NODE-B Commissioning guidelines
JYOSTNA INFRASTRUCTURE PRIVATE LIMITED
Er Himanshu Maurya+919807888440
![Page 2: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/2.jpg)
PLEASE ENSURE THE FOLLOWING IP AT YOUR LAPTOP FOR CONNECTING NODE-B
![Page 3: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/3.jpg)
ENSURE THAT SOFTWARE VERSION OF VERSION OF WN6.0 IS INSTALLED IN YOUR LAPTOP
This can be cross checked by clicking About option on left side of the BTS Manager Window
![Page 4: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/4.jpg)
CONNECT TO THE NODE-B
User Name: Nemuadmin
Password: nemuuser
The following Pop-up Window will be observed.
Click on Update SW option.
![Page 5: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/5.jpg)
CLICK ON CONTINUE HERE FOR UPDATING FILE
![Page 6: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/6.jpg)
BROWSE HERE FOR FILE. CLICK ON UPDATE. ONCE THE SOFTWARE IS UPDATED, THE HARDWARE WILL BE VISIBLE (in uncommissioned state)
![Page 7: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/7.jpg)
NOW START COMMISSIONING. CLICK ON TEMPLATE IN COMMISSIONING TYPE. BROWSE THE GOLDEN COMMISSIONING FILE (specific for RNC). THEN CLICK NEXT
![Page 8: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/8.jpg)
EDIT SITE NAME, LOCATION, DESCRIPTION, BTS ID, TRS (Transmission) IP, BTS IP, RNC IP & NTP SERVER IP. (most imp)
![Page 9: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/9.jpg)
CLICK ON CLOSE
![Page 10: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/10.jpg)
CLICK ON NEXT.
![Page 11: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/11.jpg)
CLICK NEXT. (Note: 4 E1s in IMA 33 would be already selected)
![Page 12: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/12.jpg)
CLICK NEXT (Note: IF 1 (E1) AND IF2 (E2) in TIMING SOURCE already done)
![Page 13: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/13.jpg)
CLICK NEXT. (Note: Traffic already defined)
![Page 14: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/14.jpg)
CLICK NEXT. (Note: TRAFFIC already mapped) (VP1,VP0 and their VCs)
![Page 15: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/15.jpg)
CLICK NEXT (Note: DCN INTERFACE already mapped)
![Page 16: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/16.jpg)
CLICK NEXT. (Note: RNC IP should be in DEFAULT GATEWAY IP)
![Page 17: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/17.jpg)
CLICK ON NEXT
![Page 18: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/18.jpg)
CLICK NEXT. (Note: Iub sync in use would be already clicked)
![Page 19: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/19.jpg)
CLICK NEXT. (Note: CELLS already created with 20W power
![Page 20: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/20.jpg)
CLICK NEXT
![Page 21: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/21.jpg)
CLICK NEXT. (Note: UARFCN already inserted as per plan)
![Page 22: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/22.jpg)
CLICK NEXT.
![Page 23: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/23.jpg)
CLICK NEXT
![Page 24: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/24.jpg)
CLICK NEXT
![Page 25: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/25.jpg)
CLICK NEXT
![Page 26: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/26.jpg)
CLICK ON SEND PARAMETERS. BY THIS THE PARAMETERS WOULD BE SENT TO NODE-B
![Page 27: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/27.jpg)
CLICK NEXT
![Page 28: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/28.jpg)
CLICK NEXT
![Page 29: 3G COMMISSIONING STEPS](https://reader035.vdocuments.mx/reader035/viewer/2022081419/55cdee4fbb61eb13538b4581/html5/thumbnails/29.jpg)
CLICK FINISH. SAVE THE COMMISSIONING FILE & COMISSIONING REPORT ON YOUR LAPTOPS AND INCLUDE COMMISSIONING REPORT’s HARD COPY IN SITE FOLDER.