SOUTHERN REGIONAL POWER COMMITTEE BANGALORE

Record Notes of the discussions in the Special Meeting of Protection Co-Ordination Sub-Committee (PCSC)

held at SRPC, Bangalore on 19.08.2014

A Special Meeting of PCSC was held at SRPC, Bangalore on

19.08.2014. The list of participants is furnished at Annexure – I.

Shri S. R. Bhat, Member Secretary I/c., SRPC welcomed the

participants to the Meeting. He briefed the details about the need for early

implementation of the Protection Audit Recommendations and the directions

of Hon’ble CERC to SRPC and SRLDC for appraising the status of

implementation by SR constituents of Phase I and Phase II of Protection

Audit Remarks; Hon’ble CERC order dated 19.12.2013 in petition No

146/MP/2013 with I.A. 36/2013 and Hon’ble CERC order dated 31.07.2014

in Petition No 86/MP/2014.

Gist of the Minutes of the Special meeting of PCSC :

I. SPRC Secretariat

a) It is a matter of concern that most of the items are yet to be

implemented by SR constituents despite repeatedly taking up in all the

OCC / PCC and TCC meetings of SRPC since the year 2012.

b) Chairperson, SRPC (MD, KPTCL) had also addressed a letter

regarding the implementation of the above issues (Annexure II).

Page 3: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 2

c) Implementation of Protection Audit recommendation was also an

agenda item in the Special meeting called by Additional Secretary,

MoP (Originally scheduled on 05.08.2014 and re-scheduled to later

date ).

d) Though the timeline for implementation of Phase-I was already over

(i.e. by 1.5.2014) and Phase-II would be over by 1.9.2014, only KSEB

had appraised the Hon’ble Commission about the action taken so far

and requested through a petition for time extension for pending items.

e) Hon’ble Commission had directed KSEB to submit an affidavit by

14.08.2014 with phase-wise details on action taken so far in

compliance of the Commission’s order dated 20.02.2014 in Petition

No.146/MP/2013 and proposed road map with time line for

implementation of remaining works along with PERT chart.

f) Similarly SRPC & SRLDC requested all other constituents also to

furnish the detailed road map with time line for implementation of

pending items.

g) The agenda of this special meeting was to review the status of

implementation by all the SR constituents and appraise the same to

Hon’ble CERC as directed in the RoP of petition no.86 / MP / 2014

and not for granting the extension of time limit for implementing the

Protection Audit recommendations. Extension of time limit was not in

the purview of SRPC or SRLDC.

h) The constituents those who have not completed the Protection Audit

recommendations as stipulated in the Hon’ble CERC order dated

19.12.2013 in petition No 146/MP/2013 with I.A. 36/2013 for Phase I

Page 4: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 3

and Phase II items are requested to approach the Hon’ble commission

through Petition (or affidavit) at the earliest.

i) The constituents were requested to furnish the road map with the time

line for implementation of remaining works along with PERT chart in

the petition/affidavit seeking time extension for implementation of

Phase-I & Phase-II activities

j) In case any protection audit recommendation was not envisaged in the

regulations and guidelines of CERC/CEA/CBIP and the constituents

take a view that those have to be dropped, then such a proposal can be

submitted with the consent of PCSC forum and prayer made to

Hon’ble CERC to drop the protection audit recommendation.

k) As clearly brought out during various meetings of SRPC and hearings

of Hon’ble Commission, all the constituents were requested not to

link the financial assistance from PSDF for implementation of

protection audit recommendations. However, it is to mention that

action for PSDF assistance is progressing in positive direction and the

DPR submitted by KSEB was approved by the nodal agency, NLDC.

All other constituents who had not done so are also requested to

expedite submission of DPR to NLDC and attend clarifications /

details that may be required during scrutiny by the committee for

approval.

Page 5: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 4

II. SRLDC

a) The implementation of protection audit recommendations were time

and again discussed in the various forum (i.e PCSC ,Sub Group/Spl

meetings of PCSC,OCC meetings of SRPC ). However, the progress

seen is marginal.

b) Only KSEB had discharged their responsibility of appraising the

status to Hon’ble CERC and submitted the detailed action plan for

individual itmes for implementing the Phase I and Phase II activities.

c) The Hon’ble Commission had also given extension to KSEB for

Phase I up to 31.12.2014 and directed SRPC & SRLDC to ascertain

the reasonability of time extension sought by KSEB in respect of

Phase – II items.

d) The other constituents were also requested to abide by Hon’ble

Commission’s order dated 20.2.2014 in Petition No. 146/MP/2013

and demonstrate their commitment for implementation of Protection

Audit Recommendations with clear road map and detailed PERT chart

/mile stone chart depicting the time line for individual items and

discharge the responsibility of appraising Hon’ble Commission

through affidavit / petition. Even after providing sufficient margin, the

maximum time required for any item that requires procurement action

would be about 10 months as per the understanding of SRLDC as

given below.

Page 6: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 5

Activity Month Finalization of Specification 0.5 Estimate Preparation 0.5 Initiating Proposal 0.5 Approval of Proposal 1 Calling Tender 0.5 Processing Tenders 2 Discussion & issue of LoA 1 Supply of Materials 3 Erection, Testing & Commissioning 1

Total Period 10

e) Only for items like CT / CVT / Circuit Breakers the supply &

Erection period may be 8 to 10 months in place of 3 to 4 months as

shown in the table. Thus no item shall take more than 15 to 16 months

while already more than 24 months passed away.

f) Being important / critical requirement, the constituents are expected to

use the spare materials if available, place repeat orders wherever

possible, process the procurement action for multiple items in parallel

and explore all possible ways to minimize the time required and

expedite the implementation.

III. APTRANSCO

a) The status of APTRANSCO w.r.t implementation of protection

Audit Recommendations is given as Annexure III.

b) The protection audit recommendations which were not requiring

fund mobilization like review of settings etc were done.

Page 7: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 6

c) Due to Bifurcation of APTRANSCO/TTRANSCO and budget

issues the Procurement issues were delayed.

d) APTRANSCO would be approaching Hon’ble commission for

extension of time through affidavit latest by 06.09.2014.

IV. APGENCO

a) The status of APGENCO w.r.t to implementation of protection

Audit Recommendations is given as Annexure IV.

b) APGENCO requires minimum 8-9 months for implementing the

protection audit recommendations which require procurements.

c) The protection audit recommendations without involves monetary

requirements were attended.

d) APGENCO would be approaching Hon’ble commission for

extension of time through affidavit latest by 06.09.2014.

V. KPTCL

a) Informed that the implementing the protection audit

recommendations were taken seriously. All the items that do not

involve procurement were already completed.

b) KPTCL clubbed both Phase – I and Phase – II recommendations

that involve procurement and issue of NIT is scheduled on

05.09.2014. To expedite the implementation, the total work has

been split in to four geographical packages such that work could be

simultaneously implemented at four areas:

Page 8: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 7

i. Placement of LOA expected by 15.01.2015 and the phase I and

Phase II protection audit recommendations expected completion

by 15.01.2016.

ii. The above completion schedule would be informed to Hon’ble

CERC vide affidavit latest by 23.08.2014.

VI. KPCL

a) The status of Implementation of Protection Audit recommendation

is enclosed as Annexure V ( Phase I) and Annexure VI (Phase

II).

b) KPCL would be approaching Hon’ble CERC for extension of time

for implementing the Protection Audit recommendation through

affidavit latest by 30.08.2014.

VII. TANTRANSCO

a) The status of implementation of Protection Audit

recommendations is given as Annexure VII (Phase I –completed),

Annexure VIII (Phase I-Pending), Annexure IX (Phase II-

completed), Annexure X (Phase II-pending) .

b) For the extension of time required for completion of activities, TN

would approach Hon’ble CERC through petition.

c) TN has completed all the items that do not involve financial

implication. Due to shortage of funds, the procurement action

could not be initiated so for. On receipt of details of PSDF

assistance from NLDC, procurement action will be initiated for

major items like CT / CVT / Breakers etc. Tender for procurement

Page 9: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 8

of relays was already called for and thereby items like relay

replacement is expected completion by March 2015.

d) The extension of time required for completing the Phase I and

Phase II activities is as follows.

i. Activities requiring minor procurement: 31.03.2015 ii. Activities requiring procurement of CTs, CVTs, Bus Bar

etc: 30.06.2016. iii. Activities requiring retrofitting /R&M: 30.06.2017

e) Expressed their inability to proceed with the procurement of

protection audit recommendations for want of funds/budget and

waiting for PSDF fund /consent letter etc.

VIII. KSEB

a) KSEB would be completing the Phase I of the protection Audit

recommendations by 31.12.2014 except for two substations (viz.

Idukki and Sabarigiri) which are of major in nature and require

more time to implement the protection audit recommendations.

Thereby considered as a part of R&M works.

b) KSEB have filed the affidavit as stipulated in the Hon’ble CERC

order dated 31.07.2014 in Petition No 86/MP/2014 on 13.08.2014.

KSEB has initiated action for every individual item and furnished

the % of progress and action plan for completion of each item

through a detailed PERT chart in their reply to Hon’ble CERC.

c) KSEB would be completing Bus-bar protection works identified

for Kaniyambetta sub-station by March 2015 and all other items

of the Phase II activities by December 2015.

Page 10: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 9

d) There is limitation / constraint of space in sub-stations where

transfer bus is suggested by the audit recommendations. After

deliberation, it was suggested by the forum to have bus

sectionaliser arrangement in place of transfer bus. The same was

agreed by KSEB for implementation.

IX. PGCIL

a) PGCIL requested for dropping of provision of Numerical Bus Bar

Protection for the following substations

i. 400 KV Gooty Substation ii. 400 KV Hiriyur Substation

iii. 400 KV Kadapa Substation iv. 400 KV Puducherry Substation

b) PGCIL informed the forum that the Bus Bar protection requirements

as recommended in the CBIP guidelines were incorporated in the

static relays in the above substations.

c) SRLDC requested PGCIL to consider / implement the provision of

Numerical Bus Bar relays during the Renovation and Modernization

(R&M) of the substation.

X. NLC

a) The status of Implementation of Protection Audit recommendation

is enclosed as Annexure XI (Phase I) and Annexure XII (Phase

II).

b) NLC would be approaching the Hon’ble CERC in the form of

Affidavit latest by 28.08.2014.

Page 11: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 10

XI. NPCIL, Kaiga

a) The status of NPCIL, Kaiga w.r.t to implementation of protection

Audit Recommendations is given as Annexure XIII.

b) Line relays of 220 KV side are provided with primary protection

i.e. Static Relay, and a backup protection is electro mechanical

relay with high set. Blocking of High set protection in the back up

relay was reviewed; Action has been completed during May 2014.

c) The installation of numerical relays is expected to be completed by

31st January 2015.

d) NPCIL, Kaiga would be approaching the Hon’ble CERC through

Affidavit latest by 06.09.2014.

XII. TSTRANSCO

a) The status of TSTRANSCO regarding the implementation of

Protection Audit Recommendation as submitted by Joint

Managing Director ,TSTRANCO , is enclosed herewith as

Annexure XIV.

b) It was informed that in April 2014 it was approved to take up the

protection audit recommendation works in phased manner.

c) Ist phase would be taken up with RMI budget of FY 2014-15

(R&M budget approved by APERC for FY 2014-15 is Rs

147.6 Crores) and 2nd phase would be taken up with PSDF fund

after reimbursement of Phase I fund.

Page 12: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 11

d) The PCSC forum requested TSTRANSCO to approach Hon’ble

CERC through petition for extension of time to complete the Phase

I and Phase II activities.

XIII. TSGENCO

a) The status of TS GENCO vide Lr No CEG/SE (GEN)/EME-

III/ADE (P)/F.SRPC/D.No 16/14 dt 13.08.2014 (Annexure XV)

informed that half of the works were completed in phase I and

Phase II activities and the remaining works are held up due to the

state bifurcation.

b) Vide above stated letter TSGENCO requested to extend the time

for completion of Phase I & Phase II activities of Protection

recommendation items of TSGENCO.

c) The PCSC forum requested TSGENCO to approach Hon’ble

CERC through petition for extension of time to complete the Phase

I and Phase II activities.

Joint Comments of SRPC and SRLDC:

1. All the constituents have completed the items like revision of relay

setting, attending battery etc., that do not involve procurement action.

However, KPCL is yet to implement many of the Phase – I items that

did not involve any procurement action.

2. APTRANSCO is yet to start procurement action including finalization

of specification of materials, approval of competent authority,

tendering etc. It is confirmed that their management have advised to

go ahead without linking release of PSDF assistance. Though they

Page 13: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two

Record Notes of the Special meeting of PCSC held on 19.08.2014 Page 12

mention that entire works will be completed in 8 to 10 months, the

status does not reflect the same. APTRANSCO needs to submit the

detailed action plan with PERT chart.

3. Procurement action of APGENCO will be done independently by

thermal generation wing and Hydro generation wing. Action including

approval of competent authority for tendering is yet to start.

4. KPTCL is ready for tendering with NIT scheduled on 05.09.2014. It

envisages placement of LoA by January 2015 and completion of

work by January 2016 as the per the time line given in the tender

documents. KPTCL also confirmed to go ahead with implementation

without linking PSDF assistance.

5. KPCL is yet to initiate action for many of the non-procurement items

too. Regarding procurement oriented activities, the action are yet to be

commenced including approval of competent authority to go in for

tendering. The commitment for early completion is missing as per the

status review.

6. KSEB submitted details demonstrating their commitment to complete

the phase – I activities by December 2014. Regarding Phase – II

activities, Bus-bar protection work at Kaniyambetta is expected

completion by March 2015 and all other items by December 2015.

KSEB confirmed that administrative approvals for most of the

proposals were received and tendering is in progress. KSEB

mentioned that works mentioned at Idukki & Edamon will be done as

a part of R&M.

7. TN has not submitted the DPR to NLDC. However, they are waiting

for PSDF Fund /consent letter.

Page 14: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 15: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE I (1/5)
Page 16: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE I (2/5)
Page 17: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE I (3/5)
Page 18: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE I (4/5)
Page 19: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE I (5/5)
Page 20: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE II (1/2)
Page 21: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE II (2/2)
Page 22: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE III (1/7)
Page 23: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE III (2/7)
Page 24: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE III (3/7)
Page 25: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE III (4/7)
Page 26: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE III (5/7)
Page 27: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE III (6/7)
Page 28: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE III (7/7)
Page 29: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE IV (1/5)
Page 30: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE IV (2/5)
Page 31: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE IV (3/5)
Page 32: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE IV (4/5)
Page 33: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE IV (5/5)
Page 34: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE V (1/2)
Page 35: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE V (2/2)
Page 36: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE VI (1/4)
Page 37: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE VI (2/4)
Page 38: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE VI (3/4)
Page 39: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE VI (4/4)
Page 40: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
COMPLIED
Page 41: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 42: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 43: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 44: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 45: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 46: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 47: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 48: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 49: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 50: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 51: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 52: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE XIII
Page 53: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Rajan
ANNEXURE XIII
Page 54: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 55: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 56: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 57: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 58: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 59: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 60: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 61: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 62: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 63: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 64: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 65: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 66: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two
Page 67: 7636-66 - Karnatakawaiting for PSDF fund /consent letter etc. VIII. KSEB a) KSEB would be completing the Phase I of the protection Audit recommendations by 31.12.2014 except for two