25 january 2007velo sub-projectseddy jans 0 velo-meeting january 25, 2007 sub-projects: sx8-2.003...
DESCRIPTION
25 January 2007VELO sub-projectsEddy Jans 2 22 Jan 16 Feb: - pull long-distance (RB84 D3) analog cables by INEO - “simultaneously” connectorize D3-side 19 Feb 23 Feb: - pull control cables (RB84 balcony) 26 Feb 2 Mar: - pull HV cables (RB84 D3) Cabling Cooling cables still need to be connectorized at both ends, i.e. RB84 and C3. Estimated time: 2*1 manweek.TRANSCRIPT
25 January 2007 VELO sub-projects
Eddy Jans 1
VELO-meetingJanuary 25, 2007
• Sub-projects:• SX8-2.003 & SX8-2.004• connectorize cooling cables• alignment procedure• motion• test bake out procedure• turn over project• P-project• VELO vacuum commissioning
• LHCb installation planning• summary + timelines
25 January 2007 VELO sub-projects
Eddy Jans 2
clean up SX8-2.003&4Spaces 2.003 and 2.004 are future storage, repair and
working places for the whole VELO + PU communities.
With other people and parts/equipment approaching soon, our stuff needs to be reorganized/cleaned up.
Estimated time: 0.5 manweek.
25 January 2007 VELO sub-projects
Eddy Jans 3
•22 Jan 16 Feb:- pull long-distance (RB84 D3) analog cables by
INEO - “simultaneously” connectorize D3-side
• 19 Feb 23 Feb:- pull control cables (RB84 balcony)
• 26 Feb 2 Mar:- pull HV cables (RB84 D3)
Cabling
Cooling cables still need to be connectorized at both ends,i.e. RB84 and C3.
Estimated time: 2*1 manweek.
25 January 2007 VELO sub-projects
Eddy Jans 4
AlignmentCentre FrameFiducial Marks
Alignment procedure uses 5 fiducialpoints on each side of center frame.
However, these are soon not visible anymore due to the repeater crates, mounted on the detector hood.
25 January 2007 VELO sub-projects
Eddy Jans 5
Solution:Install new alignment pointsabove and below the existing ones.
Watch out that the analog cable supporting frame is not in the way also.
Estimated time: design: 1.5 mwconstruction: 1.5 mwimplementation: 2*0.5 mw
25 January 2007 VELO sub-projects
Eddy Jans 6
MotionIncreasing expertise with the system has revealed the necessity to take a few additional safety measures.Partly to be implemented in the PLC, partly in the PVSS application. • moving both XL and XR in the same direction from a position in which XL=-XR, needs special precautions.• implement the possibility to stop the stepper motor when really necessary (moving wrong way based on pot. meters, one side not moving at all, etc.)
Estimated time: thinking: 2 mwimplementation: 2 mwtesting: 2*1 mw
25 January 2007 VELO sub-projects
Eddy Jans 7
Test bake-out procedureBake-out procedure of rf-boxes has to be commissioned:regulation of lamps, temperature interlock, etc.
Estimated time: preparation: 1 mwimplementation: 2*1 mw
25 January 2007 VELO sub-projects
Eddy Jans 8
Turn over projectRotation of the detector half is adelicate, not yet well-establishedactivity.
Likely solution:Use 2 small cranes. Either poweredby hand or electricity.
Estimated time: preparation: 0.5 mwproduction of test tool: 0.5 mw ?testing: 2*0.2 mw
25 January 2007 VELO sub-projects
Eddy Jans 9
P project
-0.4
-0.3
-0.2
-0.1
0
0.1
0.2
0.3
0.4
-6 -4 -2 0 2 4 6
Mod 7Mod 3
x[mm]
p [mbar]
(elastic) deflection:0.3 mm @ 4 mbar
0.4 mm @ 5 mbar
25 January 2007 VELO sub-projects
Eddy Jans 10
evacuation
p=pbeam-pdet[mbar]
foilhits
sensorsside
25 January 2007 VELO sub-projects
Eddy Jans 11
venting
p=pbeam-pdet[mbar]
foilhits
sensorsside
25 January 2007 VELO sub-projects
Eddy Jans 12
Possible remedy:change p-range and/or central p-value.
Estimated time: preparation: 2*1 mwtesting: 2*0.5 mw
25 January 2007 VELO sub-projects
Eddy Jans 13
VELO vacuum commissioningUnacceptable leak rate (10-5 mbar.l/s) of rf-boxes necessitates additional tests + attempts to (temporary) fix the problem.Present plan with VELO + part I of the beam pipe:
• evacuate• bake rf-boxes @ 160 oC • vent ??• evacuate ??• determine leak rate• vent• seal “holes” with Varnish• evacuate• determine leak rate
Estimated time of NIKHEF-involvement: 2*2 mw
25 January 2007 VELO sub-projects
Eddy Jans 14
LHCb installation schedule
• Coming months lots of activities from RICH1, TT, VELO (HV, LV, ECS, etc.) in the vicinity of the VELO. Need for coordination, flexibility and mutual cooperation.• Jan 22 Mar 2:
Cabling (analog + control) around the VELO.• March + April: installation LV-distribution boxes, HV-patch panels• April 5:
Start bake out + commissioning of the complete LHCb beam pipe.
25 January 2007 VELO sub-projects
Eddy Jans 15
Summarywhat what where time
[mw]start at the latest on
ready before
who
2.003&4 cleanup IP8 0.5 1 Mar 15 Mar FM/MD/MKcooling cables connectorize IP8 2*1 15 Mar 1 Apr JS+??alignment design NL 1.5 1 Feb 15 Feb JvdB+FM
production NL 1.5 20 Feb 5 Mar VU
align IP8 2*0.5 15 Mar 23 Mar JvdB+FM
motion design NL 2 15 Apr 1 May PdG+MvBcoding NL 2 15 May 1 June PdG+MvB
testing IP8 2*1 15 Jun 1 July PdG+MvB
bake out design NL 1 15 Feb 1 Mar PdG+MvBtesting IP8 2*1 1 Mar 10 Mar PdG+??
turn over prep NL 0.5 15 Feb 1 Mar MK/MDprod. of test tool NL 0.5 1 Mar 15 Mar NIKHEF/CERN?
testing ?? 2*0.2 15 Mar 1 Apr MK+MD+RD
p prep NL 2*1 20 Feb 15 Mar MD+LJtesting IP8 2*0.5 15 Mar 1 Apr MD+LJ
vacuum comm. leak rate++ IP8 2*2 10 Mar 1 April LJ/MD/BM/FM