Local knowledge International experience Focused on success Leighton’s experience in mining in Mongolian Mongolia Mining Investment 2010 Conference Local knowledge International experience Focused on success Leighton Asia Today Leighton Asia is part of the Leighton Group – one of the world’s major project development and contracting organisations, we are also the world largest contracts miner Employing over 7,800 employees Work in hand exceeds A$7 million Leighton Asia operates in Hong Kong, Macau, China, Mongolia, Indonesia, Taiwan, the Philippines, Guam, Vietnam, Thailand, Laos, Cambodia and Kazakhstan Focused on resources, civil & infrastructure, property and mining Leighton Asia is part of the Leighton Group – one of the world’s major project development and contracting organisations, we are also the world largest contracts miner Employing over 7,800 employees Work in hand exceeds A$7 million Leighton Asia operates in Hong Kong, Macau, China, Mongolia, Indonesia, Taiwan, the Philippines, Guam, Vietnam, Thailand, Laos, Cambodia and Kazakhstan Focused on resources, civil & infrastructure, property and mining

Upload: the-business-council-of-mongolia

Post on 23-Jan-2017

100 views

Category:

Business


1 download

TRANSCRIPT

Page 1: 22.06.2010 Leighton's experience in mining in Mongolian, Hamish Tyrwhitt

Local knowledge International experience Focused on success

Leighton’s experience in mining in MongolianMongolia Mining Investment 2010 Conference

Local knowledge International experience Focused on success

Leighton Asia Today

� Leighton Asia is part of the Leighton Group – one of the world’s major project development and contracting organisations, we are also the world largest contracts miner

� Employing over 7,800 employees� Work in hand exceeds A$7 million� Leighton Asia operates in Hong Kong,

Macau, China, Mongolia, Indonesia, Taiwan, the Philippines, Guam, Vietnam, Thailand, Laos, Cambodia and Kazakhstan

� Focused on resources, civil & infrastructure, property and mining

� Leighton Asia is part of the Leighton Group – one of the world’s major project development and contracting organisations, we are also the world largest contracts miner

� Employing over 7,800 employees� Work in hand exceeds A$7 million� Leighton Asia operates in Hong Kong,

Macau, China, Mongolia, Indonesia, Taiwan, the Philippines, Guam, Vietnam, Thailand, Laos, Cambodia and Kazakhstan

� Focused on resources, civil & infrastructure, property and mining

Page 2: 22.06.2010 Leighton's experience in mining in Mongolian, Hamish Tyrwhitt

Local knowledge International experience Focused on success

Why Mongolia?

� Enormous mineral wealth� Developing mining legislation� Low security risk� High growth potential� Logistically challenging due

to remote mining location and extreme environmental conditions

� A mining industry at its infancy requiring modern equipment, technical support and training of the Mongolian workforce

� Hardworking, well educated, industrious workforce

� Enormous mineral wealth� Developing mining legislation� Low security risk� High growth potential� Logistically challenging due

to remote mining location and extreme environmental conditions

� A mining industry at its infancy requiring modern equipment, technical support and training of the Mongolian workforce

� Hardworking, well educated, industrious workforce

Local knowledge International experience Focused on success

Leighton Asia Mongolia Business

Page 3: 22.06.2010 Leighton's experience in mining in Mongolian, Hamish Tyrwhitt

Local knowledge International experience Focused on success

Contract Mining in Mongolia

Owner Operator Traditional Contract Miner

Full Services Contracting

Contractor Activity

� Infrastructure setup � Pre-strip� Mining� Rehabilitation

� Infrastructure set-up� Mine planning� Pre-strip� Mining� Processing & loadout� Rehabilitation

Delivery System

� Design & construct� Lump sum

� Schedule of rates� Lump sum

� Alliancing/relationship� Schedule of rates

Investment by Contractor

� Nil � Plant & equipment � Plant & equipment� Working capital� Investment stake in mine

Skills Required by Contractor

� Construction � Earthmoving/mining � Construction� Mine planning� Earthmoving/mining� Operations &

maintenance

Local knowledge International experience Focused on success

Challenges for Mongolian businesses

� Lack of developed capital market

� Infrastructure constraints� Lack of skilled labour� Evolving & changing mining

legislation� Foreign exchange

regulations� Isolation & climate� Inflation potential� Political risk� Land locked country –

Russia and China

� Lack of developed capital market

� Infrastructure constraints� Lack of skilled labour� Evolving & changing mining

legislation� Foreign exchange

regulations� Isolation & climate� Inflation potential� Political risk� Land locked country –

Russia and China

+40oC to – 40oC

Page 4: 22.06.2010 Leighton's experience in mining in Mongolian, Hamish Tyrwhitt

Local knowledge International experience Focused on success

Ukhaakhudag Coal Mine

Location Southern Gobi Desert

Client Energy Resources LLC

Entity Leighton LLC

Scope Works includes pit de-watering, drill & blast, overburden removal, load & haul of coal, and loading of ROM coal into client’s transport. Also includes the provision of mine planning and engineering services.

Resource 430 million tonne coking & thermal coal deposit, part of the TavanTolgoi coal resource. Open pit extraction.

Local knowledge International experience Focused on success

UHG mine issues

UHG mine issues

At the UHG Coal Project our people have successfully overcome many obstacles

� One of the harshest environments in the world� Team members from different countries of origin and cultures� No previous experience of working together� Creating a new mine in a very remote location� Introducing new mining methods and equipment that were not previously

tested in Mongolia� Setting production at high levels not previously achieved in Mongolia� Achieving accelerated ramp up objectives – producing coal at 400K

tonnes/month

UHG mine issues

At the UHG Coal Project our people have successfully overcome many obstacles

� One of the harshest environments in the world� Team members from different countries of origin and cultures� No previous experience of working together� Creating a new mine in a very remote location� Introducing new mining methods and equipment that were not previously

tested in Mongolia� Setting production at high levels not previously achieved in Mongolia� Achieving accelerated ramp up objectives – producing coal at 400K

tonnes/month

Page 5: 22.06.2010 Leighton's experience in mining in Mongolian, Hamish Tyrwhitt

Local knowledge International experience Focused on success

UHG mine today

� Leighton Asia is delivering a world class mine to international best practice and standards - focused on safety, environment, community, training and productivity excellence with a predominantly Mongolian workforce.

� Contract with Energy Resources based on relationship principles providing a foundation for a long term relationship with one unified team

� Over 310 employees on site� 996 excavator and 793 trucks� 9250 excavator and 785 trucks� Planned coal production 2010 – 3.8 million tonne

� Leighton Asia is delivering a world class mine to international best practice and standards - focused on safety, environment, community, training and productivity excellence with a predominantly Mongolian workforce.

� Contract with Energy Resources based on relationship principles providing a foundation for a long term relationship with one unified team

� Over 310 employees on site� 996 excavator and 793 trucks� 9250 excavator and 785 trucks� Planned coal production 2010 – 3.8 million tonne

Local knowledge International experience Focused on success

UHG mine tomorrow

� Planned mining capacity end 2010 – 5 mtpa� Planned mining capacity June 2011 - 10 mtpa

– Co-ordinating with the infrastructure developments– Power plant– Coal wash plant– Rail line to Chinese border– Water pipeline– Equipment ramp up and delivery– Training of the workforce

� Planned mining capacity end 2010 – 5 mtpa� Planned mining capacity June 2011 - 10 mtpa

– Co-ordinating with the infrastructure developments– Power plant– Coal wash plant– Rail line to Chinese border– Water pipeline– Equipment ramp up and delivery– Training of the workforce

Page 6: 22.06.2010 Leighton's experience in mining in Mongolian, Hamish Tyrwhitt

Local knowledge International experience Focused on success

Community involvement

Local knowledge International experience Focused on success

Mine safety & environment

� International standard practices established� Risk based approach to safety & environment� Strive for LIFE programme implemented� Buy-in from client & workforce� Full time expatriate safety manger on site� No class 1 injuries to date� Successfully mined through two winters� Staff & Workforce united and aligned with common vales

and culture

� International standard practices established� Risk based approach to safety & environment� Strive for LIFE programme implemented� Buy-in from client & workforce� Full time expatriate safety manger on site� No class 1 injuries to date� Successfully mined through two winters� Staff & Workforce united and aligned with common vales

and culture

Page 7: 22.06.2010 Leighton's experience in mining in Mongolian, Hamish Tyrwhitt

Local knowledge International experience Focused on success

Training at UHG

� Established a training school at the mine site and in Ulaanbaatar

� Trainers on site full time� Simulator commissioned onsite –

March 2010� Utilizing Leighton’s proven training

systems� Working closely with industry

partners– CAT– Liebherr

� Mongolians are keen to learn and have achieved world class productivity rapidly

� World standard plant utilisationachieved

� Established a training school at the mine site and in Ulaanbaatar

� Trainers on site full time� Simulator commissioned onsite –

March 2010� Utilizing Leighton’s proven training

systems� Working closely with industry

partners– CAT– Liebherr

� Mongolians are keen to learn and have achieved world class productivity rapidly

� World standard plant utilisationachieved

Local knowledge International experience Focused on success

� The ER and Leighton partnership has developed a world class coal mine in a very short time period

� The opportunities to further expand in Mongolia are significant and well within our capabilities

� Leighton keen to work with Government and mine operators to plan & develop Tavan Tolgoi resource

� Improving infrastructure is crucial for the development of the resource sector in Mongolia

� The ER and Leighton partnership has developed a world class coal mine in a very short time period

� The opportunities to further expand in Mongolia are significant and well within our capabilities

� Leighton keen to work with Government and mine operators to plan & develop Tavan Tolgoi resource

� Improving infrastructure is crucial for the development of the resource sector in Mongolia