Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

23 AVENUE GRADE SEPARATION● LRT IN MEDIAN UNDER 23 AVENUE

● LIMITED RIGHT OF WAY

● SPLIT NORTHBOUND AND SOUTHBOUND LANES

● PROFILE OF LRT UNDER 23 AVENUE

● GEOTECHNICAL CONCERNS

● STORMWATER MANAGEMENT

● IMPACTS ON EXISTING BERM

Page 2: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

IMPACTS ON EXISTING BERM

OPTION 2 – NOISE WALL ADJACENT TO LRT

OPTION 1 – NOISE WALL ON PROPERTY LINE

Page 3: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

23 AVENUE GRADE SEPARATION

111 STREET •

111 Street will be realigned to the west for construction staging

23 AVENUE•

23 Avenue will be realigned to the north for construction staging

CONSTRUCTION STAGING

Page 4: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

BLACKMUD CREEK OPTION 1

MULTI-USE TRAIL ON LRT BRIDGE

Page 5: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

BLACKMUD CREEK OPTION 2

MULTI-USE TRAIL ON SEPARATE BRIDGE

Page 6: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

3 – SPAN BRIDGE

Page 7: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

STEEL ARCH BRIDGE

Page 8: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

SEPARATE MULTI-USE TRAIL BRIDGE

Page 9: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

TWIN BROOKS (12 AVENUE – 9 AVENUE)

Page 10: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

9 AVENUE – SOUTH ANTHONY HENDAY DRIVE OPTION 1

Page 11: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

9 AVENUE – SOUTH ANTHONY HENDAY DRIVE OPTION 2

Page 12: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

PARK AND RIDE AND STATION

Page 13: 23 AVENUE GRADE SEPARATION - Edmonton · 23 AVENUE GRADE SEPARATION ... AND STATION . Preliminary Design for South LRT Extension – Century Park to Ellerslie Road SCHEDULE • FALL

Preliminary Design for South LRT Extension –Century Park to Ellerslie Road

SCHEDULE

FALL 2009 •

PUBLIC OPEN HOUSE - OCTOBER 8 (4-8pm), ELLERSLIE RUGBY CLUB.

CONTINUE ENGINEERING DESIGN.

SECOND SIP MEETING (DATE TO BE DETERMINED)

EARLY 2010•

PUBLIC INFORMATION SESSION (DATE AND LOCATION TO BE DETERMINED) .

FINALIZE ENGINEERING REPORT.