CLUSTER C7-5Indosat 2013 Network Roll Out Phase 2 DT Report

This is to certify that CLUSTER C7-5 has achieved the taget acceptance requirements in accordance with the Indosat 2013 Network Roll Out Phase 2.

Indosat 2G Ericsson

Signature:

Date:

Signature:

Date:

Name: Name:

Date Date

Page 2: 2G DT REPORT Baseline Cluster

CLUSTER C7-5 Indosat 2013 Network Roll Out Phase 2 DT Report

Page 3: 2G DT REPORT Baseline Cluster

Contents1 INTRODUCTION......................................................................................41.1 Measurement Information......................................................................41.2 Cluster Geographical Area and Definition...........................................42 DRIVE TEST ROUTE...............................................................................53 METHODOLOGY.....................................................................................63.1 Drive Test Equipment Set-Up................................................................63.1.1 Indosat 2012 Network Roll Out Phase 2 Active Measurement...........64 DRIVE TEST STATISTICAL MEASUREMENT RESULT.......................75 SITE RF PLOTS.......................................................................................85.1 RX_LEVEL IDLE......................................................................................85.2 Rx_LevSubdBm by SHORT CALL.........................................................95.3 RX_QUAL by SHORT CALL.................................................................105.4 SQI by SHORT CALL............................................................................115.5 FREQUENCY BAND by IDLE MODE...................................................125.6 Cell List..................................................................................................136 CONCLUSION.......................................................................................14

Tables & FiguresTable 1: ………………………………………….5Table 2: List and activity……………....………………...………… 5Table 3: Active UE Configuration and Setup……………………………………..6Table 4: Indosat 2012 Network Roll Out Phase 2 AcceptanceForm…………………………………………..…………………………………7

Figure 1 Drive Test Acceptance Cluster and Route........................................5Figure 2 Active Drive Test Configuration.........................................................6Figure 3 RX Level Plot.....................................................................................8Figure 4 RX Qual Plot....................................................................................11Figure 5 SQI Plot...........................................................................................11Figure 6 Frequency Band Plot.......................................................................12

Page 4: 2G DT REPORT Baseline Cluster

1 INTRODUCTION

This document presents the Indosat 2013 Network Roll Out Phase 2 for cluster based on active measurement of the network drive test performance.

1.1 Measurement Information

CLUSTER C7-5 Baseline Achievement Swap Date Drive Test Date 04 November 2013    

Table 1: Drive Test Information

1.2 Cluster Geographical Area and Definition

Listed below are the list of sites within the test cluster, as well as its status during the measurement period.

NO SITE ID SITE NAME Longitude Latitude BSC Sub CLUSTER1 03KRW004 GANTIONO 107.36656 -6.36878 BKWN05 C7-52 03KRW008 KOSAMBIHUB_IM3_SMI 107.38305 -6.37675 BKWN05 C7-53 03KRW012 KLARI_IM3 107.34402 -6.35633 BKWN01 C7-54 03KRW013 SURYACIPTA_IM3 107.33822 -6.38654 BKWN05 C7-55 03KRW032 TELAGASARI 107.38531 -6.28671 BKWN01 C7-56 03KRW040 TAMELANG 107.40179 -6.38624 BKWN05 C7-57 03KRW054 DARAWOLONG 107.41174 -6.32956 BKWN05 C7-58 03KRW092 BELENDUNG 107.38136 -6.32937 BKWN05 C7-59 03KRW099 CILEWO_SMI 107.424 -6.29244 BKWN05 C7-5

10 03KRW102 CIRANGGON 107.36517 -6.29127 BKWN01 C7-511 03KRW115 CICANGOR 107.37767 -6.35054 BKWN05 C7-512 03KRW135 RAGOG 107.35073 -6.41259 BKWN05 C7-513 03KRW176 BENGLE_SMI 107.35744 -6.33055 BKWN01 C7-514 03KRW181 PASIRTALAGA_SMI 107.38234 -6.30431 BKWN01 C7-515 03KRW182 RAWAUNGU_SMI 107.34625 -6.366231 BKWN05 C7-516 03KRW186 CENGKONG_SMI 107.39922 -6.35904 BKWN05 C7-517 03KRW199 WALAHAR 107.37965 -6.39576 BKWN05 C7-518 03KRW212 CICALUNG_PL 107.39331 -6.3837 BKWN05 C7-5

Table 2: Group Site List and activity

Page 5: 2G DT REPORT Baseline Cluster

2 DRIVE TEST ROUTE

This is the agreed drive test route between Indosat and Ericsson for this Site acceptance.

Figure 1: Drive Test Acceptance Cluster and Route

Page 6: 2G DT REPORT Baseline Cluster

3 METHODOLOGY

3.1 Drive Test Equipment Set-Up

3.1.1 Indosat 2013 Network Roll Out Phase 2 Active Measurement

The Indosat 2012 Network Roll Out Phase 2 is done by drive-testing in cluster basis. The KPI is evaluated in the RF related and the services based related. Configuration of active measurement as shown below:

Figure 3 : Active Drive Test configuration

Equipment Set Service Configuration KPI

MS 1 Idle Mode Lock 2G Rx Level Full

MS 2 Voice Short Call Lock 2G, Connected = 50 s, Idle = 15 s CSSR, CDR and HOSR

MS 3 R99 Short Download (1 MB) Lock 3G, Ftp download PDP CSSR and DCR

MS 4 Scanner Lock F1 = 10713 CPICH RSCP and CPICH EcIo

Table 5 : Active UE Configuration and Setup

Page 7: 2G DT REPORT Baseline Cluster

4 DRIVE TEST STATISTICAL MEASUREMENT RESULT

MEASUREMENT WEIGHTING Event

BASELINE ACHIEVEMENT REMARKS

Sample % Sample %

CSSR Voice 15Call Setup 133

99,25% ImprovedCall Attempt 134

CDR Voice 15 Dropped Call 0 0,00% Maintained

HOSR 10Handover 107

98,13% MaintainedHandover Failure 2

MEASUREMENT WEIGHTING Range Sample % Sample % REMARKS

RX Lev 15>= -85 dBm 4262 91,15%

Improved< -85 dBm 414 8,85%

RX Qual 10<=5 55613 88,47%

Maintained>5 7251 11,53%

SQI 35> 18 37238 83,39%

Slightly Degrade<=18 7418 16,61%

FINAL SCORE

DT Score (Max 40%)

Table 4: Indosat 2013 Network Roll Out Phase 2 Acceptance Form

Page 8: 2G DT REPORT Baseline Cluster

5 SITE RF PLOTS

5.1 RX_LEVEL IDLE

Baseline:

Figure 3: Rx_Level Plot

RX Lev Idle Mode Weighting BASELINE ACHIEVEMENT

Sample % Sample %

RxLev >= -85 dBm Idle 35,00% 4262 91,15%

RxLev < -85 dBm 414 8,85%

Achievement :

Page 9: 2G DT REPORT Baseline Cluster

5.2 Rx_LevSubdBm by SHORT CALL

Baseline :

No SubCluster Logfile Remark

1 C7-5 0926_08

2 C7-5 0927_17

3 C7-5 0927_17

Achievement :

Page 10: 2G DT REPORT Baseline Cluster

5.3 RX_QUAL by SHORT CALL

Baseline :

Figure 4: Rx_Qual Plot

RX QUAL Mode Weighting BASELINE ACHIEVEMENT

Sample % Sample %

RxQualsub<=5 Dedicated 10,00% 55613 88,47

%

RxQualsub>5 7251 11,53%

Achievement :

Page 11: 2G DT REPORT Baseline Cluster

5.4 SQI by SHORT CALLBaseline :

Figure 5: SQI Plot

SQI Mode Weighting BASELINE ACHIEVEMENT

Sample % Sample %

20 to 30 Dedicated 15,00% 37238 83,39%

0 to 20 7418 16,61%

Achievement :

Page 12: 2G DT REPORT Baseline Cluster

5.5 FREQUENCY BAND by IDLE MODE

Baseline :

Figure 6: Frequency Band Plot

Frequency Mode Weighting BASELINE ACHIEVEMENT

Sample % Sample %

900 Idle NA 19282 46,54%

1800 22148 53,46%

Achievement :

Page 13: 2G DT REPORT Baseline Cluster

5.6 Cell List

No Cell Name BCCH BSC No Cell Name BCCH BSC

1 CICALUNG_PL2 48 BKWN05 22 CILEWO_SM1 36 BKWN05

2 D_SRYACPT_IM3_2 757 BKWN05 23 D_PSRTLGA_SM1 778 BKWN01

3 WALAHAR2 35 BKWN05 24 D_BELENDUNG1 780 BKWN05

4 D_WALAHAR2 763 BKWN05 25 D_BELENDUNG2 775 BKWN05

5 CURUGKLARI1 30 BKWN05 26 BELENDUNG2 31 BKWN05

6 D_TAMELANG2 755 BKWN05 27 D_CICANGOR1 776 BKWN05

7 D_WALAHAR3 778 BKWN05 28 CICANGOR2 34 BKWN05

8 RAWAUNGU_SM1 48 BKWN05 29 GANTIONO1 49 BKWN05

9 D_KLARI_IM3_2 781 BKWN01 30 KSMBIHB_IM_SM1 43 BKWN05

10 D_KLARI_IM3_3 765 BKWN01 31 D_KSMBHBIM_SM1 780 BKWN05

11 KLARI_IM3_3 44 BKWN01 32 CENGKONG_SM1 38 BKWN05

12 SIMARGALIH2 46 BKWN01 33 D_DARAWOLONG3 761 BKWN05

13D_CKMPKTOLKM42_3 777 BKWN01 34 D_CENGKONG_SM2 759 BKWN05

14 CIRANGGON1 33 BKWN01 35 D_KARANGSARI3 784 BKWN05

15 PASIRMUKTI3 39 BKWN03 36D_SUKASARI_KRWG1 765 BKWN05

16 TELAGASARI2 49 BKWN01 37 D_CICALUNG_PL3 769 BKWN05

17 D_CILEWO_SM3 782 BKWN05 38 D_BENGLE_SM2 769 BKWN01

18 KARANGSARI1 39 BKWN05 39 BELENDUNG3 36 BKWN05

19 DARAWOLONG1 41 BKWN05 40 D_CIRANGGON3 774 BKWN01

20 CILEWO_SM2 45 BKWN05 41 PASIRTALAGA_SM3 46 BKWN01

21 D_CILEWO_SM1 776 BKWN05 42 D_BENGLE_SM1 784 BKWN01

6 CONCLUSION

Based on the drive test KPI performance for this cluster, all KPI for Indosat 2013 Network Roll Out Phase 2 has passed.

Thereafter this site will be declared as ACCEPTED CLUSTER