client that changes in requirements will

have an impact on the schedule – Define a procedure for requirement changes– Maintain cumulative impact of changes and make it

visible to client– Negotiate payment on actual effort.

Page 78: 8 project planning

78

Examples ...

• Manpower attrition– Ensure that multiple resources are assigned on key

project areas– Have team building sessions– Rotate jobs among team members– Keep backup resources in the project – Maintain documentation of individual’s work– Follow the CM process and guidelines strictly

Page 79: 8 project planning

79

Examples ...

• Unrealistic schedules– Negotiate for better schedule– Identify parallel tasks– Have resources ready early– Identify areas that can be automated– If the critical path is not within the schedule, negotiate

with the client– Negotiate payment on actual effort

Page 80: 8 project planning

80

Risk Mitigation Plan

• Risk mitigation involves steps that are to be performed (hence has extra cost)

• It is not a paper plan - these steps should be scheduled and executed

• These are different from the steps one would take if the risk materializes - they are performed only if needed

• Risks must be revisited periodically

Page 81: 8 project planning

81

Project Monitoring Plans

Page 82: 8 project planning

82

Background

• A plan is a mere document that can guide• It must be executed• To ensure execution goes as per plan, it must

be monitored and controlled• Monitoring requires measurements• And methods for interpreting them• Monitoring plan has to plan for all the tasks

related to monitoring

Page 83: 8 project planning

83

Measurements

• Must plan for measurements in a project• Without planning, measurements will not be

done• Main measurements – effort, size, schedule,

and defects– Effort – as this is the main resource; often tracked

through effort reporting tools– Defects – as they determine quality; often defect

logging and tracking systems used

• During planning – what will be measured, how, tool support, and data management

Page 84: 8 project planning

84

Project Tracking

• Goal: To get visibility in project execution so corrective actions can be taken when needed to ensure project succeeds

• Diff types of monitoring done at projects; measurements provide data for it

Page 85: 8 project planning

85

Tracking…

• Activity-level monitoring– Each activity in detailed schd is getting done– Often done daily by managers– A task done marked 100%; tools can

determine status of higher level tasks

• Status reports– Generally done weekly to take stock– Summary of activities completed, pending– Issues to be resolved

Page 86: 8 project planning

86

Tracking…

• Milestone analysis– A bigger review at milestones– Actual vs estimated for effort and sched is done– Risks are revisited– Changes to product and their impact may be

analyzed

• Cost-schedule milestone graph is another way of doing this

Page 87: 8 project planning

87

Cost-schedule milestone graph

Page 88: 8 project planning

88

Project Management Plan

• The project management plan (PMP) contains outcome of all planning activities - focuses on overall project management

• Besides PMP, a project schedule is needed– Reflects what activities get done in the project– Microsoft project (MSP) can be used for this– Based on project planning; is essential for day-to-day management– Does not replace PMP !

Page 89: 8 project planning

89

PMP Structure - Example

• Project overview - customer, start and end date, overall effort, overall value, main contact persons, project milestones, development environment..

• Project planning - process and tailoring, requirements change mgmt, effort estimation, quality goals and plan, risk management plan, ..

Page 90: 8 project planning

90

PMP Example ...

• Project tracking - data collection, analysis frequency, escalation procedures, status reporting, customer complaints, …

• Project team, its organization, roles and responsibility, …

Page 91: 8 project planning

91

Project Planning - Summary

• Project planning forms the foundation of project management

• Key aspects: effort and schedule estimation, quality planning, risk mgmt., …

• Outputs of all can be documented in a PMP, which carries all relevant info about project

• Besides PMP, a detailed project schedule maintains tasks to be done in the project