2018/19 - 2023/24 capital improvement program … · city of henderson projects by program 2018/19...

68
City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights STREET LIGHT KNOCKDOWN PROGRAM SL-025 Project No: Submitting Department: Project Manager: Public Works Luke Smith Project Status: Annual Projected Start Date 07/01/2007 Projected Completion Date: 06/30/2029 Total Projected Cost: $12,526,000 Prior Years ActualCosts: This is an annual program to replace existing street lights. This project will be used to replace poles that are knocked down. Project Description: Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future Other Reimbursed $230,000 $230,000 $230,000 $230,000 $230,000 $690,000 $1,840,000 Capital Replacement - PW Traffic $46,000 $130,000 $130,000 $130,000 $2,050,000 $2,050,000 $6,150,000 $10,686,000 $46,000 $360,000 $360,000 $360,000 $2,280,000 $2,280,000 $6,840,000 $12,526,000 Operating Impacts 302 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Upload: letuyen

Post on 06-Sep-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Street Lights

STREET LIGHT KNOCKDOWN PROGRAM SL-025Project No:

Submitting Department:

Project Manager:

Public Works

Luke Smith

Project Status: Annual

Projected Start Date 07/01/2007

Projected Completion Date: 06/30/2029Total Projected Cost: $12,526,000

Prior Years ActualCosts:

This is an annual program to replace existing street lights. This project will be used to replace poles that are knocked down.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Other Reimbursed $230,000 $230,000 $230,000 $230,000 $230,000 $690,000 $1,840,000

Capital Replacement - PW Traffic $46,000 $130,000 $130,000 $130,000 $2,050,000 $2,050,000 $6,150,000 $10,686,000

$46,000 $360,000 $360,000 $360,000 $2,280,000 $2,280,000 $6,840,000 $12,526,000

Operating Impacts

302 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 2: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Street Lights

PAINTED/CONCRETE SL POLE REPLACEMENT SL-027Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez

Project Status: Annual

Projected Start Date 07/01/2014

Projected Completion Date: 06/30/2029Total Projected Cost: $2,750,000

Prior Years ActualCosts:

In the older areas of the City, the existing painted street light poles will be replaced with galvanized poles having a much longer life.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Capital Replacement - PW Traffic $500,000 $250,000 $250,000 $250,000 $250,000 $1,250,000 $2,750,000

$500,000 $250,000 $250,000 $250,000 $250,000 $1,250,000 $2,750,000

Operating Impacts

303 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 3: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Street Lights

STREETLIGHT WIRE THEFT REPLACEMENT SL-208Project No:

Submitting Department:

Project Manager:

Public Works

Luke Smith/Alyssa Rodriguez

Project Status: Annual

Projected Start Date 10/13/2014

Projected Completion Date: 06/30/2035Total Projected Cost: $1,100,000

Prior Years ActualCosts:

Replace stolen streelight copper wire.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Capital Replacement - PW Traffic $200,000 $100,000 $100,000 $100,000 $100,000 $500,000 $1,100,000

$200,000 $100,000 $100,000 $100,000 $100,000 $500,000 $1,100,000

Operating Impacts

304 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 4: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

SUNRIDGE HEIGHTS - EXECUTIVE AIRPORT TO SEVEN HILLS DRIVE ST-042Project No:

Submitting Department:

Project Manager:

Public Works

Tom Davy

Project Status: Active

Projected Start Date 07/01/2016

Projected Completion Date: 06/30/2019Total Projected Cost: $1,629,000

Prior Years ActualCosts:

Construct four-lane roadway along Sunridge Heights between Executive Airport and Seven Hills Drive, with traffic and drainage appurtenances per RTC standards.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,629,000 $1,629,000

$1,629,000 $1,629,000

Operating Impacts

Maintenance Labor $2,877 $2,934 $2,993 $3,053 $3,114 $3,176 $18,147

Supplies $650 $670 $683 $697 $711 $725 $4,136

$22,283 $3,527 $3,604 $3,676 $3,750 $3,825 $3,901

305 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 5: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

AMIGO - ST. ROSE TO SUNRIDGE HEIGHTS ST-047Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Proposed

Projected Start Date 07/01/2020

Projected Completion Date: 06/30/2021Total Projected Cost: $1,500,000

Prior Years ActualCosts:

Construction of new 80-foot arterial with 2 travel lanes each way and center double turn lane.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Developer - Streets

To Be Determined $1,500,000 $1,500,000

$1,500,000 $1,500,000

Operating Impacts

Maintenance Labor $2,993 $3,053 $3,114 $6,416 $15,576

Supplies $683 $697 $711 $1,465 $3,556

$19,132 $3,676 $3,750 $3,825 $7,881

306 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 6: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

ATHENS AVE - RACETRACK TO FOOTHILLS - PH II ST-059Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Proposed

Projected Start Date 07/01/2019

Projected Completion Date: 06/30/2021Total Projected Cost: $1,000,000

Prior Years ActualCosts:

Widen to four travel lanes.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Developer - Streets $100,000 $900,000 $1,000,000

$100,000 $900,000 $1,000,000

Operating Impacts

Maintenance Labor $2,993 $3,053 $3,114 $3,176 $12,336

Supplies $683 $697 $711 $725 $2,816

$15,152 $3,676 $3,750 $3,825 $3,901

307 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 7: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

BARRETT ST - WARM SPRINGS TO BOULDER HWY ST-060Project No:

Submitting Department:

Project Manager:

Public Works

Scott Fiedler

Project Status: Proposed

Projected Start Date 07/01/2027

Projected Completion Date: 06/01/2029Total Projected Cost: $3,730,000

Prior Years ActualCosts:

Construct new four lane roadway with signal at Warm Springs Road per RTC standards.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

To Be Determined $3,730,000 $3,730,000

$3,730,000 $3,730,000

Operating Impacts

Maintenance Labor

Supplies

308 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 8: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

BERMUDA ROAD - VOUNTEER TO ST. ROSE PARKWAY ST-062Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Active

Projected Start Date 07/01/2018

Projected Completion Date: 06/30/2020Total Projected Cost: $3,000,000

Prior Years ActualCosts:

Construct to six travel lanes

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $750,000 $2,250,000 $3,000,000

$750,000 $2,250,000 $3,000,000

Operating Impacts

Maintenance Labor $3,114 $3,176 $6,290

Supplies $711 $725 $1,436

$7,726 $3,825 $3,901

309 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 9: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

FOOTHILLS DR - BOULDER HIGHWAY TO EQUESTRIAN ST-072Project No:

Submitting Department:

Project Manager:

Public Works

Scott Fiedler

Project Status: Proposed

Projected Start Date 07/01/2028

Projected Completion Date: 06/30/2028Total Projected Cost: $3,300,000

Prior Years ActualCosts:

Construct new four lane roadway.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Developer - Streets $3,300,000 $3,300,000

$3,300,000 $3,300,000

Operating Impacts

Maintenance Labor $2,877 $2,877

Supplies $650 $650

$3,527 $3,527

310 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 10: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

STARR/EXECUTIVE AIRPORT - LAS VEGAS BOULEVARD TO BICENTENNIAL ST-139Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Active

Projected Start Date 07/01/2016

Projected Completion Date: 06/30/2019Total Projected Cost: $1,000,000

Prior Years ActualCosts:

Construction of four-lane roadway with traffic and drainage appurtenances per RTC standards.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,000,000 $1,000,000

$1,000,000 $1,000,000

Operating Impacts

Maintenance Labor $2,965 $2,965 $2,865 $2,865 $2,965 $2,965 $17,590

Supplies $420 $435 $450 $465 $480 $495 $2,745

$20,335 $3,385 $3,400 $3,315 $3,330 $3,445 $3,460

311 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 11: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

ON CALL STREET PATCHING ST-146Project No:

Submitting Department:

Project Manager:

Public Works

Scott Fiedler

Project Status: Annual

Projected Start Date 07/01/2006

Projected Completion Date: 06/30/2028Total Projected Cost: $15,000,000

Prior Years ActualCosts:

Yearly contract funded by gas tax revenues that will generally consist of crack seal, patching, and slurry seal (asset management) of the existing transportation network (asphalt of roadways

only) at various locations throughout the city.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Gas Tax - 1% Room Tax $100,000 $100,000 $100,000 $300,000

Gas Tax - 1 Cent $200,000 $200,000 $200,000 $600,000

Gas Tax - 2.35 Cents $1,200,000 $1,200,000 $1,200,000 $1,500,000 $1,500,000 $1,500,000 $6,000,000 $14,100,000

$1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000 $6,000,000 $15,000,000

Operating Impacts

312 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 12: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

STARR INTERCHANGE @ I-15 ST-160Project No:

Submitting Department:

Project Manager:

Public Works

Scott Fiedler

Project Status: Active

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2020Total Projected Cost: $25,000,000

Prior Years ActualCosts:

Full 4-leg interchange at Starr & I-15

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $10,000,000 $15,000,000 $25,000,000

$10,000,000 $15,000,000 $25,000,000

Operating Impacts

313 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 13: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

CENTER ST. - BURKHOLDER BLVD. TO LAKE MEAD PKWY. ST-163Project No:

Submitting Department:

Project Manager:

Public Works

Tom Davy

Project Status: Active

Projected Start Date 07/01/2012

Projected Completion Date: 06/01/2019Total Projected Cost: $2,666,400

Prior Years ActualCosts:

Rehabilitation of existing roadway by means of mill and overlay between Burkholder Blvd. and Lake Mead Pkwy. Project will be coordinated with installation of regional storm drain

infrastructure currently being added to the Clark County Regional Flood Control District Master Plan, utility infrastructure improvements and possible landscape enhancements.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $2,666,400 $2,666,400

$2,666,400 $2,666,400

Operating Impacts

314 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 14: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

INFRASTRUCTURE IMPROVEMENTS TO LOW INCOME AREAS ST-164Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Annual

Projected Start Date 07/01/2006

Projected Completion Date: 06/30/2028Total Projected Cost: $4,400,000

Prior Years ActualCosts:

Infrastructure improvements that can include improvements to storm drains, street lights, curbs, sidewalks, and gutters as required.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Grants & Contributions (CDBG, HOME,

LIHTF, Housing & Comm Dvlp, Other)

$440,000 $440,000 $440,000 $440,000 $440,000 $440,000 $1,760,000 $4,400,000

$440,000 $440,000 $440,000 $440,000 $440,000 $440,000 $1,760,000 $4,400,000

Operating Impacts

315 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 15: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

MISC. STREET AND APPURTANANCE REPLACEMENTS AND IMPROVEMENTS ST-165Project No:

Submitting Department:

Project Manager:

Public Works

Scott Fiedler

Project Status: Annual

Projected Start Date 07/01/2007

Projected Completion Date: 06/30/2028Total Projected Cost: $3,850,000

Prior Years ActualCosts:

Miscellaneous improvements to and replacements of streets and appurtenances, including short roadway segments, sidewalks, ADA ramps, curbs, gutters, striping and barrier railing as

required.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Gas Tax - 2.35 Cents $385,000 $385,000 $385,000 $385,000 $385,000 $385,000 $1,540,000 $3,850,000

$385,000 $385,000 $385,000 $385,000 $385,000 $385,000 $1,540,000 $3,850,000

Operating Impacts

316 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 16: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

ON CALL SERVICE FOR SHORT ROADWAY AND SIDEWALK MAINTENANCE OR REPLACEMENT ST-190Project No:

Submitting Department:

Project Manager:

Public Works

Sajan Abrham

Project Status: Annual

Projected Start Date 07/01/2011

Projected Completion Date: 06/30/2026Total Projected Cost: $3,850,000

Prior Years ActualCosts:

This funding will be used to complete maintenance, rehab and replacement of streets and sidewalks within the City of Henderson. This will be an on-call service contract.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Gas Tax - 1 Cent $350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $1,750,000 $3,850,000

$350,000 $350,000 $350,000 $350,000 $350,000 $350,000 $1,750,000 $3,850,000

Operating Impacts

317 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 17: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

HORIZON DRIVE FROM I-515 TO BOULDER HIGHWAY ST-207Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Active

Projected Start Date 10/15/2014

Projected Completion Date: 06/30/2020Total Projected Cost: $2,387,200

Prior Years ActualCosts:

Milling and Overlay street and re-configuring medians and sidewalk and adding bike lanes.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,000,000 $1,387,200 $2,387,200

$1,000,000 $1,387,200 $2,387,200

Operating Impacts

318 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 18: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

GV NEIGHBORHOOD REHAB - ARROYO GRANDE BOULEVARD ST-219Project No:

Submitting Department:

Project Manager:

Public Works

Al Jankowiak

Project Status: Active

Projected Start Date 07/01/2015

Projected Completion Date: 06/30/2019Total Projected Cost: $843,000

Prior Years ActualCosts:

Design and construction of roadway rehabilitation/reconstruction to address groundwater issues at Arroyo Grande Blvd and Mayan Drive, Harwick Drive and Helmsdale Drive, and Sunset

Road near Scimitar Drive. Rehab improvements to result in up to four (4) travel lanes on Arroyo Grande between Horizon Ridge Pkwy and Sunset Road, with bike lanes, pavement markings,

signage and other appurtenances as needed for a complete and functional project.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $843,000 $843,000

$843,000 $843,000

Operating Impacts

Maintenance Labor $3,511 $3,582 $3,653 $3,726 $3,801 $3,877 $22,150

Supplies $1,371 $1,405 $1,440 $1,476 $1,513 $1,551 $8,756

$30,906 $4,882 $4,987 $5,093 $5,202 $5,314 $5,428

319 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 19: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

DOWNTOWN HENDERSON COMPLETE STREETS ST-220Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Active

Projected Start Date 07/01/2015

Projected Completion Date: 06/30/2020Total Projected Cost: $8,250,000

Prior Years ActualCosts:

Design and construction of rehabilitation improvements to the Downtown Henderson business district including Pacific Ave, Market Street, Army Street, Navy Street, Marine Street, Atomic

Street, Panama Street, Basic Road, Atlantic Avenue and Van Wagenen Street.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $6,250,000 $2,000,000 $8,250,000

$6,250,000 $2,000,000 $8,250,000

Operating Impacts

320 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 20: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

VALLE VERDE - HORIZON RIDGE TO WARM SPRINGS ST-230Project No:

Submitting Department:

Project Manager:

Public Works

Tom Davy

Project Status: Active

Projected Start Date 07/01/2014

Projected Completion Date: 06/30/2018Total Projected Cost: $3,194,000

Prior Years ActualCosts:

Valle Verde - Horizon Ridge to Warm Springs.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $3,194,000 $3,194,000

$3,194,000 $3,194,000

Operating Impacts

321 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 21: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

PARKING LOT MAINTENANCE ST-231Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Proposed

Projected Start Date 07/01/2019

Projected Completion Date: 06/30/2024Total Projected Cost: $320,000

Prior Years ActualCosts:

Rehabilitation or replacement of asphalt in various parking lots throughout the City.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

To Be Determined $120,000 $40,000 $40,000 $40,000 $40,000 $40,000 $320,000

$120,000 $40,000 $40,000 $40,000 $40,000 $40,000 $320,000

Operating Impacts

322 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 22: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

VARIOUS RESIDENTIAL ROAD REHABILITATIONS ST-232Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Proposed

Projected Start Date 07/01/2019

Projected Completion Date: 06/30/2025Total Projected Cost: $14,000,000

Prior Years ActualCosts:

Rehabilitation of various residential roadways in the City.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

To Be Determined $4,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $14,000,000

$4,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $2,000,000 $14,000,000

Operating Impacts

323 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 23: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

ANTHEM PARKWAY-SUN CITY ANTHEM SIDEWALK-TRAIL IMPROVEMENTS ST-237Project No:

Submitting Department:

Project Manager:

Public Works

Tom Davy

Project Status: Proposed

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2019Total Projected Cost: $2,500,000

Prior Years ActualCosts:

Trail and ramp improvements to Anthem/Sun City Anthem Loop.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Gas Tax - 1% Room Tax $2,500,000 $2,500,000

$2,500,000 $2,500,000

Operating Impacts

324 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 24: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

PEDESTRIAN SAFETY IMPROVEMENTS ST-238Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Active

Projected Start Date 07/01/2017

Projected Completion Date: 12/31/2027Total Projected Cost: $3,600,000

Prior Years ActualCosts:

Crosswalk improvements, medians, RRFBs, Hawk and other pedestrian crossing enhancements

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $1,200,000 $3,600,000

$400,000 $400,000 $400,000 $400,000 $400,000 $400,000 $1,200,000 $3,600,000

Operating Impacts

325 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 25: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

ROUNDABOUT PROJECTS ST-239Project No:

Submitting Department:

Project Manager:

Public Works

Tom Davy

Project Status: Proposed

Projected Start Date 07/01/2018

Projected Completion Date: 06/30/2026Total Projected Cost: $6,000,000

Prior Years ActualCosts:

Design and construction of roundabouts as an alternative to traffic signals at major intersections.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

To Be Determined $1,500,000 $1,500,000 $1,500,000 $1,500,000 $6,000,000

$1,500,000 $1,500,000 $1,500,000 $1,500,000 $6,000,000

Operating Impacts

326 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 26: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

I-215 REGIONAL TRAIL CONNECTIVITY - GREEN VALLEY TO PECOS ST-241Project No:

Submitting Department:

Project Manager:

Public Works

Kevin Futch

Project Status: Active

Projected Start Date 11/01/2016

Projected Completion Date: 12/31/2018Total Projected Cost: $532,000

Prior Years ActualCosts:

Shared use path along I-215 from Green Valley to Pecos

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $22,000 $22,000

Grants & Contributions (SNPLMA, Fire,

Homeland Security, Police, Parks & Rec,

PW Grants, Private Contributions)

$510,000 $510,000

$532,000 $532,000

Operating Impacts

327 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 27: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

APPALOOSA - WAGONWHEEL TO EQUESTRIAN ST-242Project No:

Submitting Department:

Project Manager:

Public Works

Tom Davy

Project Status: Active

Projected Start Date 06/30/2016

Projected Completion Date: 12/31/2018Total Projected Cost: $884,000

Prior Years ActualCosts:

Curb and gutter, etc. as related to improvements at Appaloosa Storm Drain.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $884,000 $884,000

$884,000 $884,000

Operating Impacts

328 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 28: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

NDOT I-215 TRAIL BRIDGES ST-243Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Active

Projected Start Date 10/01/2016

Projected Completion Date: 01/31/2022Total Projected Cost: $4,513,500

Prior Years ActualCosts:

Pedestrian bridges located along the I-215 regional trail generally located at Pecos, Green Valley and Valle Verde.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Grants & Contributions (SNPLMA, Fire,

Homeland Security, Police, Parks & Rec,

PW Grants, Private Contributions)

$51,500 $377,000 $736,500 $3,200,000 $4,365,000

Regional Transportation Commission $148,500 $148,500

$200,000 $377,000 $736,500 $3,200,000 $4,513,500

Operating Impacts

329 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 29: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

SEVEN HILLS DR. - GRAND HILLS DR. TO ST. ROSE PKWY. ST-245Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Active

Projected Start Date 07/01/2020

Projected Completion Date: 06/30/2022Total Projected Cost: $4,000,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,000,000 $3,000,000 $4,000,000

$1,000,000 $3,000,000 $4,000,000

Operating Impacts

330 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 30: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

HEATHER DR. - GREENWAY RD. TO COLLEGE DR. ST-246Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Active

Projected Start Date 07/01/2018

Projected Completion Date: 06/30/2020Total Projected Cost: $1,500,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $300,000 $1,200,000 $1,500,000

$300,000 $1,200,000 $1,500,000

Operating Impacts

331 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 31: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

FOSTER/PRICE ST. - BOULDER HWY. TO BARRET ST. ST-247Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Active

Projected Start Date 07/01/2018

Projected Completion Date: 06/30/2020Total Projected Cost: $2,500,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $625,000 $1,875,000 $2,500,000

$625,000 $1,875,000 $2,500,000

Operating Impacts

332 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 32: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

GREENWAY ROAD - BOULDER HWY TO PARADISE HILLS DR ST-248Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Active

Projected Start Date 07/01/2018

Projected Completion Date: 06/30/2020Total Projected Cost: $2,700,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $675,000 $2,025,000 $2,700,000

$675,000 $2,025,000 $2,700,000

Operating Impacts

333 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 33: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

WINDMILL LANE - ARROYO GRANDE PKWY TO GREEN VALLEY PKWY ST-249Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Active

Projected Start Date 07/01/2021

Projected Completion Date: 06/30/2023Total Projected Cost: $3,250,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,250,000 $2,000,000 $3,250,000

$1,250,000 $2,000,000 $3,250,000

Operating Impacts

334 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 34: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

APPALOOSA - WAGONWHEEL TO EQUESTRIAN PHASE 2 ST-250Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Proposed

Projected Start Date 07/01/2022

Projected Completion Date: 06/30/2024Total Projected Cost: $3,250,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,250,000 $2,000,000 $3,250,000

$1,250,000 $2,000,000 $3,250,000

Operating Impacts

335 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 35: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

DOWNTOWN HENDERSON COMPLETE STREETS PHASE 2 ST-251Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Proposed

Projected Start Date 07/01/2022

Projected Completion Date: 06/30/2025Total Projected Cost: $7,500,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,500,000 $2,000,000 $4,000,000 $7,500,000

$1,500,000 $2,000,000 $4,000,000 $7,500,000

Operating Impacts

336 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 36: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

WATER STREET - MAJOR AVENUE TO LAKE MEAD PKWY ST-252Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Active

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2019Total Projected Cost: $3,400,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $3,400,000 $3,400,000

$3,400,000 $3,400,000

Operating Impacts

337 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 37: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

PUEBLO BLVD - CONCORD WAY TO LAKE MEAD PKWY ST-255Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Proposed

Projected Start Date 07/01/2025

Projected Completion Date: 06/01/2027Total Projected Cost: $3,100,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $3,100,000 $3,100,000

$3,100,000 $3,100,000

Operating Impacts

338 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 38: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

WAGONWHEEL DRIVE - I-515 TO FOOTHILLS DRIVE ST-257Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Proposed

Projected Start Date 07/01/2019

Projected Completion Date: 06/30/2021Total Projected Cost: $1,750,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $512,100 $1,237,900 $1,750,000

$512,100 $1,237,900 $1,750,000

Operating Impacts

339 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 39: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

CITY OF HENDERSON STREET MAINTENANCE PHASE 1 ST-260Project No:

Submitting Department:

Project Manager:

Public Works

Lance Olson

Project Status: Annual

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2022Total Projected Cost: $16,099,600

Prior Years ActualCosts:

Rd Recons/Rehab/Resurf

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $4,024,900 $4,024,900 $4,024,900 $4,024,900 $16,099,600

$4,024,900 $4,024,900 $4,024,900 $4,024,900 $16,099,600

Operating Impacts

340 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 40: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

VIA NOBILA - LAS VEGAS BLVD TO VIA INSPIRADA ST-263Project No:

Submitting Department:

Project Manager:

Public Works

Tom Davy

Project Status: Active

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2028Total Projected Cost: $4,000,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $4,000,000 $4,000,000

$4,000,000 $4,000,000

Operating Impacts

341 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 41: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

CITY OF HENDERSON STREET MAINTENANCE PHASE 2 ST-270Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Annual

Projected Start Date 07/01/2022

Projected Completion Date: 06/30/2027Total Projected Cost: $20,124,500

Prior Years ActualCosts:

Rd Recons/Rehab/Resurf

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $4,024,900 $4,024,900 $12,074,700 $20,124,500

$4,024,900 $4,024,900 $12,074,700 $20,124,500

Operating Impacts

342 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 42: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

EASTERN AVENUE IMPROVEMENTS PHASE 1 - ST. ROSE PKWY TO I-215 ST-271Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Active

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2019Total Projected Cost: $4,000,000

Prior Years ActualCosts:

Construction of new roadway surface, ADA improvements, traffic signal modifications, pedestrian and bike lane enhancements as appropriate

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,500,000 $2,500,000 $4,000,000

$1,500,000 $2,500,000 $4,000,000

Operating Impacts

343 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 43: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

ST. ROSE PKWY/PECOS ROAD/I-215 INTERCHANGE IMPROVEMENTS - PHASE 1 ST-282Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Proposed

Projected Start Date 07/01/2021

Projected Completion Date: 06/30/2023Total Projected Cost: $6,000,000

Prior Years ActualCosts:

Interchange improvements including rehabilitation of adjacent roadway and appurtenances

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,000,000 $5,000,000 $6,000,000

$1,000,000 $5,000,000 $6,000,000

Operating Impacts

344 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 44: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

VIA INSPIRADA TRAIL - LAS VEGAS BLVD TO EXECUTIVE AIRPORT/VOLUNTEER (NDOT) ST-291Project No:

Submitting Department:

Project Manager:

Public Works

Amie Wojtech

Project Status: Proposed

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2020Total Projected Cost: $782,000

Prior Years ActualCosts:

Trail along Via Inspirada

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $42,000 $42,000

Grants & Contributions (SNPLMA, Fire,

Homeland Security, Police, Parks & Rec,

PW Grants, Private Contributions)

$740,000 $740,000

$740,000 $42,000 $782,000

Operating Impacts

345 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 45: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

BUS TURNOUTS (NDOT FUNDED) ST-293Project No:

Submitting Department:

Project Manager:

Public Works

Tom Davy

Project Status: Proposed

Projected Start Date 10/01/2017

Projected Completion Date: 09/30/2020Total Projected Cost: $657,895

Prior Years ActualCosts:

various bus turnouts throughout the city TBD

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Grants & Contributions (SNPLMA, Fire,

Homeland Security, Police, Parks & Rec,

PW Grants, Private Contributions)

$100,000 $525,000 $625,000

To Be Determined $32,895 $32,895

$100,000 $525,000 $32,895 $657,895

Operating Impacts

346 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 46: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

ROMA HILLS DRIVE ST-298Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Active

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2019Total Projected Cost: $1,500,000

Prior Years ActualCosts:

Traffic calming improvements along Roma Hills Drive

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,500,000 $1,500,000

$1,500,000 $1,500,000

Operating Impacts

347 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 47: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

STEPHANIE ST - I-215 TO DRAGONRIDGE CC ST-299Project No:

Submitting Department:

Project Manager:

Public Works

Scott Fiedler

Project Status: Active

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2019Total Projected Cost: $1,500,000

Prior Years ActualCosts:

road rehab and improvements to Stephanie St

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $1,500,000 $1,500,000

$1,500,000 $1,500,000

Operating Impacts

348 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 48: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

UPRR - ANNUAL INSPECTION AND REPAIRS ST-300Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Annual

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2028Total Projected Cost: $770,000

Prior Years ActualCosts:

Annual inspection and repair of UPRR tracks and related appurtenances.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

To Be Determined $210,000 $70,000 $70,000 $70,000 $70,000 $280,000 $770,000

$210,000 $70,000 $70,000 $70,000 $70,000 $280,000 $770,000

Operating Impacts

349 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 49: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Streets

PACIFIC AVENUE - HORIZON DRIVE TO APIAN WAY ST-302Project No:

Submitting Department:

Project Manager:

Public Works Project Status: Proposed

Projected Start Date 07/01/2019

Projected Completion Date: 06/30/2021Total Projected Cost: $1,000,000

Prior Years ActualCosts:

roadway improvements

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $250,000 $750,000 $1,000,000

$250,000 $750,000 $1,000,000

Operating Impacts

350 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 50: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

GALLERIA DR/WHITNEY RANCH RD SIGNALIZATION TC-047Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez

Project Status: Proposed

Projected Start Date 07/01/2021

Projected Completion Date: 06/30/2022Total Projected Cost: $530,000

Prior Years ActualCosts:

Install traffic signal. Intersection No. 012

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $530,000 $530,000

$530,000 $530,000

Operating Impacts

Maintenance Labor $2,500 $2,600 $19,800 $24,900

Operations Labor $2,500 $2,600 $19,800 $24,900

$49,800 $5,000 $5,200 $39,600

351 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 51: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

MARYLAND PKWY. / SUNRIDGE HEIGHTS PKWY. SIGNALIZATION TC-115Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez

Project Status: Proposed

Projected Start Date 07/03/2018

Projected Completion Date: 06/28/2019Total Projected Cost: $530,000

Prior Years ActualCosts:

Install traffic signal, Intersection No. 205.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $530,000 $530,000

$530,000 $530,000

Operating Impacts

Maintenance Labor $2,414 $2,474 $2,536 $5,263 $12,687

Supplies $2,086 $2,148 $2,213 $4,627 $11,074

$23,761 $4,500 $4,622 $4,749 $9,890

352 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 52: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

SUNRIDGE HEIGHTS PKWY. / EXECUTIVE AIRPORT DR. SIGNALIZATION TC-121Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez

Project Status: Proposed

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2018Total Projected Cost: $530,000

Prior Years ActualCosts:

Install traffic signal, Intersection No. 204.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $530,000 $530,000

$530,000 $530,000

Operating Impacts

Maintenance Labor $2,414 $2,474 $13,779 $18,667

Supplies $2,086 $2,148 $11,820 $16,054

$34,721 $4,500 $4,622 $25,599

353 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 53: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

GREENWAY RD. / MISSION DR. TRAFFIC CONTROL TC-137Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez

Project Status: Proposed

Projected Start Date 07/01/2020

Projected Completion Date: 06/30/2021Total Projected Cost: $530,000

Prior Years ActualCosts:

Install traffic signal, Intersection No. 062.

****This project is going to be completed with ST-248****

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $530,000 $530,000

$530,000 $530,000

Operating Impacts

Maintenance Labor $2,474 $2,536 $2,599 $5,464 $13,073

Supplies $2,148 $2,213 $2,279 $4,748 $11,388

$24,461 $4,622 $4,749 $4,878 $10,212

354 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 54: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

COLLEGE DR. / MISSION DR. TRAFFIC CONTROL TC-138Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriquez

Project Status: Proposed

Projected Start Date 07/01/2020

Projected Completion Date: 06/30/2021Total Projected Cost: $530,000

Prior Years ActualCosts:

Install traffic signal, Intersection No. 049.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $530,000 $530,000

$530,000 $530,000

Operating Impacts

Maintenance Labor $7 $10,273 $10,280

Supplies $8,988 $8,988

$19,268 $7 $19,261

355 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 55: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

DESERT SHADOW TRL. / PASEO VERDE PKWY. SIGNALIZATION TC-178Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez

Project Status: Proposed

Projected Start Date 07/01/2019

Projected Completion Date: 06/30/2021Total Projected Cost: $450,000

Prior Years ActualCosts:

Install traffic signal, Intersection No. 054. FRI Funding

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $150,000 $300,000 $450,000

Developer - Traffic Control

$150,000 $300,000 $450,000

Operating Impacts

Maintenance Labor $2,664 $11,200 $13,864

Supplies $2,348 $9,872 $12,220

$26,084 $5,012 $21,072

356 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 56: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

TRAFFIC SIGN REPLACEMENT PROGRAM TC-183Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez & Luke Smith

Project Status: Annual

Projected Start Date 07/01/2010

Projected Completion Date: 06/30/2030Total Projected Cost: $405,000

Prior Years ActualCosts:

This program is to replace signage in older neighborhoods that no longer meet the current retro-reflectivity standards. This program will include all traffic signs within the identified areas

on an annual basis.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Capital Replacement - PW Traffic $60,000 $30,000 $30,000 $30,000 $30,000 $190,000 $370,000

$60,000 $30,000 $30,000 $30,000 $30,000 $190,000 $370,000

Operating Impacts

357 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 57: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

MISCELLANEOUS STRIPING CONTRACT TC-184Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez or Luke Smith

Project Status: Annual

Projected Start Date 07/01/2009

Projected Completion Date: 06/30/2027Total Projected Cost: $675,000

Prior Years ActualCosts:

Miscellaneous re-striping of roadways throughout City.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Gas Tax - 2.35 Cents $75,000 $75,000 $75,000 $75,000 $75,000 $75,000 $225,000 $675,000

$75,000 $75,000 $75,000 $75,000 $75,000 $75,000 $225,000 $675,000

Operating Impacts

358 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 58: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

CROSSWALK AND LEGEND MAINTENANCE AND MISCELLANEOUS STRIPING TC-198Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez & Luke Smith

Project Status: Annual

Projected Start Date 07/01/2014

Projected Completion Date: 06/30/2029Total Projected Cost: $3,575,000

Prior Years ActualCosts:

Routine maintenance of crosswalk, bike lane, and other pavement markings.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Capital Replacement - PW Traffic $650,000 $325,000 $325,000 $325,000 $325,000 $1,625,000 $3,575,000

$650,000 $325,000 $325,000 $325,000 $325,000 $1,625,000 $3,575,000

Operating Impacts

359 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 59: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

FIBER MAINTENANCE TC-202Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez & Luke Smith

Project Status: Annual

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2029Total Projected Cost: $330,000

Prior Years ActualCosts:

Perform routine maintenance on fiber-optic cabling across the City's traffic network.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Capital Replacement - PW Traffic $60,000 $30,000 $30,000 $30,000 $30,000 $150,000 $330,000

$60,000 $30,000 $30,000 $30,000 $30,000 $150,000 $330,000

Operating Impacts

360 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 60: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

ADA RAMPS AT SIGNALS TC-203Project No:

Submitting Department:

Project Manager:

Public Works

Scott Jarvis

Project Status: Active

Projected Start Date 07/01/2016

Projected Completion Date: 06/30/2024Total Projected Cost: $950,000

Prior Years ActualCosts:

Install ADA ramps compliant to the current standard at various traffic signal intersections.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Capital Replacement - PW Traffic $200,000 $50,000 $50,000 $325,000 $325,000 $950,000

$200,000 $50,000 $50,000 $325,000 $325,000 $950,000

Operating Impacts

361 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 61: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

RAILROAD REPAIRS TC-204Project No:

Submitting Department:

Project Manager:

Public Works

Luke Smith

Project Status: Proposed

Projected Start Date 07/01/2015

Projected Completion Date: 06/30/2024Total Projected Cost: $2,200,000

Prior Years ActualCosts:

Various repairs to City-owned sections of railroad.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

To Be Determined $600,000 $200,000 $200,000 $200,000 $200,000 $800,000 $2,200,000

$600,000 $200,000 $200,000 $200,000 $200,000 $800,000 $2,200,000

Operating Impacts

362 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 62: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

LANE AND BIKE LANE RESTRIPING- VARIOUS LOCATIONS TC-213Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez & Luke Smith

Project Status: Annual

Projected Start Date 07/01/2015

Projected Completion Date: 06/30/2030Total Projected Cost: $900,000

Prior Years ActualCosts:

Lane and bike lane restriping

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Capital Replacement - PW Traffic $200,000 $100,000 $100,000 $100,000 $100,000 $300,000 $900,000

$200,000 $100,000 $100,000 $100,000 $100,000 $300,000 $900,000

Operating Impacts

363 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 63: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

EASTERN AVE TRAFFIC SIGNALS - AT PECOS RIDGE AND ANTHONY COURT TC-214Project No:

Submitting Department:

Project Manager:

Public Works

Ed McGuire/ Alyssa Rodriguez

Project Status: Proposed

Projected Start Date 07/01/2018

Projected Completion Date: 06/30/2019Total Projected Cost: $750,000

Prior Years ActualCosts:

(2) Traffic Signals: Eastern Ave at Peco Ridge and an off-set T- traffic signal at Summit Grove and Anthony Court.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $750,000 $750,000

$750,000 $750,000

Operating Impacts

Maintenance Labor $4,200 $4,500 $4,800 $5,200 $5,500 $18,500 $42,700

Operations Labor $4,200 $4,200 $4,200 $5,200 $5,200 $17,900 $40,900

$83,600 $8,400 $8,700 $9,000 $10,400 $10,700 $36,400

364 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 64: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

GIBSON/WIGWAM TRAFFIC SIGNAL TC-216Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez

Project Status: Active

Projected Start Date 07/01/2018

Projected Completion Date: 06/30/2019Total Projected Cost: $550,000

Prior Years ActualCosts:

Remove existing median in intersection and construct signal improvements at the intersection of Gibson and Wigwam. Int. 127.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Regional Transportation Commission $550,000 $550,000

$550,000 $550,000

Operating Impacts

Operations Labor $2,500 $2,500 $2,500 $2,500 $2,500 $10,000 $22,500

Maintenance Labor $2,500 $2,500 $2,500 $2,500 $2,500 $10,000 $22,500

$45,000 $5,000 $5,000 $5,000 $5,000 $5,000 $20,000

365 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 65: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

PEDESTRIAN CROSSWALK ENHANCEMENTS- VARIOUS LOCATIONS TC-217Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez

Project Status: Active

Projected Start Date 07/01/2016

Projected Completion Date: 06/30/2020Total Projected Cost: $855,000

Prior Years ActualCosts:

There are approximately 50 locations within the City needing pedestrian activated flashers either Rectangular Rapid Flashing Beacon's or Hawk signal.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

NDOT Funding

Developer - Traffic Control $585,000 $270,000 $855,000

Regional Transportation Commission

$585,000 $270,000 $855,000

Operating Impacts

366 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 66: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

UPRR - SIGNALS AND CROSSMARKINGS TC-219Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez

Project Status: Annual

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2028Total Projected Cost: $880,000

Prior Years ActualCosts:

Annual maintenance to the UPRR signals and cross markings.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

To Be Determined $240,000 $80,000 $80,000 $80,000 $80,000 $320,000 $880,000

$240,000 $80,000 $80,000 $80,000 $80,000 $320,000 $880,000

Operating Impacts

367 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 67: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

City of Henderson

Projects by Program

2018/19 - 2023/24 Capital Improvement Program

Transportation Traffic Control

SIGNAL REPLACEMENT & UPGRADES - BOULDER/WAGONWHEEL TC-220Project No:

Submitting Department:

Project Manager:

Public Works

Alyssa Rodriguez

Project Status: Proposed

Projected Start Date 07/01/2017

Projected Completion Date: 06/30/2018Total Projected Cost: $900,000

Prior Years ActualCosts:

Replacement of foundations, signal poles and signal arms to meet current specifications. Replace deteriorated wire.

Project Description:

Funding Sources Total 2018/19 2019/20 2020/21 2021/22 2022/23 2023/24 Future

Gas Tax - 1% Room Tax $900,000 $900,000

$900,000 $900,000

Operating Impacts

Notes:

368 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

Page 68: 2018/19 - 2023/24 Capital Improvement Program … · City of Henderson Projects by Program 2018/19 - 2023/24 Capital Improvement Program Transportation Street Lights ... Scott Jarvis

369 Cycle:FY2019-2024 Capital Plan Scenario:Cycle 2019-2024 Scenario Program: Transportation SubProgram: All SubPrograms

This page intentionally left blank