City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Street Lights
STREET LIGHT KNOCKDOWN PROGRAM SL-025Project No:
Submitting Department:
Project Manager:
Public Works
Luke Smith
Project Status: Annual
Projected Start Date 07/01/2007
Projected Completion Date: 06/30/2029Total Projected Cost: $12,526,000
Prior Years ActualCosts:
This is an annual program to replace existing street lights. This project will be used to replace poles that are knocked down.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Other Reimbursed $230,000 $230,000 $230,000 $230,000 $230,000 $690,000 $1,840,000
Capital Replacement - PW Traffic $46,000 $130,000 $130,000 $130,000 $2,050,000 $2,050,000 $6,150,000 $10,686,000
$46,000 $360,000 $360,000 $360,000 $2,280,000 $2,280,000 $6,840,000 $12,526,000
Operating Impacts
302 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Street Lights
PAINTED/CONCRETE SL POLE REPLACEMENT SL-027Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez
Project Status: Annual
Projected Start Date 07/01/2014
Projected Completion Date: 06/30/2029Total Projected Cost: $2,750,000
Prior Years ActualCosts:
In the older areas of the City, the existing painted street light poles will be replaced with galvanized poles having a much longer life.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Capital Replacement - PW Traffic $500,000 $250,000 $250,000 $250,000 $250,000 $1,250,000 $2,750,000
$500,000 $250,000 $250,000 $250,000 $250,000 $1,250,000 $2,750,000
Operating Impacts
303 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Street Lights
STREETLIGHT WIRE THEFT REPLACEMENT SL-208Project No:
Submitting Department:
Project Manager:
Public Works
Luke Smith/Alyssa Rodriguez
Project Status: Annual
Projected Start Date 10/13/2014
Projected Completion Date: 06/30/2035Total Projected Cost: $1,100,000
Prior Years ActualCosts:
Replace stolen streelight copper wire.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Capital Replacement - PW Traffic $200,000 $100,000 $100,000 $100,000 $100,000 $500,000 $1,100,000
$200,000 $100,000 $100,000 $100,000 $100,000 $500,000 $1,100,000
Operating Impacts
304 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
SUNRIDGE HEIGHTS - EXECUTIVE AIRPORT TO SEVEN HILLS DRIVE ST-042Project No:
Submitting Department:
Project Manager:
Public Works
Tom Davy
Project Status: Active
Projected Start Date 07/01/2016
Projected Completion Date: 06/30/2019Total Projected Cost: $1,629,000
Prior Years ActualCosts:
Construct four-lane roadway along Sunridge Heights between Executive Airport and Seven Hills Drive, with traffic and drainage appurtenances per RTC standards.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,629,000 $1,629,000
$1,629,000 $1,629,000
Operating Impacts
Maintenance Labor $2,877 $2,934 $2,993 $3,053 $3,114 $3,176 $18,147
Supplies $650 $670 $683 $697 $711 $725 $4,136
$22,283 $3,527 $3,604 $3,676 $3,750 $3,825 $3,901
305 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
AMIGO - ST. ROSE TO SUNRIDGE HEIGHTS ST-047Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Proposed
Projected Start Date 07/01/2020
Projected Completion Date: 06/30/2021Total Projected Cost: $1,500,000
Prior Years ActualCosts:
Construction of new 80-foot arterial with 2 travel lanes each way and center double turn lane.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Developer - Streets
To Be Determined $1,500,000 $1,500,000
$1,500,000 $1,500,000
Operating Impacts
Maintenance Labor $2,993 $3,053 $3,114 $6,416 $15,576
Supplies $683 $697 $711 $1,465 $3,556
$19,132 $3,676 $3,750 $3,825 $7,881
306 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
ATHENS AVE - RACETRACK TO FOOTHILLS - PH II ST-059Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Proposed
Projected Start Date 07/01/2019
Projected Completion Date: 06/30/2021Total Projected Cost: $1,000,000
Prior Years ActualCosts:
Widen to four travel lanes.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Developer - Streets $100,000 $900,000 $1,000,000
$100,000 $900,000 $1,000,000
Operating Impacts
Maintenance Labor $2,993 $3,053 $3,114 $3,176 $12,336
Supplies $683 $697 $711 $725 $2,816
$15,152 $3,676 $3,750 $3,825 $3,901
307 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
BARRETT ST - WARM SPRINGS TO BOULDER HWY ST-060Project No:
Submitting Department:
Project Manager:
Public Works
Scott Fiedler
Project Status: Proposed
Projected Start Date 07/01/2027
Projected Completion Date: 06/01/2029Total Projected Cost: $3,730,000
Prior Years ActualCosts:
Construct new four lane roadway with signal at Warm Springs Road per RTC standards.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
To Be Determined $3,730,000 $3,730,000
$3,730,000 $3,730,000
Operating Impacts
Maintenance Labor
Supplies
308 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
BERMUDA ROAD - VOUNTEER TO ST. ROSE PARKWAY ST-062Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Active
Projected Start Date 07/01/2018
Projected Completion Date: 06/30/2020Total Projected Cost: $3,000,000
Prior Years ActualCosts:
Construct to six travel lanes
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $750,000 $2,250,000 $3,000,000
$750,000 $2,250,000 $3,000,000
Operating Impacts
Maintenance Labor $3,114 $3,176 $6,290
Supplies $711 $725 $1,436
$7,726 $3,825 $3,901
309 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
FOOTHILLS DR - BOULDER HIGHWAY TO EQUESTRIAN ST-072Project No:
Submitting Department:
Project Manager:
Public Works
Scott Fiedler
Project Status: Proposed
Projected Start Date 07/01/2028
Projected Completion Date: 06/30/2028Total Projected Cost: $3,300,000
Prior Years ActualCosts:
Construct new four lane roadway.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Developer - Streets $3,300,000 $3,300,000
$3,300,000 $3,300,000
Operating Impacts
Maintenance Labor $2,877 $2,877
Supplies $650 $650
$3,527 $3,527
310 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
STARR/EXECUTIVE AIRPORT - LAS VEGAS BOULEVARD TO BICENTENNIAL ST-139Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Active
Projected Start Date 07/01/2016
Projected Completion Date: 06/30/2019Total Projected Cost: $1,000,000
Prior Years ActualCosts:
Construction of four-lane roadway with traffic and drainage appurtenances per RTC standards.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,000,000 $1,000,000
$1,000,000 $1,000,000
Operating Impacts
Maintenance Labor $2,965 $2,965 $2,865 $2,865 $2,965 $2,965 $17,590
Supplies $420 $435 $450 $465 $480 $495 $2,745
$20,335 $3,385 $3,400 $3,315 $3,330 $3,445 $3,460
311 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
ON CALL STREET PATCHING ST-146Project No:
Submitting Department:
Project Manager:
Public Works
Scott Fiedler
Project Status: Annual
Projected Start Date 07/01/2006
Projected Completion Date: 06/30/2028Total Projected Cost: $15,000,000
Prior Years ActualCosts:
Yearly contract funded by gas tax revenues that will generally consist of crack seal, patching, and slurry seal (asset management) of the existing transportation network (asphalt of roadways
only) at various locations throughout the city.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Gas Tax - 1% Room Tax $100,000 $100,000 $100,000 $300,000
Gas Tax - 1 Cent $200,000 $200,000 $200,000 $600,000
Gas Tax - 2.35 Cents $1,200,000 $1,200,000 $1,200,000 $1,500,000 $1,500,000 $1,500,000 $6,000,000 $14,100,000
$1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $6,000,000 $15,000,000
Operating Impacts
312 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
STARR INTERCHANGE @ I-15 ST-160Project No:
Submitting Department:
Project Manager:
Public Works
Scott Fiedler
Project Status: Active
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2020Total Projected Cost: $25,000,000
Prior Years ActualCosts:
Full 4-leg interchange at Starr & I-15
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $10,000,000 $15,000,000 $25,000,000
$10,000,000 $15,000,000 $25,000,000
Operating Impacts
313 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
CENTER ST. - BURKHOLDER BLVD. TO LAKE MEAD PKWY. ST-163Project No:
Submitting Department:
Project Manager:
Public Works
Tom Davy
Project Status: Active
Projected Start Date 07/01/2012
Projected Completion Date: 06/01/2019Total Projected Cost: $2,666,400
Prior Years ActualCosts:
Rehabilitation of existing roadway by means of mill and overlay between Burkholder Blvd. and Lake Mead Pkwy. Project will be coordinated with installation of regional storm drain
infrastructure currently being added to the Clark County Regional Flood Control District Master Plan, utility infrastructure improvements and possible landscape enhancements.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $2,666,400 $2,666,400
$2,666,400 $2,666,400
Operating Impacts
314 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
INFRASTRUCTURE IMPROVEMENTS TO LOW INCOME AREAS ST-164Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Annual
Projected Start Date 07/01/2006
Projected Completion Date: 06/30/2028Total Projected Cost: $4,400,000
Prior Years ActualCosts:
Infrastructure improvements that can include improvements to storm drains, street lights, curbs, sidewalks, and gutters as required.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Grants & Contributions (CDBG, HOME,
LIHTF, Housing & Comm Dvlp, Other)
$440,000 $440,000 $440,000 $440,000 $440,000 $440,000 $1,760,000 $4,400,000
$440,000 $440,000 $440,000 $440,000 $440,000 $440,000 $1,760,000 $4,400,000
Operating Impacts
315 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
MISC. STREET AND APPURTANANCE REPLACEMENTS AND IMPROVEMENTS ST-165Project No:
Submitting Department:
Project Manager:
Public Works
Scott Fiedler
Project Status: Annual
Projected Start Date 07/01/2007
Projected Completion Date: 06/30/2028Total Projected Cost: $3,850,000
Prior Years ActualCosts:
Miscellaneous improvements to and replacements of streets and appurtenances, including short roadway segments, sidewalks, ADA ramps, curbs, gutters, striping and barrier railing as
required.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Gas Tax - 2.35 Cents $385,000 $385,000 $385,000 $385,000 $385,000 $385,000 $1,540,000 $3,850,000
$385,000 $385,000 $385,000 $385,000 $385,000 $385,000 $1,540,000 $3,850,000
Operating Impacts
316 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
ON CALL SERVICE FOR SHORT ROADWAY AND SIDEWALK MAINTENANCE OR REPLACEMENT ST-190Project No:
Submitting Department:
Project Manager:
Public Works
Sajan Abrham
Project Status: Annual
Projected Start Date 07/01/2011
Projected Completion Date: 06/30/2026Total Projected Cost: $3,850,000
Prior Years ActualCosts:
This funding will be used to complete maintenance, rehab and replacement of streets and sidewalks within the City of Henderson. This will be an on-call service contract.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Gas Tax - 1 Cent $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $1,750,000 $3,850,000
$350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $1,750,000 $3,850,000
Operating Impacts
317 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
HORIZON DRIVE FROM I-515 TO BOULDER HIGHWAY ST-207Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Active
Projected Start Date 10/15/2014
Projected Completion Date: 06/30/2020Total Projected Cost: $2,387,200
Prior Years ActualCosts:
Milling and Overlay street and re-configuring medians and sidewalk and adding bike lanes.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,000,000 $1,387,200 $2,387,200
$1,000,000 $1,387,200 $2,387,200
Operating Impacts
318 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
GV NEIGHBORHOOD REHAB - ARROYO GRANDE BOULEVARD ST-219Project No:
Submitting Department:
Project Manager:
Public Works
Al Jankowiak
Project Status: Active
Projected Start Date 07/01/2015
Projected Completion Date: 06/30/2019Total Projected Cost: $843,000
Prior Years ActualCosts:
Design and construction of roadway rehabilitation/reconstruction to address groundwater issues at Arroyo Grande Blvd and Mayan Drive, Harwick Drive and Helmsdale Drive, and Sunset
Road near Scimitar Drive. Rehab improvements to result in up to four (4) travel lanes on Arroyo Grande between Horizon Ridge Pkwy and Sunset Road, with bike lanes, pavement markings,
signage and other appurtenances as needed for a complete and functional project.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $843,000 $843,000
$843,000 $843,000
Operating Impacts
Maintenance Labor $3,511 $3,582 $3,653 $3,726 $3,801 $3,877 $22,150
Supplies $1,371 $1,405 $1,440 $1,476 $1,513 $1,551 $8,756
$30,906 $4,882 $4,987 $5,093 $5,202 $5,314 $5,428
319 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
DOWNTOWN HENDERSON COMPLETE STREETS ST-220Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Active
Projected Start Date 07/01/2015
Projected Completion Date: 06/30/2020Total Projected Cost: $8,250,000
Prior Years ActualCosts:
Design and construction of rehabilitation improvements to the Downtown Henderson business district including Pacific Ave, Market Street, Army Street, Navy Street, Marine Street, Atomic
Street, Panama Street, Basic Road, Atlantic Avenue and Van Wagenen Street.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $6,250,000 $2,000,000 $8,250,000
$6,250,000 $2,000,000 $8,250,000
Operating Impacts
320 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
VALLE VERDE - HORIZON RIDGE TO WARM SPRINGS ST-230Project No:
Submitting Department:
Project Manager:
Public Works
Tom Davy
Project Status: Active
Projected Start Date 07/01/2014
Projected Completion Date: 06/30/2018Total Projected Cost: $3,194,000
Prior Years ActualCosts:
Valle Verde - Horizon Ridge to Warm Springs.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $3,194,000 $3,194,000
$3,194,000 $3,194,000
Operating Impacts
321 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
PARKING LOT MAINTENANCE ST-231Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Proposed
Projected Start Date 07/01/2019
Projected Completion Date: 06/30/2024Total Projected Cost: $320,000
Prior Years ActualCosts:
Rehabilitation or replacement of asphalt in various parking lots throughout the City.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
To Be Determined $120,000 $40,000 $40,000 $40,000 $40,000 $40,000 $320,000
$120,000 $40,000 $40,000 $40,000 $40,000 $40,000 $320,000
Operating Impacts
322 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
VARIOUS RESIDENTIAL ROAD REHABILITATIONS ST-232Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Proposed
Projected Start Date 07/01/2019
Projected Completion Date: 06/30/2025Total Projected Cost: $14,000,000
Prior Years ActualCosts:
Rehabilitation of various residential roadways in the City.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
To Be Determined $4,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $14,000,000
$4,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $14,000,000
Operating Impacts
323 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
ANTHEM PARKWAY-SUN CITY ANTHEM SIDEWALK-TRAIL IMPROVEMENTS ST-237Project No:
Submitting Department:
Project Manager:
Public Works
Tom Davy
Project Status: Proposed
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2019Total Projected Cost: $2,500,000
Prior Years ActualCosts:
Trail and ramp improvements to Anthem/Sun City Anthem Loop.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Gas Tax - 1% Room Tax $2,500,000 $2,500,000
$2,500,000 $2,500,000
Operating Impacts
324 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
PEDESTRIAN SAFETY IMPROVEMENTS ST-238Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Active
Projected Start Date 07/01/2017
Projected Completion Date: 12/31/2027Total Projected Cost: $3,600,000
Prior Years ActualCosts:
Crosswalk improvements, medians, RRFBs, Hawk and other pedestrian crossing enhancements
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $1,200,000 $3,600,000
$400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $1,200,000 $3,600,000
Operating Impacts
325 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
ROUNDABOUT PROJECTS ST-239Project No:
Submitting Department:
Project Manager:
Public Works
Tom Davy
Project Status: Proposed
Projected Start Date 07/01/2018
Projected Completion Date: 06/30/2026Total Projected Cost: $6,000,000
Prior Years ActualCosts:
Design and construction of roundabouts as an alternative to traffic signals at major intersections.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
To Be Determined $1,500,000 $1,500,000 $1,500,000 $1,500,000 $6,000,000
$1,500,000 $1,500,000 $1,500,000 $1,500,000 $6,000,000
Operating Impacts
326 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
I-215 REGIONAL TRAIL CONNECTIVITY - GREEN VALLEY TO PECOS ST-241Project No:
Submitting Department:
Project Manager:
Public Works
Kevin Futch
Project Status: Active
Projected Start Date 11/01/2016
Projected Completion Date: 12/31/2018Total Projected Cost: $532,000
Prior Years ActualCosts:
Shared use path along I-215 from Green Valley to Pecos
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $22,000 $22,000
Grants & Contributions (SNPLMA, Fire,
Homeland Security, Police, Parks & Rec,
PW Grants, Private Contributions)
$510,000 $510,000
$532,000 $532,000
Operating Impacts
327 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
APPALOOSA - WAGONWHEEL TO EQUESTRIAN ST-242Project No:
Submitting Department:
Project Manager:
Public Works
Tom Davy
Project Status: Active
Projected Start Date 06/30/2016
Projected Completion Date: 12/31/2018Total Projected Cost: $884,000
Prior Years ActualCosts:
Curb and gutter, etc. as related to improvements at Appaloosa Storm Drain.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $884,000 $884,000
$884,000 $884,000
Operating Impacts
328 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
NDOT I-215 TRAIL BRIDGES ST-243Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Active
Projected Start Date 10/01/2016
Projected Completion Date: 01/31/2022Total Projected Cost: $4,513,500
Prior Years ActualCosts:
Pedestrian bridges located along the I-215 regional trail generally located at Pecos, Green Valley and Valle Verde.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Grants & Contributions (SNPLMA, Fire,
Homeland Security, Police, Parks & Rec,
PW Grants, Private Contributions)
$51,500 $377,000 $736,500 $3,200,000 $4,365,000
Regional Transportation Commission $148,500 $148,500
$200,000 $377,000 $736,500 $3,200,000 $4,513,500
Operating Impacts
329 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
SEVEN HILLS DR. - GRAND HILLS DR. TO ST. ROSE PKWY. ST-245Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Active
Projected Start Date 07/01/2020
Projected Completion Date: 06/30/2022Total Projected Cost: $4,000,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,000,000 $3,000,000 $4,000,000
$1,000,000 $3,000,000 $4,000,000
Operating Impacts
330 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
HEATHER DR. - GREENWAY RD. TO COLLEGE DR. ST-246Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Active
Projected Start Date 07/01/2018
Projected Completion Date: 06/30/2020Total Projected Cost: $1,500,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $300,000 $1,200,000 $1,500,000
$300,000 $1,200,000 $1,500,000
Operating Impacts
331 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
FOSTER/PRICE ST. - BOULDER HWY. TO BARRET ST. ST-247Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Active
Projected Start Date 07/01/2018
Projected Completion Date: 06/30/2020Total Projected Cost: $2,500,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $625,000 $1,875,000 $2,500,000
$625,000 $1,875,000 $2,500,000
Operating Impacts
332 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
GREENWAY ROAD - BOULDER HWY TO PARADISE HILLS DR ST-248Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Active
Projected Start Date 07/01/2018
Projected Completion Date: 06/30/2020Total Projected Cost: $2,700,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $675,000 $2,025,000 $2,700,000
$675,000 $2,025,000 $2,700,000
Operating Impacts
333 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
WINDMILL LANE - ARROYO GRANDE PKWY TO GREEN VALLEY PKWY ST-249Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Active
Projected Start Date 07/01/2021
Projected Completion Date: 06/30/2023Total Projected Cost: $3,250,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,250,000 $2,000,000 $3,250,000
$1,250,000 $2,000,000 $3,250,000
Operating Impacts
334 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
APPALOOSA - WAGONWHEEL TO EQUESTRIAN PHASE 2 ST-250Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Proposed
Projected Start Date 07/01/2022
Projected Completion Date: 06/30/2024Total Projected Cost: $3,250,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,250,000 $2,000,000 $3,250,000
$1,250,000 $2,000,000 $3,250,000
Operating Impacts
335 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
DOWNTOWN HENDERSON COMPLETE STREETS PHASE 2 ST-251Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Proposed
Projected Start Date 07/01/2022
Projected Completion Date: 06/30/2025Total Projected Cost: $7,500,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,500,000 $2,000,000 $4,000,000 $7,500,000
$1,500,000 $2,000,000 $4,000,000 $7,500,000
Operating Impacts
336 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
WATER STREET - MAJOR AVENUE TO LAKE MEAD PKWY ST-252Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Active
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2019Total Projected Cost: $3,400,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $3,400,000 $3,400,000
$3,400,000 $3,400,000
Operating Impacts
337 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
PUEBLO BLVD - CONCORD WAY TO LAKE MEAD PKWY ST-255Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Proposed
Projected Start Date 07/01/2025
Projected Completion Date: 06/01/2027Total Projected Cost: $3,100,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $3,100,000 $3,100,000
$3,100,000 $3,100,000
Operating Impacts
338 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
WAGONWHEEL DRIVE - I-515 TO FOOTHILLS DRIVE ST-257Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Proposed
Projected Start Date 07/01/2019
Projected Completion Date: 06/30/2021Total Projected Cost: $1,750,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $512,100 $1,237,900 $1,750,000
$512,100 $1,237,900 $1,750,000
Operating Impacts
339 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
CITY OF HENDERSON STREET MAINTENANCE PHASE 1 ST-260Project No:
Submitting Department:
Project Manager:
Public Works
Lance Olson
Project Status: Annual
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2022Total Projected Cost: $16,099,600
Prior Years ActualCosts:
Rd Recons/Rehab/Resurf
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $4,024,900 $4,024,900 $4,024,900 $4,024,900 $16,099,600
$4,024,900 $4,024,900 $4,024,900 $4,024,900 $16,099,600
Operating Impacts
340 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
VIA NOBILA - LAS VEGAS BLVD TO VIA INSPIRADA ST-263Project No:
Submitting Department:
Project Manager:
Public Works
Tom Davy
Project Status: Active
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2028Total Projected Cost: $4,000,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $4,000,000 $4,000,000
$4,000,000 $4,000,000
Operating Impacts
341 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
CITY OF HENDERSON STREET MAINTENANCE PHASE 2 ST-270Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Annual
Projected Start Date 07/01/2022
Projected Completion Date: 06/30/2027Total Projected Cost: $20,124,500
Prior Years ActualCosts:
Rd Recons/Rehab/Resurf
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $4,024,900 $4,024,900 $12,074,700 $20,124,500
$4,024,900 $4,024,900 $12,074,700 $20,124,500
Operating Impacts
342 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
EASTERN AVENUE IMPROVEMENTS PHASE 1 - ST. ROSE PKWY TO I-215 ST-271Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Active
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2019Total Projected Cost: $4,000,000
Prior Years ActualCosts:
Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,500,000 $2,500,000 $4,000,000
$1,500,000 $2,500,000 $4,000,000
Operating Impacts
343 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
ST. ROSE PKWY/PECOS ROAD/I-215 INTERCHANGE IMPROVEMENTS - PHASE 1 ST-282Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Proposed
Projected Start Date 07/01/2021
Projected Completion Date: 06/30/2023Total Projected Cost: $6,000,000
Prior Years ActualCosts:
Interchange improvements including rehabilitation of adjacent roadway and appurtenances
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,000,000 $5,000,000 $6,000,000
$1,000,000 $5,000,000 $6,000,000
Operating Impacts
344 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
VIA INSPIRADA TRAIL - LAS VEGAS BLVD TO EXECUTIVE AIRPORT/VOLUNTEER (NDOT) ST-291Project No:
Submitting Department:
Project Manager:
Public Works
Amie Wojtech
Project Status: Proposed
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2020Total Projected Cost: $782,000
Prior Years ActualCosts:
Trail along Via Inspirada
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $42,000 $42,000
Grants & Contributions (SNPLMA, Fire,
Homeland Security, Police, Parks & Rec,
PW Grants, Private Contributions)
$740,000 $740,000
$740,000 $42,000 $782,000
Operating Impacts
345 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
BUS TURNOUTS (NDOT FUNDED) ST-293Project No:
Submitting Department:
Project Manager:
Public Works
Tom Davy
Project Status: Proposed
Projected Start Date 10/01/2017
Projected Completion Date: 09/30/2020Total Projected Cost: $657,895
Prior Years ActualCosts:
various bus turnouts throughout the city TBD
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Grants & Contributions (SNPLMA, Fire,
Homeland Security, Police, Parks & Rec,
PW Grants, Private Contributions)
$100,000 $525,000 $625,000
To Be Determined $32,895 $32,895
$100,000 $525,000 $32,895 $657,895
Operating Impacts
346 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
ROMA HILLS DRIVE ST-298Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Active
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2019Total Projected Cost: $1,500,000
Prior Years ActualCosts:
Traffic calming improvements along Roma Hills Drive
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,500,000 $1,500,000
$1,500,000 $1,500,000
Operating Impacts
347 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
STEPHANIE ST - I-215 TO DRAGONRIDGE CC ST-299Project No:
Submitting Department:
Project Manager:
Public Works
Scott Fiedler
Project Status: Active
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2019Total Projected Cost: $1,500,000
Prior Years ActualCosts:
road rehab and improvements to Stephanie St
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $1,500,000 $1,500,000
$1,500,000 $1,500,000
Operating Impacts
348 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
UPRR - ANNUAL INSPECTION AND REPAIRS ST-300Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Annual
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2028Total Projected Cost: $770,000
Prior Years ActualCosts:
Annual inspection and repair of UPRR tracks and related appurtenances.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
To Be Determined $210,000 $70,000 $70,000 $70,000 $70,000 $280,000 $770,000
$210,000 $70,000 $70,000 $70,000 $70,000 $280,000 $770,000
Operating Impacts
349 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Streets
PACIFIC AVENUE - HORIZON DRIVE TO APIAN WAY ST-302Project No:
Submitting Department:
Project Manager:
Public Works Project Status: Proposed
Projected Start Date 07/01/2019
Projected Completion Date: 06/30/2021Total Projected Cost: $1,000,000
Prior Years ActualCosts:
roadway improvements
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $250,000 $750,000 $1,000,000
$250,000 $750,000 $1,000,000
Operating Impacts
350 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
GALLERIA DR/WHITNEY RANCH RD SIGNALIZATION TC-047Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez
Project Status: Proposed
Projected Start Date 07/01/2021
Projected Completion Date: 06/30/2022Total Projected Cost: $530,000
Prior Years ActualCosts:
Install traffic signal. Intersection No. 012
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $530,000 $530,000
$530,000 $530,000
Operating Impacts
Maintenance Labor $2,500 $2,600 $19,800 $24,900
Operations Labor $2,500 $2,600 $19,800 $24,900
$49,800 $5,000 $5,200 $39,600
351 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
MARYLAND PKWY. / SUNRIDGE HEIGHTS PKWY. SIGNALIZATION TC-115Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez
Project Status: Proposed
Projected Start Date 07/03/2018
Projected Completion Date: 06/28/2019Total Projected Cost: $530,000
Prior Years ActualCosts:
Install traffic signal, Intersection No. 205.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $530,000 $530,000
$530,000 $530,000
Operating Impacts
Maintenance Labor $2,414 $2,474 $2,536 $5,263 $12,687
Supplies $2,086 $2,148 $2,213 $4,627 $11,074
$23,761 $4,500 $4,622 $4,749 $9,890
352 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
SUNRIDGE HEIGHTS PKWY. / EXECUTIVE AIRPORT DR. SIGNALIZATION TC-121Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez
Project Status: Proposed
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2018Total Projected Cost: $530,000
Prior Years ActualCosts:
Install traffic signal, Intersection No. 204.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $530,000 $530,000
$530,000 $530,000
Operating Impacts
Maintenance Labor $2,414 $2,474 $13,779 $18,667
Supplies $2,086 $2,148 $11,820 $16,054
$34,721 $4,500 $4,622 $25,599
353 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
GREENWAY RD. / MISSION DR. TRAFFIC CONTROL TC-137Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez
Project Status: Proposed
Projected Start Date 07/01/2020
Projected Completion Date: 06/30/2021Total Projected Cost: $530,000
Prior Years ActualCosts:
Install traffic signal, Intersection No. 062.
****This project is going to be completed with ST-248****
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $530,000 $530,000
$530,000 $530,000
Operating Impacts
Maintenance Labor $2,474 $2,536 $2,599 $5,464 $13,073
Supplies $2,148 $2,213 $2,279 $4,748 $11,388
$24,461 $4,622 $4,749 $4,878 $10,212
354 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
COLLEGE DR. / MISSION DR. TRAFFIC CONTROL TC-138Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriquez
Project Status: Proposed
Projected Start Date 07/01/2020
Projected Completion Date: 06/30/2021Total Projected Cost: $530,000
Prior Years ActualCosts:
Install traffic signal, Intersection No. 049.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $530,000 $530,000
$530,000 $530,000
Operating Impacts
Maintenance Labor $7 $10,273 $10,280
Supplies $8,988 $8,988
$19,268 $7 $19,261
355 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
DESERT SHADOW TRL. / PASEO VERDE PKWY. SIGNALIZATION TC-178Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez
Project Status: Proposed
Projected Start Date 07/01/2019
Projected Completion Date: 06/30/2021Total Projected Cost: $450,000
Prior Years ActualCosts:
Install traffic signal, Intersection No. 054. FRI Funding
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $150,000 $300,000 $450,000
Developer - Traffic Control
$150,000 $300,000 $450,000
Operating Impacts
Maintenance Labor $2,664 $11,200 $13,864
Supplies $2,348 $9,872 $12,220
$26,084 $5,012 $21,072
356 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
TRAFFIC SIGN REPLACEMENT PROGRAM TC-183Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez & Luke Smith
Project Status: Annual
Projected Start Date 07/01/2010
Projected Completion Date: 06/30/2030Total Projected Cost: $405,000
Prior Years ActualCosts:
This program is to replace signage in older neighborhoods that no longer meet the current retro-reflectivity standards. This program will include all traffic signs within the identified areas
on an annual basis.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Capital Replacement - PW Traffic $60,000 $30,000 $30,000 $30,000 $30,000 $190,000 $370,000
$60,000 $30,000 $30,000 $30,000 $30,000 $190,000 $370,000
Operating Impacts
357 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
MISCELLANEOUS STRIPING CONTRACT TC-184Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez or Luke Smith
Project Status: Annual
Projected Start Date 07/01/2009
Projected Completion Date: 06/30/2027Total Projected Cost: $675,000
Prior Years ActualCosts:
Miscellaneous re-striping of roadways throughout City.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Gas Tax - 2.35 Cents $75,000 $75,000 $75,000 $75,000 $75,000 $75,000 $225,000 $675,000
$75,000 $75,000 $75,000 $75,000 $75,000 $75,000 $225,000 $675,000
Operating Impacts
358 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
CROSSWALK AND LEGEND MAINTENANCE AND MISCELLANEOUS STRIPING TC-198Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez & Luke Smith
Project Status: Annual
Projected Start Date 07/01/2014
Projected Completion Date: 06/30/2029Total Projected Cost: $3,575,000
Prior Years ActualCosts:
Routine maintenance of crosswalk, bike lane, and other pavement markings.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Capital Replacement - PW Traffic $650,000 $325,000 $325,000 $325,000 $325,000 $1,625,000 $3,575,000
$650,000 $325,000 $325,000 $325,000 $325,000 $1,625,000 $3,575,000
Operating Impacts
359 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
FIBER MAINTENANCE TC-202Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez & Luke Smith
Project Status: Annual
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2029Total Projected Cost: $330,000
Prior Years ActualCosts:
Perform routine maintenance on fiber-optic cabling across the City's traffic network.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Capital Replacement - PW Traffic $60,000 $30,000 $30,000 $30,000 $30,000 $150,000 $330,000
$60,000 $30,000 $30,000 $30,000 $30,000 $150,000 $330,000
Operating Impacts
360 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
ADA RAMPS AT SIGNALS TC-203Project No:
Submitting Department:
Project Manager:
Public Works
Scott Jarvis
Project Status: Active
Projected Start Date 07/01/2016
Projected Completion Date: 06/30/2024Total Projected Cost: $950,000
Prior Years ActualCosts:
Install ADA ramps compliant to the current standard at various traffic signal intersections.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Capital Replacement - PW Traffic $200,000 $50,000 $50,000 $325,000 $325,000 $950,000
$200,000 $50,000 $50,000 $325,000 $325,000 $950,000
Operating Impacts
361 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
RAILROAD REPAIRS TC-204Project No:
Submitting Department:
Project Manager:
Public Works
Luke Smith
Project Status: Proposed
Projected Start Date 07/01/2015
Projected Completion Date: 06/30/2024Total Projected Cost: $2,200,000
Prior Years ActualCosts:
Various repairs to City-owned sections of railroad.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
To Be Determined $600,000 $200,000 $200,000 $200,000 $200,000 $800,000 $2,200,000
$600,000 $200,000 $200,000 $200,000 $200,000 $800,000 $2,200,000
Operating Impacts
362 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
LANE AND BIKE LANE RESTRIPING- VARIOUS LOCATIONS TC-213Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez & Luke Smith
Project Status: Annual
Projected Start Date 07/01/2015
Projected Completion Date: 06/30/2030Total Projected Cost: $900,000
Prior Years ActualCosts:
Lane and bike lane restriping
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Capital Replacement - PW Traffic $200,000 $100,000 $100,000 $100,000 $100,000 $300,000 $900,000
$200,000 $100,000 $100,000 $100,000 $100,000 $300,000 $900,000
Operating Impacts
363 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
EASTERN AVE TRAFFIC SIGNALS - AT PECOS RIDGE AND ANTHONY COURT TC-214Project No:
Submitting Department:
Project Manager:
Public Works
Ed McGuire/ Alyssa Rodriguez
Project Status: Proposed
Projected Start Date 07/01/2018
Projected Completion Date: 06/30/2019Total Projected Cost: $750,000
Prior Years ActualCosts:
(2) Traffic Signals: Eastern Ave at Peco Ridge and an off-set T- traffic signal at Summit Grove and Anthony Court.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $750,000 $750,000
$750,000 $750,000
Operating Impacts
Maintenance Labor $4,200 $4,500 $4,800 $5,200 $5,500 $18,500 $42,700
Operations Labor $4,200 $4,200 $4,200 $5,200 $5,200 $17,900 $40,900
$83,600 $8,400 $8,700 $9,000 $10,400 $10,700 $36,400
364 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
GIBSON/WIGWAM TRAFFIC SIGNAL TC-216Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez
Project Status: Active
Projected Start Date 07/01/2018
Projected Completion Date: 06/30/2019Total Projected Cost: $550,000
Prior Years ActualCosts:
Remove existing median in intersection and construct signal improvements at the intersection of Gibson and Wigwam. Int. 127.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Regional Transportation Commission $550,000 $550,000
$550,000 $550,000
Operating Impacts
Operations Labor $2,500 $2,500 $2,500 $2,500 $2,500 $10,000 $22,500
Maintenance Labor $2,500 $2,500 $2,500 $2,500 $2,500 $10,000 $22,500
$45,000 $5,000 $5,000 $5,000 $5,000 $5,000 $20,000
365 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
PEDESTRIAN CROSSWALK ENHANCEMENTS- VARIOUS LOCATIONS TC-217Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez
Project Status: Active
Projected Start Date 07/01/2016
Projected Completion Date: 06/30/2020Total Projected Cost: $855,000
Prior Years ActualCosts:
There are approximately 50 locations within the City needing pedestrian activated flashers either Rectangular Rapid Flashing Beacon's or Hawk signal.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
NDOT Funding
Developer - Traffic Control $585,000 $270,000 $855,000
Regional Transportation Commission
$585,000 $270,000 $855,000
Operating Impacts
366 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
UPRR - SIGNALS AND CROSSMARKINGS TC-219Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez
Project Status: Annual
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2028Total Projected Cost: $880,000
Prior Years ActualCosts:
Annual maintenance to the UPRR signals and cross markings.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
To Be Determined $240,000 $80,000 $80,000 $80,000 $80,000 $320,000 $880,000
$240,000 $80,000 $80,000 $80,000 $80,000 $320,000 $880,000
Operating Impacts
367 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
City of Henderson
Projects by Program
2018/19 - 2023/24 Capital Improvement Program
Transportation Traffic Control
SIGNAL REPLACEMENT & UPGRADES - BOULDER/WAGONWHEEL TC-220Project No:
Submitting Department:
Project Manager:
Public Works
Alyssa Rodriguez
Project Status: Proposed
Projected Start Date 07/01/2017
Projected Completion Date: 06/30/2018Total Projected Cost: $900,000
Prior Years ActualCosts:
Replacement of foundations, signal poles and signal arms to meet current specifications. Replace deteriorated wire.
Project Description:
Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future
Gas Tax - 1% Room Tax $900,000 $900,000
$900,000 $900,000
Operating Impacts
Notes:
368 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
369 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms
This page intentionally left blank