445 baltic street retrofit model: wet floodproofing
TRANSCRIPT
445 BALTIC STREETRETROFIT MODEL: WET FLOODPROOFING
BUILDING SUMMARYLandlord Fi f th Avenue Commit tee
Zone R6
Evacuat ion Zone 2
Resident ial Uni ts 5
Stories 4
Basement Yes
Structure Type Br ick
Elevator? Walk Up
Year Bui l t 1900
Year Al tered 1997
Subsidy LIHTC
Subsidy Start Year 1998
KEY LONG-TERM RESILIENCE CHALLENGES
1. Basement flooding
2. Flooding from attached building
3. Equipment is located below BFE
4. Basement is accessed through an exterior hatch
5. Others?
PROPOSED SOLUTIONWET FLOODPROOFING
WET FLOODPROOFINGDETAILS
WET FLOODPROOFINGIMPLEMENTATION PLAN
WET FLOODPROOFINGREGULATORY BARRIERS
WET FLOODPROOFINGOTHER CHALLENGES
MOST COST-EFFECTIVE SOLUTION(NOTE: If you find a solution that will be more cost effective in the long run that wet floodproofing, please use the following supporting slides to illustrate the idea and its challenges.)
COST-EFFECTIVE SOLUTIONDETAILS
COST-EFFECTIVE SOLUTIONIMPLEMENTATION PLAN
COST-EFFECTIVE SOLUTIONREGULATORY BARRIERS
COST-EFFECTIVE SOLUTIONOTHER CHALLENGES
BEST SOLUTION(NOTE: If you find a solution that team agrees is better for this building than what you’ve already addressed, please use the following supporting slides to illustrate the idea and its challenges.)
BEST SOLUTIONDETAILS
BEST SOLUTIONIMPLEMENTATION PLAN
BEST SOLUTIONREGULATORY BARRIERS
BEST SOLUTIONOTHER CHALLENGES
Are any or all of these solutions models for retrofitting other, similar buildings?
DISCUSSION QUESTIONS