205 HOLLAND PARK ACCESS AND LOGISTICS
Job Reference: 46/8451 Rev: 1 Date: Dec-14
1 of 46
INDEX
• Directions to site & Holding areas.• Access for pedestrians and vehicles. • Crane radius drawing. • Electronic booking in system & Waste Management.• Typical temp services. • Material distribution.• Internal walls to be left down.• External Elevation Access • Gantry drawing • Hoist and Beam Hoist
2 of 46
Directions to site & delivery vehicle holding area’s
3 of 46
BY Rail & Tube Shepherds Bush on Central Line or Over ground WalkFrom Shepherds Bush station Uxbridge Road Continue along Uxbridge Road for 4 metresTake a slight left on to Holland Park Roundabout, continue for 130 metresContinue along Holland Park Avenue for 50 metresCrossing over at the lights, then turn right back towards shepherds bush greenWalking under the gantry, and around the corner onto Holland roadThe site entrance will then be on your left where there is a turnstile. BY ROAD From A40Start out on Western Avenue towards Central London, Shepherds BushAt Savoy Circus continue forward onto WestwayBranch left, then at roundabout take the 2nd exit onto the A3220 At White City Junction continue forwardAt Holland Park Roundabout take the 2nd exit onto the A3220Arrive on Holland Road From M1End of Motorway (junction 1) At roundabout take the 3rd exit onto the A406 towards Harrow/ Kilburn A5 North Circular WestAt roundabout take the 2nd exit onto the A406 towards WembleyMerge onto the A406At Stonebridge Park continue forward onto the A406 towards EalingAt Hanger Lane roundabout take the 2nd exit, then merge onto the A40 towards Central LondonPark Royal Underground StationAt Savoy Circus continue forward onto WestwayBranch left, then at roundabout take the 2nd exit onto the A3220 At White City Junction continue forwardAt Holland Park Roundabout take the 2nd exit onto the A3220Arrive on Holland Road
PLEASE NOTE: THERE IS NO PARKING ON SITE
4 of 46
HOLDING AREA 15 of 46
The parkway A312 – approx. 10 miles and 45 minutes from site in peak hours traffic. For deliveries coming from the M25 / M4 junction there are two lay-bys opposite each other on the A312 just off junction 3 of the M4. these are accessed by turning right from the M4 onto Parkway. The southbound lay-by is approximately 300m down on the left hand side. On the opposite side of the road accessed via a roundabout junction at the parkway / Bath road (A4) junction there is a similar sized lay by.
HOLDING AREA 26 of 46
HOLDING AREA 37 of 46
Access for Vehicles & Pedestrians
8 of 46
KEY
GateHoarding
Site Accommodation
Tower Crane
KEY
GateHoarding
Site Accommodation
Tower Crane
Clearwater Terrace
Holland Park Avenue
Pedestrian access
ACCESS VEHICLES
LOADING BAY ACCESS FROM ROUNDABOUT
Pedestrian footpath air lock
WAY IN
OUTTurnstile
Hoist
Pedestrian Entrance
Site Entrance
PE 01
PE 02
PE 03
Female W/C (GF)Canteen (BAS)
Drying Rooms/ Toilets (GF)
Site Office (BAS)
9 of 46
KEY
GateHoarding
Site Accommodation
Pedestrian Route to siteaccommodation
Pedestrian route to site
Holland Park Avenue
Clearwater Terrace
Holland Road
Female W/C (GF)Canteen (BAS)
Drying Rooms/ Toilets (GF)
Site Office (BAS)
Turnstile
Hoist
10 of 46
Crane Radius Drawing
11 of 46
LOADING BAY
CRANE RADIUS DRAWING 12 of 46
Electronic Booking in system & Waste Management
(Madigan Gill)
13 of 46
- Site office provides a white board with written down visually site deliveries to come.- Website where to book in deliveries http://deliver.madigangill.co.uk/admin/diary.php
14 of 46
Delivery Booking in System with Madigan Gill
15 of 46
16 of 46
17 of 46
18 of 46
19 of 46
20 of 46
21 of 46
22 of 46
23 of 46
24 of 46
25 of 46
26 of 46
27 of 46
28 of 46
Groundwork's/Concrete/Rebar disposal to site, is the responsibility of Modebest.
Hard-core/masonry skins wills be produced by SCL. It is then the sub-contractors responsibility to place any debris into these skips.
Waste/rubbish collection facilities will be positioned on each level of each block.
The bins will be collected from these locations and taken to the compactor/skips and removed from site for recycling, then
returned to their respective collection points on each floor.
There will be clearly labelled wheelie bins, showing which waste stream should be placed in each bin.
Any elements that are returnable will be the responsibility of the relevant subcontractor. It is our Logistics Manager’s
responsibility to manage and audit this process to ensure returnable items are returned including all/any liaison with
Subcontractors.
The site will be patrolled at regular intervals to ensure that:
• Waste is being put into the bins provided.
• Waste is segregated into the correct bin.
• Materials are stored in the correct location and are adequately protected.
• Items such as pallets, cable drums, packing crates and stillage's which are deemed to form part of the waste stream are
returned to the original supplier, at the responsibility of the subcontractor.
Transgressions of the site cleanliness regime will result in the offender being issued with a Non-Compliance Notice.
Prior to issuing Non-Compliance Notices we will use our reasonable endeavours to highlight the issue to the subcontractor, unless of a health and safety breach.
Non-Compliance Notices will be issued utilising a fixed fee contra charge notification system.
The system will include the taking of digital photographic evidence and then electronically issuing to the defaulting
subcontractors for non-compliance of their cleaning responsibilities.
Waste Management
29 of 46
Material distribution
30 of 46
• Delivery/Collection vehicles only permitted between 8:00 & 18:00 from Mon-Fri, due to the planning constraints and consideration of the neighbours.
• This is a very restricted site, so all materials need to be off loaded & distributed to the correct level promptly.• All deliveries will be booked in by the electronic booking in system, which also allows booking of, beam hoist ,hoist
or crane. Delivery vehicles must keep to their booked in time slot or they will be turned away.• All delivery drivers must be told NOT TO STOP IN THE ROUNDABOUT if they cant pull in to layby they must drive on.• Hoist will go from ground to 10th floor roof with landing on gantry as well.• Framework contractor will require half of the 5th floor slab as his storage area. • Floors will have to have walls left down for movement of materials (see following drawings) all bulky materials for
the remainder of works in these flats needs to be loaded out before walls are built.• Materials for 5th floor can be landed on 5th floor roof by crane till crane goes.• All roof materials will be off loaded by crane/hoist.• All precast concrete Mullions will be off loaded & installed by main crane and spider crane.• All vertical transportation is by SCL i.e. hoist drivers and crane driver only – Subcontractors need to provide
competent / trained men to sling and move material into and out of hoists. The gantry has been designed so materials can be wheeled from the beam hoist to the hoist, subcontractors must provided the means to wheel these materials.
• The ground floor will be able to be accessed from the road layby in certain circumstances through the pavement air lock gates, if it is agreed with SCL management that a subcontractor will use this route then the subcontractor must provide sufficient operatives to operate the air locks safely.
• Small delivery vehicles will be able to access the basement via the ramp at the back of the building rigids will not be able to turn the corner to gain access to this ramp. This though, will only be permitted in the last 6-8 weeks of the project.
• No materials are to be stored on the gantry, loading platforms or within the vehicle lay by.
Material Distribution
31 of 46
PROPOSED DISTRIBUTION OF MATERIALS
Material Method of DistributionMetsec Canti deck / Hoist
Underfloorheating insulation/ pipework Hoist
Screed Pump in designated area/Insulation Hoist .
Stud/ Plasterboard Canti deck/ Hoist
Bags of filler/ plaster Hoist
Electrical items 1st fix/ 2nd fix Hoist
Mechanical 1st fix/ 2nd fix Hoist
Blockwork Crane /forklift
Windows Hoist
Render/ Insulation Hoist
Flooring Hoist
Kitchen/ appliances Hoist
Roof materials Crane/ Hoist
Joinery- doors/ skirting/ wardrobes? Hoist
Perimeter boarding Hoist
Mirrors Hoist
Formwork/ decking/ rebar Crane
Vanity units Hoist
Concrete mullians Main Tower and Spider Crane
Tiles/ Grout Hoist 32 of 46
Internal walls to be left down
33 of 46
HOIST IN Wall left down
WALLS LEFT OUT FOR LOADING 1ST TO 3RD FLOOR 34 of 46
WALLS LEFT OUT FOR LOADING 4TH FLOOR
HOIST IN Wall left down
35 of 46
WALLS LEFT DOWN FOR LOADING 5TH TO 9TH FLOOR
Wall left down
HOIST IN
36 of 46
External Elevation Access
37 of 46
Scaffold from ground to 5th Scaffold from ground to 10th with pedestrian ramp at lower lift
HOIST
Projecting bays see other drawing
Bridge over light well
Projecting bays starts at 1st & finishes at 5th bridge over top of bay
Bridge over basement ramp 3 meters clear & 2 meters wide
Approx 6 lin m cantilevered out at 1st floor level to 5th
GROUND FLOOR
Bridge over at 5th floor level floor 1 to 4 to have 1 lift per floor for this section of over hand block work
Scaffold from Ground to 10th
Scaffold from ground to 8th floor
Bridge over at 3 meters clear & wide
This corner to have no legs to ground to allow access to carnet court
38 of 46
3rd – 4th FLOOR
Scaffold from 3rd floor to 4th
Scaffold from 4th floor to 5th
39 of 46
Scaffold from 4th floor to 5th
This elevation is shown on another drawing
4TH FLOOR
This section from 3rd
40 of 46
Scaffold from 5th roof floor to 10th
Scaffold from Ground to 10th Scaffold from ground to 8th floorScaffold from ground to 5th floorScaffold from Ground to 4th
Scaffold from 4th floor roof to 10th
Projecting bay starts at 2nd floor & finishes at 6th floor level beam out
Projecting bay starts at 2nd floor & finishes at 4th floor level then starts again at 6th and finishes at 7th floor level beam out
Roofs
Scaffold from 8th floor roof to 10th
Scaffold from 5th floor roof to 8th
41 of 46
Gantry Drawing
42 of 46
Holland Park Avenue
Hoist
Gantry with external scaffold Built off
Beam Hoist
GANTRY
Public Pedestrian Access Under Gantry
Gates Five board wide fan
2 meter long gantry 35 meter long
gantry with dogleg
43 of 46
Beam Hoist & Hoist
44 of 46
BIG E BEAM HOIST 2 ton SWL fixed on Gantry
Beam Hoist 45 of 46
Hoist 46 of 46