DS San Diego Unified School District Long Range Facility Master Plan 6: District Facilities Assessment Site Data Evaluation for E.B. Scripps Elementary School SITE DATA ES SCRIPPS ES 90 Site Net Acreage: 6.7 Total Permanent Building Sq. Footage: 32,913 Total Quantity of Classrooms: 42 Quantity of Permanent Classrooms 42 Number of Permanent Buildings 8 School Program Capacity 943 Current Enrollment - 2007-08 553 Projected Enrollment - 2016-17: 653 Student to Acre Ratio: 83 Quantity of Portable Classrooms 0 % of Total Classrooms in Portables 0% Quantity of Portable Buildings on Site 2 Quantity of Undersized Classrooms 2 % of Undersized Classrooms 5% API Rating (2007 Base Statewide Rank) 10 Quantity of buildings over 50 years 0 Age of Building-% over 50 years 0% FCA Rating New Climate Control lll ADA Report Fair Delta from Capacity 390 Site Findings : This is a new school building Input From Site Surveys: Shade structure requested on playground Student drop-off & bus turnaround problems reported Fencing reportedly insufficient currently Input from Cluster Meetings: Request security cameras Request AC Would like covered walkway from cafeteria to multi-purpose room Request intercom system Request landscaping upgrades Request amplified sound system Request vandalism prevention measures

Upload: nguyenhanh

Post on 18-Mar-2018

221 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: 6: District Facilities Assessment - San Diego Unified … B Scripps...DS San Diego Unified School District Long Range Facility Master Plan 6: District Facilities Assessment Site Data

DS

San Diego Unified School District Long Range Facility Master Plan

6: District Facilities Assessment

Site Data Evaluation for E.B. Scripps Elementary School

SITE DATA ES SCRIPPS ES 90Site Net Acreage: 6.7Total Permanent Building Sq. Footage: 32,913Total Quantity of Classrooms: 42Quantity of Permanent Classrooms 42Number of Permanent Buildings 8School Program Capacity 943Current Enrollment - 2007-08 553Projected Enrollment - 2016-17: 653Student to Acre Ratio: 83Quantity of Portable Classrooms 0% of Total Classrooms in Portables 0%Quantity of Portable Buildings on Site 2Quantity of Undersized Classrooms 2% of Undersized Classrooms 5%API Rating (2007 Base Statewide Rank) 10Quantity of buildings over 50 years 0Age of Building-% over 50 years 0%FCA Rating NewClimate Control lllADA Report FairDelta from Capacity 390

Site Findings: • This is a new school building

Input From Site Surveys: • Shade structure requested on playground • Student drop-off & bus turnaround problems reported • Fencing reportedly insufficient currently

Input from Cluster Meetings: • Request security cameras • Request AC • Would like covered walkway from cafeteria to multi-purpose room • Request intercom system • Request landscaping upgrades • Request amplified sound system • Request vandalism prevention measures