35w tunnel presentation - bonding request

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 35W Tunnel Presentation - Bonding Request

    1/7

    City of MinneapolisI-35W North & South Storm Tunnel

    S.F. 194

    35W South Tunnel Outfall 35W North Tunnel Outfall

  • 7/29/2019 35W Tunnel Presentation - Bonding Request

    2/7

    35W North TunnelConstructed in 1965 Material concrete (not reinforced)

    8 14 foot diameter 9,415 feet / 1.8 miles in length Roughly 80 100 feet below the surface 62% Minneapolis Flow / 38% MnDOT Flow Funding need $5.5 million

    35W South TunnelConstructed 1961 to 1964 Material concrete (not reinforced) 8 14 foot diameter 24,540 feet / 4.7 miles in length Roughly 80 100 feet below the surface 85% Minneapolis Flow / 15% MnDOT Flow Funding need - $14 million

  • 7/29/2019 35W Tunnel Presentation - Bonding Request

    3/7

    35W North Tunnel Tunnel built to accommodate citystorm water that was originally draining

    to the sanitary system and freewaydrainage Agreements between the City ofMinneapolis and MnDOT regarding thetunnel construction and maintenance

    35W South Tunnel Original flow - west to east to theMississippi River Freeway bisected the original flowpattern Tunnel built to accommodate city andfreeway drainage Agreements between the City ofMinneapolis and MnDOT regarding thetunnel construction and maintenance

  • 7/29/2019 35W Tunnel Presentation - Bonding Request

    4/7

    Current Bonding Request2012 $4.5 million State, $4.5 million Local

    * Request based on 2006 Tunnel Condition Assessment Report which identified segments of the tunnel and cost estimates.

    Current Bonding Request2013 $4.5 million State, $4.5 million Local

  • 7/29/2019 35W Tunnel Presentation - Bonding Request

    5/7

    Deficiencies to beAddressed

    Groundwater Longitudinal Cracks

    Liner FailureVoids outside the tunnel

    Holes in the Liner

    Groundwater Longitudinal Cracks

    Liner FailureVoids outside the tunnel

    Holes in the Liner

  • 7/29/2019 35W Tunnel Presentation - Bonding Request

    6/7

    City of MinneapolisI-35W North & South Storm Tunnel

    Solutions Removing sedimentation and debris from the tunnel

    Sealing open joints, fractures, and cracks

    Repairing holes and erosion in the tunnel liner

    Grouting voids outside of the liner

    Solutions Removing sedimentation and debris from the tunnel

    Sealing open joints, fractures, and cracks

    Repairing holes and erosion in the tunnel liner

    Grouting voids outside of the liner

  • 7/29/2019 35W Tunnel Presentation - Bonding Request

    7/7

    City of MinneapolisI-35W North & South Storm Tunnel

    Need to manage the condition before it becomes asafety issue

    The City of Minneapolis needs to continue to takerain water out of the sanitary system and into thestorm water system to avoid Combined SewerOverflows (CSO) and to meet the requirements ofthe Metropolitan Council Environmental Services(MCES) Inflow and Infiltration (I/I) Program

    MnDOT supports this work and funding request

    Need to manage the condition before it becomes asafety issue

    The City of Minneapolis needs to continue to takerain water out of the sanitary system and into thestorm water system to avoid Combined SewerOverflows (CSO) and to meet the requirements ofthe Metropolitan Council Environmental Services(MCES) Inflow and Infiltration (I/I) Program

    MnDOT supports this work and funding request