4- time scaled network

6

Click here to load reader

Upload: tucd2k42

Post on 02-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 4- Time Scaled Network

8/10/2019 4- Time Scaled Network

http://slidepdf.com/reader/full/4-time-scaled-network 1/6

 

Tutorial # 4

Time Scaled

Network

King Saud University

College of Engineering

 

GE 404 Engineering Management

Page 2: 4- Time Scaled Network

8/10/2019 4- Time Scaled Network

http://slidepdf.com/reader/full/4-time-scaled-network 2/6

The project network is plotted to a time scale as

a one dimensional line (similar to Gantt chart).

The horizontal length is equal to its estimated

time duration  

(beginning at either its ES and/or

ending with its EF values).

TIME 

SCALED

DIAGRAM

Page 3: 4- Time Scaled Network

8/10/2019 4- Time Scaled Network

http://slidepdf.com/reader/full/4-time-scaled-network 3/6

Activity Predecessor(s) Duration

A - 4

B - 5

H A 5

G A,B 3

F H 4

E G,F 3

D E 2

C E 1

I D 5

J C,D 3

K - 2

L K,G 4

Example1For a small Engineering project listed below, Draw the Early Start

 project schedule using Time- scaled network

Page 4: 4- Time Scaled Network

8/10/2019 4- Time Scaled Network

http://slidepdf.com/reader/full/4-time-scaled-network 4/6

Activity Predecessor(s) Duration

A - 4

B - 5

H A 5

G A,B 3

F H 4

E G,F 3

Activity Predecessor(s) Duration

D E 2

C E 1

I D 5

J C,D 3

K - 2

L K,G 4

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

A

B

H

G

F E

D

C J

K

I

L

Activity A H F E D I B G C J K L

FF 0 0 0 0 0 0 0 0 1 2 6 11

TF 0 0 0 0 0 0 5 5 3 2 17 11

Duration; 23 Critical path : A-H-F-E-D-I

Page 5: 4- Time Scaled Network

8/10/2019 4- Time Scaled Network

http://slidepdf.com/reader/full/4-time-scaled-network 5/6

Act. Depends on Time Act. Depends on Time Act. Depends on Time

A None 4 D C, G 3 G F 4

B A 6 E None 3 H None 1

C B 7 F A, E 4 I H 5

Example2:For a small Engineering project listed below, draw the Early Start project

schedule using Time-scaled network , and determine the total & free float

and critical path. 

Page 6: 4- Time Scaled Network

8/10/2019 4- Time Scaled Network

http://slidepdf.com/reader/full/4-time-scaled-network 6/6

Act. Depends on Time Act. Depends on Time Act. Depends on Time

A None 4 D C, G 3 G F 4

B A 6 E None 3 H None 1

C B 7 F A, E 4 I H 5

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

A

E

B

F

C

D

H I

G

Activity A B C D E F G H I

FF 0 0 0 0 1 0 5 0 14

TF 0 0 0 0 6 5 5 14 14

Duration; 20 Critical path : A-B-C-D