Assembly of a Wall with cost and micro production time simulation.
Individual part by Emanuele Bianco 3J group 2
Assembly of a wall- table of contents
1. Documents 2. Wall chosen 3. Wall assembly-timber frame 4. Wall assembly-plywood 5. Wall assembly-insulation 6. Wall assembly-lathes 7. Wall assembly-cladding in walls workshop 8. Wall assembly-assembly wall with gr.floor 9. Wall assembly-cladding at gr.floor workshop 10. Wall assembly-assembly with ceiling 11. Wall assembly-plasterboards 12. Wall assembly-connection with foundation wall n 1 13. Wall assembly-window profile 14. Wall assembly-connection between two units top view 15. Wall assembly-connection between two units section 16. Production flow chart walls 17. Time estimation 18. Manufacturing cost 19. Cost comparison
Assembly of a wall- documents
Property
Analysis
Property
analysis of
timber
Overview of the walls in unit 1 and Wall chosen
Overview of the production flow of wall n. 1 between the workshops
Standard wall construction
Connection between two units/ top view details
Timber frame construction of all units
details
Unit 1 Unit 2
Unit 3
Production flow chart details
120.30 H for manufacturing of Wall n 1 in fabric
Micro production time simulation details
Manufacturing cost/ elemental cost sigma ( blu book netto uden salær)
details
Manufacturing cost wall n 1: 14270,285DKK
Database Sigma cost wall n 1* 20078,00 DKK
*Prisdatabasen2012/netto/nybyggeri
Cost comparison details
1: Manufacturing cost wall n 1: 14270,285DKK 2:Database Sigma cost wall n 1* 20078,00 DKK
Cost reduction: 29 %