CREATE 3D CONTOURS FROM THE SURVEY

Page 3: 3 d mine plan

CREATE 3D CONTOURS FROM THE SURVEY

72 MTRS

Page 4: 3 d mine plan

ENTIRE MINE TO BE DIVIDED INTO 10 MTR BENCHES

Page 5: 3 d mine plan

EXISTING ROAD AND CLIFF OF 72 MTRS HEIGHT

72 MTRS

Page 6: 3 d mine plan

CROSS SECTIONS OF ROAD DESIGNED WITH 1:16 MOTORABLE SLOPE

Page 7: 3 d mine plan

PHOTO REALISTIC (TO THE SCALE GRAPHIC DESIGN )

72 MTRS

Page 8: 3 d mine plan

FLAT GROUND 50 x 200 MTRS ON THE TOP OF 72 MTRS CLIFF

START OF EXCAVATION

72 MTRS

Page 9: 3 d mine plan

EXCAVATIONS IN 10 MTR BENTCHES

Page 10: 3 d mine plan

AS PER THE SUITABILITY OF EXCAVATOR AVAILABLE

Page 11: 3 d mine plan

FLAT GROUND DESIGNED FOR TWO OPTIONS

OPTION 1: DOZE BLASTED MATERIAL DIRECTLY FROM 72 MTRS HEIGHT

OPTION 2: INSTALL PRIMARY CRUSHER & CONVEY 200mm CRUSHED AGGREEGATE FROM 72 MTRS HEIGHT

Page 12: 3 d mine plan

SHORTEST, SAFEST, MOTORABLE ROAD DESIGN

Page 13: 3 d mine plan

FIRST BENCH OF 10 MTRS HEIGHT

58292 cum

Page 14: 3 d mine plan

SECOND BENCH…..

218744 cum.

Page 15: 3 d mine plan

THIRD BENCH…..

393812 cum.

Page 16: 3 d mine plan

EVERY BENCH PRE-DESIGNED

605086 cum.

Page 17: 3 d mine plan

EVERY CO-ORDINATE IN THE DESIGN IS KNOWN

822805 cum.

Page 18: 3 d mine plan

EVERY STEP PRE-CONFIGURED IN THE MINE PLAN WHICH WILL GO FOR YEARS

1032266 cum.

Page 19: 3 d mine plan

CAN VISUALISE ANY COMPLICATION WHICH MAY ARISE AFTER SOME YEARS

1263592 cum.

Page 20: 3 d mine plan

VOLUME CALCULATIONS ARE ACCURATE AS IT’S A CAD DESIGN

1507198 cum.

Page 21: 3 d mine plan

SLOPE STABILIZATION AND DEWATERING POINTS ARE DEFINED

1703947 cum.

Page 22: 3 d mine plan

EASY TO UNDERSTAND, EASY TO CONVINCE, EASY TO UPDATE FOR YEARS

Page 23: 3 d mine plan

ONE SINGLE DRAWING START TO END

Page 24: 3 d mine plan

GOOGLE EARTH IMAGES