4 high work concrete bp mr alan wan mr cc wai
DESCRIPTION
CON.TRANSCRIPT
-
2
0
0
5
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
Standing Committee on Concrete Technology Annual Concrete Seminar 2007
High Workability Concrete for Bored Pile Construction
CC Wai, Alan Wan Gammon Construction Limited
-
iR
l
l
A
.
d
e
t
m
i
i
L
n
o
i
c
t
u
r
s
t
n
o
C
n
o
m
m
a
G
6
0
0
2
2
g
h
t
s
R
e
s
e
r
v
e
d
.
-
Week 2
Week 3
Week 1
Sequence of Work in Bored Pile Construction
Sun Mon Tue Wed Thu Fri Sat
Excavation
Excavation Rock Drilling
Rock Drilling Airlifting Concrete Cage
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
3
-
.
d
v
e
r
s
e
e
R
s
t
h
g
i
R
l
l
A
.
d
e
t
i
m
i
L
n
o
i
c
t
u
r
s
t
n
o
C
n
o
m
m
a
G
6
0
0
2
4
-
Presentation Scope
Method of Concreting Bored Pile
Problems and Defects
Deficiencies in Current Practice
Proactive Approach
The Way Forward
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
5
-
Concreting of Bored Pile
.
d
v
e
r
s
e
e
R
s
t
h
g
i
R
l
l
A
.
d
e
t
i
m
i
L
n
o
i
c
t
u
r
s
t
n
o
C
n
o
m
m
a
G
6
0
0
2
6
-
General Setup
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
Ramp
Skip
Tremie Pipe
Concreting Platform
Concrete Truck
Concrete
7
-
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
Stages in Bored Pile Concreting
(1) (2) (3) (4)
Extract Tremie Pipe Extract Temporary Casing
Concrete Overbreak
Drop in Concrete
Head
Tremie Pipe
Temporary Casing
2
0
0
6
G
a
m
8
-
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
9
Cement Grout
Concrete
-
QA / QC
Slump tests / Flow table
Check temperature ( 32o)
Cube samples to determine concrete strength
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
10
-
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
11
Concreting Takes Many Hours
12:00 14:00
18:00 21:00
-
30
25
o
u
r
s
)
20
(
h 15
10
T
i
m
e
5
0 0 20 40 60 80 100
Pile Length (m)
Concreting Time Varies With Pile Length
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
12
-
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
13
Slump Varies With Time
Time
S
l
u
m
p
-
Common Problems Encountered
Temporary casing cannot be withdrawn
Tremie pipe cannot be withdrawn
Blocked tremie pipe
Reinforcement cage rides up with temporary casing
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
14
-
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
15
Defects
-
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
16
Honeycomb
Reduced workability affects self compaction
-
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
17
Air Voids
-
Entrapped Air Inside Concrete During Pouring
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
Air Voids
(1) (2) (3) 18
-
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
19
Segregated Concrete
Additive quantity needs fine-tuning
-
Remedial Actions
Grouting
High pressure water jet to remove weak concrete, followed by pressure grouting
Stitched pile
Additional pile
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
20
-
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
21
Deficiencies in Current Practice
-
First In . Last Out
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
16
17
1 *
2
3
18
First few truckloads need to remain workable throughout concreting
* Indicate order of truckload
22
-
Deficiencies in Current Practice
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
Large piles / deep piles mean large concrete volume
Specification / Contract Document Single slump value specified on drawing Workability vs time not considered Lack of flexibility in interpretation
Quality control Need to control consistency in material
properties
23
-
The Proactive Approach
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
Need to Consider .. Specification Concrete volume (related to pile size
and depth) Site constraints (physical or
environmental restrictions) Site location (travel time to site from
batching plant) 24
-
Pile Acceptance
Time
Concrete Performance
Material Consistency
Concrete Site Construction Volume Constraints Procedure
Route to Pile Acceptance
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
25
-
Delivery ~ 3 hours
Grade 45/20 Designed slump 200mm
Workability 5 hours
SUCCESS STORY
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
Hong Kong Shenzhen Western Corridor
26
-
SUCCESS STORY Hong Kong Shenzhen Western Corridor
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
Supplier formulated a special concrete mix with enhanced workability
Engineer relaxed concreting time to 5 hours
Contractor checked workability prior to pouring
Side-effect : minor segregation, need to pour additional concrete to avoid undercasting
27
-
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
28
Way Forward
-
Concrete Triangle
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
Designer
Contractor Concrete Supplier
Concrete Quality / Performance
Constructability
Slump Retention Consistency
29
-
2
0
0
6
G
a
m
m
o
n
C
o
n
s
t
r
u
c
t
i
o
n
L
i
m
i
t
e
d
.
A
l
l
R
i
g
h
t
s
R
e
s
e
r
v
e
d
.
30
The End
Structure Bookmarks2005 Gammon Construction Limited. All Rights Reserved Standing Committee on Concrete Technology. Annual Concrete Seminar 2007. High Workability Concrete for. Bored Pile Construction. High Workability Concrete for. Bored Pile Construction. CC Wai, Alan Wan. Gammon Construction Limited. 2006 Gammon Construction Limited. All 2 Sequence of Work in Bored Pile Construction. Sequence of Work in Bored Pile Construction. Sun Sun Sun Mon Tue Wed Thu Fri Sat
Week 1 Week 2 Excavation Excavation Excavation Rock Drilling Week 3 Rock Drilling Rock Drilling Rock Drilling Airlifting
Concrete Cage 2006 Gammon Construction Limited. All Rights Reserved. 2006 Gammon Construction Limited. All Rights Reserved. 4
Presentation Scope. Presentation Scope. Method of Concreting Bored Pile.
Problems and Defects
Deficiencies in Current Practice.
Proactive Approach
The Way Forward
2006 Gammon Construction Limited. All Rights Reserved. 2006 Gammon Construction Limited. All Rights Reserved. 6 Concreting of Bored Pile
General Setup. General Setup. 2006 Gammon Construction Limited. All Rights Reserved. Ramp Skip Tremie Pipe Concreting Platform Concrete Truck Concrete
Stages in Bored Pile Concreting. Stages in Bored Pile Concreting. (1) (2) (3) (4) Extract Tremie Pipe Extract Temporary Casing Concrete Overbreak Drop in Concrete Head Tremie Pipe Temporary Casing 2006 Gam 2006 Gammon Construction Limited. All Rights Reserved. 9 Cement Grout Concrete
QA /QC. QA /QC. . . . Slump tests / Flow table
. . Check temperature ( 32) o
. . Cube samples to determine concrete strength
2006 Gammon Construction Limited. All Rights Reserved. 2006 Gammon Construction Limited. All Rights Reserved. 11 Concreting Takes Many Hours 12:00 14:00 18:00 21:00 Concreting Time Varies With Pile Length. 2006 Gammon Construction Limited. All Rights Reserved. Time (hours) 30. 25. 20. 15. 10. 5. 0. Figure0 20 40 60 80 100. Pile Length (m). 0 20 40 60 80 100. Pile Length (m).
2006 Gammon Construction Limited. All Rights Reserved. 13 Slump Varies With Time Time Slump
Common Problems Encountered. Common Problems Encountered. Temporary casing cannot be withdrawn.
Tremie pipe cannot be withdrawn
Blocked tremie pipe
Reinforcement cage rides up with temporary casing
2006 Gammon Construction Limited. All Rights Reserved. 2006 Gammon Construction Limited. All Rights Reserved. 15 Defects 2006 Gammon Construction Limited. All Rights Reserved. 16 Honeycomb Reduced workability affects self compaction 2006 Gammon Construction Limited. All Rights Reserved. 17 Air Voids
Entrapped Air Inside Concrete During Pouring. Entrapped Air Inside Concrete During Pouring. 2006 Gammon Construction Limited. All Rights Reserved. Air Voids (1) (2) (3) 2006 Gammon Construction Limited. All Rights Reserved. 19 Segregated Concrete Additive quantity needs fine-tuning
Remedial Actions. Remedial Actions. Grouting
High pressure water jet to remove weak. concrete, followed by pressure grouting.
Stitched pile
Additional pile
2006 Gammon Construction Limited. All Rights Reserved. 2006 Gammon Construction Limited. All Rights Reserved. 21 Deficiencies in Current Practice
First In . Last Out. First In . Last Out. 2006 Gammon Construction Limited. All Rights Reserved. First few truckloads need to remain workable throughout concreting 16 17 1 * 2 3 18
* Indicate order of truckload
Deficiencies in Current Practice. Deficiencies in Current Practice. 2006 Gammon Construction Limited. All Rights Reserved. . . . Large piles / deep piles mean large concrete volume
. . . Specification / Contract Document
. . . Single slump value specified on drawing
. . Workability vs time not considered
. . Lack of flexibility in interpretation
. . Quality control
Need to control consistency in material properties
The Proactive Approach. The Proactive Approach. 2006 Gammon Construction Limited. All Rights Reserved. Need to Consider .. Specification
Concrete volume (related to pile size and depth)
Site constraints (physical or. environmental restrictions).
Site location (travel time to site from batching plant)
Route to Pile Acceptance. Route to Pile Acceptance. Pile Acceptance Time Concrete Performance Material Consistency 2006 Gammon Construction Limited. All Rights Reserved. Concrete Site Construction. Volume Constraints Procedure.
SUCCESS STORY. SUCCESS STORY. 2006 Gammon Construction Limited. All Rights Reserved.
Hong Kong Shenzhen Western Corridor. Hong Kong Shenzhen Western Corridor. Delivery ~ 3 hours Delivery ~ 3 hours Figure
Grade 45/20
Designed slump 200mm
Workability 5 hours
Figure
SUCCESS STORY. Hong Kong Shenzhen Western Corridor. SUCCESS STORY. Hong Kong Shenzhen Western Corridor. 2006 Gammon Construction Limited. All Rights Reserved. Supplier formulated a special concrete mix with enhanced workability
Engineer relaxed concreting time to 5 hours.
Contractor checked workability prior to pouring
Side-effect : minor segregation, need to pour additional concrete to avoid undercasting
2006 Gammon Construction Limited. All Rights Reserved. 28 Way Forward Concrete Triangle. 2006 Gammon Construction Limited. All Rights Reserved. Designer Contractor Concrete Supplier Concrete Quality / Performance Constructability Slump Retention Consistency 2006 Gammon Construction Limited. All Rights Reserved. 30 The End