1 FACULTY OF IVIL ENGINEERING & EARTH RESOURCES INTRODUCTION/ EXECUTIVE SUMMARY Project title for the project was proposed 20 units double storey quarters for foreign lecturer in UMP. Quarters was proposed due to the continuously increasing number of foreign lecturer in University Malaysia Pahang (UMP). Regarding to this condition, accommodation place for foreign lecturer that already exists in UMP is not enough. Housing project is proposed in order to fix this problem and provide more accommodation place in campus. Another objective for the project is to provide a convenient and comfortable living accommodation for them with the design of houses. The houses design of the project is suitable for foreign lecturer who brings along their family together during the period they have their position at UMP. The project site proposed was located at the back area of Kolej Kediaman 2 in campus. 20 units of quarter were proposed in this project. The reason to choose the project location in UMP campus is because it is convenient for foreign lecturer went to the work place every day. The distance from the live place to work place is more shorten compare from the nearest residential area. For information, the nearest residential area is about 4KM far from the campus. The boundary of a unit of a quarter is 23m x 25m. Specification of the houses proposed is 5 bedroom, 1 master bedroom, 5 toilets, 1 wet kitchen, 1 dry kitchen, 1 family area, 1 living room, porch, and entrance hall. Modern quarter design that proposed will give harmony and comfortable living area for foreign lecturers. This is benefit for them in many aspects.

Upload: miraara

Post on 13-Oct-2014

20 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: 3p Proposal Group 25

1

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

INTRODUCTION/ EXECUTIVE SUMMARY

Project title for the project was proposed 20 units double storey quarters for foreign

lecturer in UMP. Quarters was proposed due to the continuously increasing number of foreign

lecturer in University Malaysia Pahang (UMP). Regarding to this condition, accommodation

place for foreign lecturer that already exists in UMP is not enough. Housing project is proposed

in order to fix this problem and provide more accommodation place in campus. Another

objective for the project is to provide a convenient and comfortable living accommodation for

them with the design of houses. The houses design of the project is suitable for foreign lecturer

who brings along their family together during the period they have their position at UMP.

The project site proposed was located at the back area of Kolej Kediaman 2 in campus.

20 units of quarter were proposed in this project. The reason to choose the project location in

UMP campus is because it is convenient for foreign lecturer went to the work place every day.

The distance from the live place to work place is more shorten compare from the nearest

residential area. For information, the nearest residential area is about 4KM far from the campus.

The boundary of a unit of a quarter is 23m x 25m. Specification of the houses proposed is

5 bedroom, 1 master bedroom, 5 toilets, 1 wet kitchen, 1 dry kitchen, 1 family area, 1 living

room, porch, and entrance hall. Modern quarter design that proposed will give harmony and

comfortable living area for foreign lecturers. This is benefit for them in many aspects.

Page 2: 3p Proposal Group 25

2

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

PROBLEM STATEMENTS

In this recent year, numbers of foreign lecturer in Universiti Malaysia Pahang (UMP) is

increased. The increasing numbers of foreign lecturers in UMP are expected will continuously

increase for next few years. Regarding to this condition, it brings some problems to university

especially the accommodation problem. The increment of new foreign lecturers in UMP by times

has led to inadequate accommodation for them. The nearest residential is quite far from the

campus which is about 25km. Since they are newcomers in our country, it must be hard for them

to adapt with new environment that lead to difficulties in finding accommodation here.

Another problem is the existing accommodations are not appropriate for lecturers whom choose

to live with their families here. As far as we concern, the size of the accommodation is relatively

small and there is no enough room provided which will probably make them feel uncomfortable.

PROJECT OBJECTIVES

i) General Objective

The general objective of the project is to improve the quality of the accommodation for

foreign lecturers with conducive environment.

ii) Specific Objective

The specific objective of the project is to build a more comfortable accommodation for

foreign lecturers and their family. Accommodation with houses design will provide a

convenient living for them who live with family. It is also to reduce the time consumed

cause by the distance from university campus to their home. Besides that, the specific

objective is to meet the increment of new foreign lecturers in UMP by times.

Page 3: 3p Proposal Group 25

3

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

PROJECT DESCRIPTION

This project will consist of 20 units of quarters for foreign lecturer. Double storey

quarters with 5 bedroom, 1 master bedroom, 5 toilet, 1 wet kitchen, 1 dry kitchen, 1 family area,

1 living room, porch and entrance hall. The lot for every quarters is 122m x 127m including land

besides the house.

4.1 Scope of Works

1. Project Proposal

Briefing Project Requirement & Expectations

Selection of Project Title

Identifying the Study Area & the Scope of works

Preparation & Presentation of Project proposal

2. Project Planning

Information Gathering & Data Collection

Identifying Project Options & Alternatives

Preparation & Presentation of Project Progress Report 1

Page 4: 3p Proposal Group 25

4

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

3. Project Design

Finalising Project Layout Plan

Designing Typical Sections

Preparation & Presentation of Project Progress Report 2

4. Preparation of Tender Document

Preparing Bill of Quantities

Estimating Project Course

Preparation & Presentation of the Final Report

Page 5: 3p Proposal Group 25

5

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

4.2 Gantt Chart

Page 6: 3p Proposal Group 25

6

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

PROJECT OUTPUT

From this project , the construction of this quarters will bring many positive things such

as the project will reduces the problem the placement of foreign lecturer that work at Universiti

Malaysia Pahang (UMP) that have families.

The other output that had been discovered is, this project can give more comfortable

residency to all foreign lecturer, in addition to increasing enthusiasm for teaching at this

university.

Other than that, it can reduces the cost of living for foreigner lecturer and shorten the

journey of foreigner lecturer to go teaching when they live inside the university.

EXPECTED PROJECT OUTCOME

Expected outcome from this project is to give more conducive lifestyle and conducive

environment to foreigner lecturer also in order to build more resident for foreigner lecturer.

Page 7: 3p Proposal Group 25

7

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

APPENDIXES

Propose idea: Double Storey Quarters for Foreign Lecturers

Below are the figures of the propose site:

Figure 1

Figure 2

Page 8: 3p Proposal Group 25

8

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

Figure 3

Figure 4

Page 9: 3p Proposal Group 25

9

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

Figure 5

Figure 6

Page 10: 3p Proposal Group 25

10

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

ORGANIZATION CHART

ENGR. NORHAIZA BINTI GHAZALI

PROJECT DIRECTOR

WAFA’ BINTI MOHD SALLEH

PROJECT MANAGER

GEOTECHNICAL

ENGINEER

ABD RAHIM BIN IBRAHIM

HIGHWAY/TRAFFIC

ENGINEER

LEE YING YING

CIVIL&STRUCTURE

ENGINEER

MOHD SOBRI BIN IBRAHIM

Page 11: 3p Proposal Group 25

11

FACULTY OF IVIL ENGINEERING & EARTH RESOURCES

LOCATION LAYOUT/PLAN