Dietrich Liko

6. Juli 2015

Physics Computing

114. Vorstandssitzung

2Dietrich Liko6. Juni 2015

Overview

• Computer Security

• Status 2015– CMS Grid– Belle Grid– OpenAFS– Batch System– Backup

• Plans up to 2018

• Cloud Computing

3Dietrich Liko

Computer Security

• 5 % of HEPHY Staff victim of a Phishing Attack– Blocking of ÖAW

Account– Blocking of CERN

Account– Further user

accounts compromised

6. Juni 2015

4Dietrich Liko

Computing Rules

• Remind users of Computing Rules– Präsidum der ÖAW– ACONET Usage Rules– Betriebsvereinbarung

• Basic Computer Security Training

6. Juni 2015

5Dietrich Liko

CMS Grid 2015

• Usual number of Requests by CMS

• Spacemonitoring• New Phedex Box• AAA still broken

• CMS Operation requests additional 100 TB of pledged 500 TB– 200 TB to 300 TB

6. Juni 2015

6Dietrich Liko

Belle Grid 2015

• Belle Currently the #1 user– Will change when new

CMS analysis are starting

• Belle has requested 100 TB to be reserved for Belle – Empty Diskspace

6. Juni 2015

7Dietrich Liko

Storage Upgrade Plans

Satus Now Upgrade Final Upgrade0

200

400

600

800

1000

1200

New (4TB)Old (1TB)

6. Juni 2015

8Markus Friedl (HEPHY Wien)

Operation

• We are for long times marked as bad– In ATLAS this time

does not count as contribution

• For example– We were marked bad

during AFS migration– We are marked as

good only today

20. Oktober 2009

“Waiting room”

9Dietrich Liko

OpenAFS

• New AFS Operational– New Software– Partially New Hardware– Bigger Caches

• Daily backup to disk

6. Juni 2015

10Dietrich Liko

User Accounts

• New AFS has a state of the art identity management

• Integration of other services during the summer– indico.hephy.oeaw.ac.at– forge.hephy.oeaw.ac.at– New web page– wiki.hephy.at– ticket.hephy.oeaw.ac.at (helpdesk)– nagios.hephy.oeaw.ac.at

17. Dezember 2013

11Dietrich Liko

Refurbished Supermicro

• Old Storage Server• New Disk• New RAID Controller• SSD Cache• 10 Gbit Interface

6. Juni 2015

Backup

13Dietrich Liko

OpenAFS Raw Capacity

Today Upgrade Maximum0

50

100

150

200

250

4TB1TB

6. Juni 2015

14Dietrich Liko

How much do we need ?

• CMS Scratch– 40 TB

• CRESST– 40 TB ?

6. Juni 2015

15Dietrich Liko

Backup

• Biggest risk– Scratch disks without

Backup

• As of today– Synology NAS 80 TB

• Reduction of Storage cost – 6TB Disks– 200 TB about 25 K

6. Juni 2015

16Dietrich Liko

Batch System

• New AFS gives new possibilities

• Standalone Batch system by end of August

• Later– Integration with Grid

6. Juni 2015

17Dietrich Liko

The new system

• New AFS and new Batch system are the elements that should form the basis of physics analysis starting until 2018

• Efficient use limited resources

• It should be useable for all user groups– CMS, CRESST, Belle, Theory– CMS Grid, Belle Gird

• Close interaction with users required that it does what they want

6. Juni 2015

18Dietrich Liko

Aging Hardware

• Best example

• We lost the big UPS– Cannot be repaired

• We can life (now) without it

6. Juni 2015

19Dietrich Liko

Further Investments

• New central switch

• Netgear M6100

• Mini version of an enterprise switch

• Replaces a number of old switches

6. Juni 2015

20Dietrich Liko

Further Plans

• New cabling in the house– Contact to Baureferat to see what would be the

costs

• New Internet connection– 10 Gbit– NAT– Firewall

• Renewal of interactive login machines6. Juni 2015

21Dietrich Liko

2018 - End of lifetime for …

More then 10 years of service for …

• Grid Cooling• UPS• Grid Network• Storage Servers• CPU Blades

6. Juni 2015

22Dietrich Liko

The future is in the cloud …

• Discussion in the academy

• Discussion with possible partners at TU Wien

6. Juni 2015

23Dietrich Liko

We need to understand how we could run a site in the cloud…

6. Juni 2015

• Grid Storage• Grid CE

• User Storage• Batch System

• We will need an understanding how and which personal needs training

24Dietrich Liko

Summary• New AFS Operational• Storage upgrade for the grid on the way

• New physics analysis system for the end of summer– OpenAFS– Batch System– Backup of all data

• Some investment necessary to keep the system running in the next years