Unpacking and Installation of Micro Powder Grinding Mill Unpacking: For the convenience of long distance transportation, the whole set of grinding mill breaks down into its component parts. Please check the below points upon receipt of equipment: Check if the model and specification are same as you ordered Check the packages according to the packing list offered Please contact with our company within one week if have any problems about our products. Installation environment Good ventilation condition in workshop Foundation handling refer to related foundation drawing Foundation treatment: 1) Excavate the foundation according to foundation drawing, and tamp town the bottom layer. 2) Add a layer of concrete cushion, and make it smooth. 3) Measure the positions of the preformed holes (openings) for main unit, reducer, bucket elevator, hammer crusher, and make marks separately on the cushion. Make PVC pipes or logs according to the diameter and depth of preformed holes, then fix them with reinforcing steel bar and keep PVC pipes or logs vertical. 4) Set reinforcing steel bars on the foundations of main unit, reducer and crusher. Place concrete; make sure the crusher chute even and smooth. 5) After 12 hours of concrete placement, take out PVC pipes or logs. Double check if the size of the preformed holes (openings) is accurate to dimensions in the foundation drawing. ( Make sure the inner wall of preformed holes (openings) roughens the inner wall in order to connect well with second pouring process.) 6) Make chutes on the top of preformed holes for easy second-pouring of concrete. 7) Build the inner wall of bucket elevator pit by pouring concrete where the groundwater level is high to prevent water from seeping into the pit through the walls. Installation: Please follow the below instructions before installation: 1) Check if all the equipment parts are in good condition before installation, particularly check driving mediums for damage or breakage, inspect installed and welded parts for out pf shape, check fasteners in the component parts if they get loose. 2) Check to ensure there aren’t any screws, nuts and tools in the grinding mill. 3) When connecting inlet and outlet pipes, the flanges should be paralleled and fitted well. Asbestors cords should be used to keep airproof at the connecting point. 4) All fasteners and connecting pieces should be fastened well. 5) Seal bolts connections using sealants. 6) The cables shall meet the requirements of every motor rated current.

Upload: zhao-jessie

Post on 22-Jan-2018

73 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: 20150129 micro powder grinding mill

Unpacking and Installation of Micro Powder Grinding Mill

Unpacking:

For the convenience of long distance transportation, the whole set of grinding mill breaks down

into its component parts. Please check the below points upon receipt of equipment:

Check if the model and specification are same as you ordered

Check the packages according to the packing list offered

Please contact with our company within one week if have any problems about our products.

Installation environment

Good ventilation condition in workshop

Foundation handling refer to related foundation drawing

Foundation treatment:

1) Excavate the foundation according to foundation drawing, and tamp town the bottom layer.

2) Add a layer of concrete cushion, and make it smooth.

3) Measure the positions of the preformed holes (openings) for main unit, reducer, bucket elevator,

hammer crusher, and make marks separately on the cushion. Make PVC pipes or logs according to

the diameter and depth of preformed holes, then fix them with reinforcing steel bar and keep PVC

pipes or logs vertical.

4) Set reinforcing steel bars on the foundations of main unit, reducer and crusher. Place concrete;

make sure the crusher chute even and smooth.

5) After 12 hours of concrete placement, take out PVC pipes or logs. Double check if the size of

the preformed holes (openings) is accurate to dimensions in the foundation drawing. ( Make sure

the inner wall of preformed holes (openings) roughens the inner wall in order to connect well with

second pouring process.)

6) Make chutes on the top of preformed holes for easy second-pouring of concrete.

7) Build the inner wall of bucket elevator pit by pouring concrete where the groundwater level is

high to prevent water from seeping into the pit through the walls.

Installation:

Please follow the below instructions before installation:

1) Check if all the equipment parts are in good condition before installation, particularly check

driving mediums for damage or breakage, inspect installed and welded parts for out pf shape,

check fasteners in the component parts if they get loose.

2) Check to ensure there aren’t any screws, nuts and tools in the grinding mill.

3) When connecting inlet and outlet pipes, the flanges should be paralleled and fitted well.

Asbestors cords should be used to keep airproof at the connecting point.

4) All fasteners and connecting pieces should be fastened well.

5) Seal bolts connections using sealants.

6) The cables shall meet the requirements of every motor rated current.