    Ithaca Commons Repair & Upgrade Project C#2 Utilities, C#3A Surface, C#3B Electric

    Date Start End Next Date Next Time Prepared By05/20/2014 10:00 AM 11:00 AM 05/27/2014 10:00 AM Jessica Buckley

    Purpose Location

    2014 Construction Meeting #8 Commons Project Office215 East State St Ithaca, NY

    Distribution/Attendance: (Present at meeting unless noted: Aabsent)

    City of Ithaca Michael Kuo, Jessica Buckley, Nicole Mason

    Downtown Ithaca Alliance Tammy Baker

    Sasaki Associates Susannah Ross (A), Eamonn Hutton (A)

    Labella Associates Dan Walker, James Matzat (A)

    Vacri Construction / ACP Ralph Avery, Andy Breznay, Matt Thomas (A), Roberto DeVincentis (A),

    Bob Belavigna - ACP

    Power & Construction Group Lou Zupan, Bill Planert (A), Brian Planert (A)

    Verizon James Edwards (A), Dave Comer (A)

    NYSEG Gas Doug Stafford (A), Jack Barker (A), Dawn Stillwell

    DDS Jeff Bubb (A), Flint Brann

    NYSEG Electric Jack Czapranski, Dennis Kuhn (A)

    Item / Description Notes Due

    1.

    SITE MANAGEMENT

    1.1.

    Thank you for being aware of site

    sensitivities: Pedestrian access,

    emergency access, business owner

    requests, fence / safety maintenance,

    coordinating with each other, etc.

    1.2.

    Meeting of the Minds: Optional

    superintendant daily meeting at 3:00 PM

    at project office to map out work

    footprint & coordinate with others on site

    MK: Mandatory 10 minute meeting at

    Trolley Circle at 3:00 PM

    1.3.

    Lockout Tagout procedures to be put in

    place by Vacri for temp lighting electric

    panel

    Vacri to issue procedure to be distributed

    by the project office

    1.4.

    Notify JB of any storm pipe removal GiveVacri24 hours to schedule Action

    Cleaners & Cityto schedule Microbac

    1.5.

    Vacriis to schedule temp paving of

    trenches prior to the end of the week for

    Cornell graduation

    Vacri to do temp paving 05/22 05/23

    1.6.

    Lights out on N TiogaVacri to

    investigate

    2. CRICTIAL PATH ITEMS

    MEETING MINUTES

  • 8/10/2019 2014-05-20 Construction Meeting Minutes.pdf

    2/3

    Page 2of 3

    2.1. P&CG: Status of lighting submittal; City /

    Architect to respond to cat. light pole /

    Verizon DB conflict; N Tioga field directive

    Cityto follow up on cat lighting; FD to

    issue directive on electrical N Tioga 5/20

    2.2.

    Vacri: TTC alley storm field directive from

    Engineer / Architect to be issued, Verizon

    / Danella to be scheduled to expose

    conduit prior to storm work

    LaBella/Sasaki to issue FD 05/20; JBto

    schedule Verizonto hammer out DB in

    alley 05/21; Vacrito install storm 05/22

    05/23; EE Root scheduled to re-install

    cable into HH in alley 05/27

    2.3.

    Vacri: Water feature rough in to be issued

    by Architect pending response from

    water treatment plant / health

    department

    City to clarify vault spec;

    2.4.

    Vacri: City to determine vault infill at 119 MK & ABto observe vault w/ MM

    (LaBella)

    3.

    SCHEDULE

    3.1.

    NYSEG Gas/DDS: Tentative schedule to

    be presented

    05/27 05/28 Crossing at Cayuga St; Fire

    access to be down the center; Schedule

    service crews for mid June; NYSEGs crew

    is to complete 7 services, DDS all others;

    Predict 1-2 services per day

    3.2.

    NYSEG Electric to complete relocation of

    secondary to Aurora St by 05/23

    05/21 Vault (30x 30)installation

    pending storm progress in alley; Aurora St

    to be opened 05/27;P&CG to complete

    diagonals by 05/27

    3.3.

    Vacri / AC&P:

    May: Complete utilities (Storm)

    June: N TiogaSite demo; Pour

    foundations / footers; Site grading, curbs,

    expansion jointsJuly:Prep & pour slab N Tioga; Paving

    program

    Vacri to take a crew off site; Vacri

    excavate footers for ACP; City & Vacrito

    review remaining Contract 2 work; DDS

    requested ABto mark out gateway footers

    prior to 05/27

    3.4.

    TTC / EE Root: Scheduled to reinstall

    cable into TTC Alley HH 05/27; Lantechto

    install separator in TMH-4

    See Item 2.2

    3.5. Verizon / Danella:

    05/20: To work alongside NYSEG E at

    Trolley Circle crossing to lower DB for WF

    TTC Alley work to be scheduled

    Danella to be scheduled to work in TTC

    Alley 05/21

    3.6.

    P&CG:

    05/20:Realigned at NW corner of 100block moving east

    05/19 06/16:Complete N Tioga

    Vacri & P&CG to determine installation of

    conduit to gateways

    3.7.

    Asphalt Restoration: Vacri, NYSEG Gas&

    Signals project (P&CG)to coordinate in

    intersections

    4.

    M&PTP: MAINTENANCE & PROTECTION

    OF TRAFFIC & PEDESTRIANS

  • 8/10/2019 2014-05-20 Construction Meeting Minutes.pdf

    3/3

    Page 3of 3

    4.1. Vacri / ACP, P&CG, NYSEG Gas: Please

    submit typical ped. traffic M&P plan,

    include list of signage available on site

    5/27

    4.2.

    Vacri to propose sidewalk demo plan Sidewalk demo sequence in N Tioga is

    priority

    5.

    New Business: Open RFIs, submittals,concerns, etc. Cityrequest Granite submittal fromVacri/ACP

    5.1. Vacri concerned about valve boxes & site

    settlement

    All contractors to keep track of valve

    boxes; DDSto continue use jumping jack;

    Crusher run used to backfill; DDSto

    submit all backfill material proctor

    DATES TO REMEMBER

    May 23 to May 25Cornell Graduation, no work on weekend

    May 30 to June 1Ithacafest, Cayuga St entrance closed

    ADDITIONAL NOTES

    3.1 Map of tentative NYSEG Gas schedule was available in meeting