    Ithaca Commons Repair & Upgrade Project C#3A Surface, C#3B Electric

    Date Start End Next Date Next Time Prepared By09/23/2014 11:00 AM 12:00 PM 09/30/2014 10:00 AM Nicole Mason / Jess Buckley

    Purpose Location

    2014 Construction Meeting #27 Commons Project Office 215 East State St Ithaca, NY

    Distribution/Attendance: (Present at meeting unless noted: A absent)

    City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason

    Downtown Ithaca Alliance Tammy Baker

    Sasaki Associates Susannah Ross, Eamonn Hutton (A), Kimberly Michaels (A) TWM

    Labella Associates Dan Walker, James Matzat (A)

    Vacri Construction / ACP / Ralph Avery (A), Andy Breznay, Matt Thomas (A), Roberto DeVincentis,

    Bob Bellavigna (A), Ken Height ACP

    Power & Construction Group Lou Zupan (A), Bill Planert

    Verizon Gloria Moran (A), Jeff Utter (A)

    NYSEG Gas Doug Stafford (A), Jack Barker (A), Dawn Stillwell (A), John Mattiace (A)

    DDS Jeff Bubb (A), Flint Brann (A)

    NYSEG Electric Jack Czapranski (A), Dennis Kuhn (A)

    Item / Description Notes Due

    1.

    RFIs, SUBMITTALS

    1.1.

    Vacri (Contract #3A):

    1.1.1.

    Structural Soil (#90R2): Vacri to

    update on status of re-submittal;

    Need delivery of material for State

    Street 9/29/14

    1.1.2.

    Topsoil (#104R2): Sasaki reviewed

    9/15; Must be mixed with other

    components to form Planting Soil

    per spec

    1.1.3.

    Gateway (#106, #114a/b): Vacri to

    advise on schedule for delivery

    1.1.4.

    Play Benches (#117): Vacri issued

    9/17/14; Sasaki to review1.1.5.

    Trolley Circle Sculpture: Vacri to

    submit sample of etched paver for

    Sasaki to review

    1.1.6.

    Bronze Inlays: Vacri to provide

    submittal for bronze play pieces

    1.1.7.

    Etched Pavers (Play Pieces): Sasaki

    waiting for Hanover sample

    1.1.1 Last test was Sand 23.6%. Silt 47.6%

    pH 6.8 organic 3.87% Clay 18.8%

    (minimum spec is 20%). Vacri will order

    40 CY for Bank Alley green screen area

    and submit current mix to document

    exactly what it is. M Kuo approved

    pulling back structural soil limits from

    next to the northern seat wall so

    concrete pour is not held up tomorrow.

    Pogo said they now have all the

    components for the mix that meets every

    spec believe that they have a good

    source of clay, they are waiting for anutrient test.

    1.1.2 Going to get each component

    approved and then mix it to spec. Need

    to submit on mix as well as components.

    MEETING MINUTES

  • 8/10/2019 2014-09-23 Construction Meeting Minutes.pdf

    2/4

    Page 2of 4

    1.2.

    P&CG (Contract #3B):

    1.2.1.

    Bollards Components (#18R1):

    Reviewed by Sasaki 9/22/14

    1.2.2.

    Catenary Cabling (#22, RFI#24):

    Material vendor/manufacturer

    approved; PCG to submit shop

    drawings

    1.2.3.

    EX6 Cable (TBD): PCG to submit

    shielded cable for City Electrical

    Inspector to review

    1.2.1 Expect shop drawing for cabling

    tomorrow.

    1.2.3 Electrician to coordinate on getting

    shielded cable for inspector.

    2. DESIGN, FIELD DIRECTIVES

    2.1.

    Bulletin 21 (140 E State Storm Lateral):

    Issued 8/29/2014; Vacri to provide cost

    estimate

    2.2.

    Bulletin 22 (Benchwarmers Vault):

    Property owner to block up wall; Vacri to

    backfill and demo existing walls when

    work progresses to this area

    Vacri to demo and backfill vault on T&M

    2.3.

    Aurora/Cayuga Kiosk Pad: Kiosk pad for

    Cayuga and Aurora to be 2 wider for

    parking pay station; run conduit for

    power to pay station

    Sasaki is to issue bulletin. PCG will run

    spare conduit in case of future use to

    the pay station.

    2.4.

    HH-2, HH-3: Relocate HHs to allow PCG

    to complete DB to LP-1A/1B; Avoid

    conflict with gateway footer

    Ithaca team to propose locations to

    Sasaki.

    2.5.

    Weeps: Need to finalize spacing and size

    of weeps; weeps to be packed with stone

    and covered with landscaping fabric

    ACP is concerned about installing weeps

    close to expansion joint. Joint is at lowest

    point next expansion joint before slot

    drains.2.6.

    Expansion Joints: Sasaki to comment on

    using fibre in lieu of cork

    Sasakis preference is cork however MK

    approved use of fiber for increased speed

    and ease of installation

    2.7.

    Slot Drain Slab #3/DT511: Sasaki to

    comment on revised detail as installed

    behind Yellowwoods

    ACP has 3 pavers ordered already.

    Sasaki to review modified detail with

    ACO and respond on acceptability.

    3.

    CRITICAL PATH ITEMS

    3.1.

    Bank Alley

    3.1.1.

    Granite Curb & Seat Walls: AC+P to

    provide delivery date

    3.1.2.

    Planter Curbs: Excess concrete hasbeen removed; KM to visit site

    9/23/14 to confirm number and

    layout of trees

    3.1.3.

    Gas Valve Adjustments: Vacri to

    coordinate with NYSEG G

    3.1.4.

    Waterproofing 202: Property owner

    ok with specd material previously

    3.1.1 Pouring up to the pavilion today,

    finish slab in middle next week, seat walls

    Oct 13, curbing Oct 20, setting the pavers

    by Oct 27, through Nov 17.200 block: concrete slab and footings by

    Oct 13.

    3.1.5 Sasaki to request a specific location

    for paving mock-up on southern Bank

    Alley.

    3.1.7 Sasaki to look at which is preferred

    location with Kim. Vacris surveyor

  • 8/10/2019 2014-09-23 Construction Meeting Minutes.pdf

    3/4

    Page 3of 4

    used; MM advised that protection

    course must be used on top of

    membrane

    3.1.5.

    Paving Mock-Up: Sasaki to select 8

    x 8 area on Bank Alley for mock-up

    3.1.6.

    Planting Soil: Vacri to provide

    remaining material mix (see

    Submittals)

    3.1.7.

    Greenscreen: Location of

    greenscreen (centered in planting

    bed or offset to east) see PP103

    layout vs. Detail #4/PP104; when to

    install footings

    3.1.8.

    Structural Steel: Vacri to provide

    installation start date

    3.1.9.

    Lighting: PCG to install EX3, EX4

    when steel installed; EX2 to be

    delivered 10/31; EX6 to be installedwhen granite delivered

    currently laying out location close to

    property line with plants on west side of

    screen.

    3.1.8 Vacri thinks steel will be ready the

    first week in October but may not have

    area complete for install until end of

    October. PCGs schedule is to pull wire at

    the end of October.

    3.2.

    200 Block

    3.2.1.

    Light Poles: PCG sent letter to NYSEG

    9/16/14; NYSEG G to remove all

    conflicts within 20 of C/L light pole

    on 9/24/14; PCG started augering

    yesterday; had to replace 24 casing

    with 25 casing

    3.2.2.

    Bollards: 4 of 5 bollard bases

    installed; will complete after

    gateway footing is backfilled3.2.3.

    Gateways: AC+P installed #4 rebar

    for uprights instead of #8; DE to

    review and advise on detail for

    supplemental reinforcing

    3.2.4.

    Signals Project Coordination: Electric

    feed to NYSEG vault at Aurora

    completed 9/23/14; Signals and

    streetlights need power; Start date

    for work at intersection?

    3.2.1 NYSEG will be here tomorrow to cut

    out old gas main. PCG to expose lengths of

    pipe in preparation. Vacri will be ready to

    install structural soil next Monday; light

    poles are to be installed prior to Monday

    so not to delay finish work.

    3.2.4 Signals project will be completed

    11/15.

    3.3.

    Home Dairy Alley: Vacri to start 9/25/14;

    Coordinate access through Center Ithaca

    and Mate Factor

    Starting at the South side of the alley and

    move north to keep truck access from

    Commons. Will start on Thursday. DIA to

    find place to store announcement panels.

    3.4.

    Trench Drains: Vacri to confirm with ACO

    that channels shipped for job will

    maintain warranty; Vacri to confirm if

    protruding connecting pipe will conflict

    with pavers

    4.

    M&PTP: MAINTENANCE & PROTECTION