6-nov-06 falc resource board global design effort 1 report from the gde barry barish caltech / gde...

26
6-Nov-06 FALC Resou rce Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

Post on 20-Dec-2015

220 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board

Global Design Effort 1

Report from the GDE

Barry Barish

Caltech / GDE

6-Nov-06

Page 2: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 2

Outline

• Progress Since Last Meeting– Last FALC Resource Group Mtg– FALC report –May-06– Vancouver status – July 06– Design Cost Optimization for RDR (Valencia)– GDE Coordination of Global R&D Program

• Plans for Valencia Meeting

• Plans for Completing Reference Design Report

• Longer Term Issues and Plans (Resources)

Page 3: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 3

Report– Feb 06 – Baseline Achieved

Page 4: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 4

Next Steps Outlined

Page 5: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 5

Reorganized for Reference Design

Page 6: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 6

Our Plan as Reported at Feb Meeting

Page 7: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 7

FALC Report – May 06

Page 8: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 8

FALC Report – May 06

Page 9: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 9

FALC Report – May 06

Page 10: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 10

FALC Report – May 06

Page 11: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 11

FALC Report – May 06

Page 12: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 12

FALC Report – May 06

Page 13: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 13

FALC Report – May 06

Page 14: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 14

FALC Report – May 06

Page 15: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 15

The ‘S’ R&D Task Forces

S0High-Gradient Cavities

S1High-Gradient Cryomodule

S2Test Linac

S3Damping Ring

S4Beam Delivery

S5…Sn

To address priority R&D items, RDB has convened several ‘task forces’.

S0-S3 will report on Friday AM GDE plenary

Page 16: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 16

The ‘S’ R&D Task Forces

• Addresses current ‘poor’ yield for EP cavities

• Primary goal: establish parameters for routinely producing 35 MV/m EP’d cavities– required 80% yield

S0High-Gradient Cavities

S1High-Gradient Cryomodule

S2Test Linac

S3Damping Ring

S4Beam Delivery

S5…SnH. Hayano, T. Higo, L. Lilje, J. Mammosser, H. Padamsee, M. Ross, K. Saito

Page 17: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 17

Baseline to a RDR

Jan July Dec 2006

Freeze ConfigurationOrganize for RDR

Bangalore

Review Design/Cost Methodology

Review InitialDesign / Cost Review Final

Design / CostRDR Document

Design and Costing PreliminaryRDR

Released

Frascati Vancouver Valencia

Page 18: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 18

System July 18, 2006 - Cost Estimates received for Regionaldescription common e- e+ DR RTML ML BDS Exp Am Asia Eure- Source √e+ Source √DR √RTML √Main LinacBDS √Com, Op, ReliabControl System √ √ √ √ √ √ √Cryogenics √ √ √ * √ √ √ *Convent. Facilities √ √ √ √ √ √ √ * √ √ √ √Installation √ √ √ √ √ √ √Instrumentation √ √ √ √ √ √ √Cavities √ √ √Cryomodules √ √ √ √ √ √ √RF √ √ √ √ √ √ √ √ √Magnets & PS √ * √ *Dumps & Collim √ √ √ √ √Vacuum √ √ √ √ √ √Accel Phys

√ = complete, √ * = almost complete, missing something minor

Vancouver Cost Data

Page 19: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 19

ILC Estimate by Area Systems -17july06

Main Linac DRs Beam Deliv RTML e+ Source Exp. Halls e- Source General

Costs by Area System

Page 20: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 20

ILC Estimate by Technical & Global Systems - 22july06

Conventional Facilities

Dumps & Collimators

CM & Cavities

Instrumentation

RF

Vacuum

Installation

Magnets

Cryogenics

Controls

Costs by Technical & Global System

Page 21: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 21

Vancouver Valencia

CostReduction

Design Scope

Component Costs

Physics ScopeNo big ticket items!

Just lots of 1% effects

Page 22: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 22

Design Changes Under Consideration

RDR MB CCB

214mr IRs supported central injectors supported Removal of service tunnel rejected

conventional e+ source rejected

RF unit modifications (24 26 cav/klys) supported submitted

reduced RF in DR (6 9mm z) supported in prep

DR race-track lattice (CFS) supported in prep

reduced static cryo overhead supported in prep

removal linac RF overhead supported in prep

single-stage bunch compressor rejected

e- source: common pre-accelerator supported in prep

Page 23: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 23

Potential Physics Scope Cuts

• Nobody want's to do this but it may still be necessary– We must wait and see our new "Bottom Line"

• If we are still too expensive, then need to consider 'physics reach‘:– Energy reach: re-defining 500 GeV– Peak Luminosity

• Single IR (push-pull)– not directly a physics scope issue

• These will need to be fully discussed and coordinated with the Physics Community– Physics Parameter Group– MDI panel– (WWS)

Page 24: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 24

Plans until Beijing (Feb. '07)

November December January February

Valencia

Further cost consolidationCCR preparation & submission

Cost & Design Freeze 30/11

Prepare for Full Cost Review

SLAC Cost Review 14-16/12

MAC 10-12/01/07

Final cost corrections and documentation

Agency cost briefings

Beijing: RDR draft published

RDR final editing

RDR prepare 1st drafts

2006 2007

Page 25: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 25

What Happens after Beijing?

• Public Release of Draft RDR and Preliminary Costing at Beijing– Cost Reviews, etc– Finalize RDR by Summer 2007?

• Enter into Engineering Design Phase– Planning underway internally– Design will evolve through value engineering

and R&D program– General Goal is to have Construction Proposal

ready by 2010

Page 26: 6-Nov-06 FALC Resource Board Global Design Effort 1 Report from the GDE Barry Barish Caltech / GDE 6-Nov-06

6-Nov-06 FALC Resource Board Global Design Effort 26

Summary• Status of Costing

– First costing available at Vancouver (July)– Cost to performance optimization

• Component level cost reduction (requirements) • Machine design changes• Changes effecting physics performance

• Status & Plans for design modifications– Several proposals accepted and some rejected– Changes having physics impact (Valencia)– Complete RDR by Beijing Meetings

• Global planning for critical R&D beginning– Formation of ‘S’ task forces